Jump to content

Blogs

Roofing a flat roof

Our flat roof guys have been great.  Though they worked very short hours compared to MBC (doesn't everyone).   With a flat roof you apparently need at least 18mm OSB to lay the roof membrane onto.  The standard MBC spec is less than that for a flat roof so we had to stump up some money to upgrade the roof deck to 18mm.   We have three different roof decks.  Here is one roof deck with the roof lights (more on those in a separate post one day).     The upper roof

Weebles

Weebles

Driven to the edge

I am a very strong person, I don’t usually let things get me down, If I think it’s at all possible to do something myself I don’t ask for help, not even from hubby, some of the things I’ve done many a woman wouldn’t even know about never mind know how to do but these last few weeks have broken me. After the major problem with our electricity supply which I managed to sort out I didn’t think it could get any worse but things are all just getting on top of me now to the point where I have cried to

recoveringbuilder

recoveringbuilder

I don't care what the weather man says.....

....if the weather man says it's raining!  So goes the old song and me, too, by the end of this week.  The roof itself has been watertight for a couple of weeks now, but there was still significant water ingress from the gulleys hidden behind the parapets formed at the top of the ground floor.  However, my flat roof guys have been back on site this week and are working hard.  Today they were finishing off the long, east facing balcony and also moving onto the south facing parapet; they will cont

vivienz

vivienz

Tender does it....!

I received the tender documents from the Architect last Friday, about 4 weeks later than I'd hoped. Still it had around 12 documents and a cover letter for me to absorb and read over the weekend. They provided all the details the builders need to price the job which is a lot of detail, wall makeup, foundation and roof elements and I finally get a preview of different cross sections of the house. They provided a window and door schedule, room elevations including a design for the kitchen, utility

mike2016

mike2016

The Build - Now on notice !

Blimey another month on there is a real sense we are getting there. So much so, we have given notice on our rental. We move in on Friday 30th November regardless!   The main emphasis this month has been installing the treatment plant and drainage system. The treatment plant was initially installed, somewhat optimistically, without any anchors only for it to pop back out of the ground within 24hrs, despite being filled with water and the pit filled with pea shingle. Needless to say the

Redoctober

Redoctober

Today we went to meet the Planners...

Some things are irresistable.   This prescient 1903 painting by C. M. Coolidge shows Planning Consultants meeting the Council, even though it is supposedly called "A Friend in Need".     With apologies to any highbrow art people on the forum ... this is very much the 1890s version of the Jack Vettriano niche.    

Ferdinand

Ferdinand

Guttering

In our last blog entry we completed the roof.   Guttering was one of those areas in the build that I had never really given much thought to. After doing some research, and asking on here, we came across cast iron effect guttering from Brett Martin. Unfortunately the lead time to get the guttering to Skye was quite long (3-4 weeks). When the outlets and fascias finally arrived, the actual guttering was missing having been lost in transit. We had to order it again, waiting another three

Thedreamer

Thedreamer

Are they doing it on purpose!!!

So 16 days ago the builder said he had a weeks worth of work to do, 16 days later he still has, the electricity connection is happening this week and we’ve told them once there is power we’re in but it doesn’t seem to make any difference to them, the plumber said today when I told him our plans, do you really think this will happen, short answer- yes you lot are not forcing me into staying in this caravan any longer my furniture is coming home next Thursday and once it’s here there’s no builders

recoveringbuilder

recoveringbuilder

Electricity burial

No, I haven't managed to sneakily bury the wayleave officer somewhere on site!  This post is for the other electricity cable on my site, namely the one that directly supplied the previous building and will supply the new one.  This comes onto the site via an overhead cable and a post and stay that are very close to the new building.  Entirely safe but very ugly and certainly won't fit in with the lovely garden that we're planning. So, from the outset, we've planned to bury this supply as much as

vivienz

vivienz

Before...

So a few snaps from Google Earth of the before images - these may be the current images also for a few months. of course Google does mangle the views and the walls are straighter than they appear!  

Adam2

Adam2

Ooops (anyone need a window?)

So going on holiday in the middle of your build is not ideal.  Best laid plans and all that.  Holiday booked a year previously.  With extended family so couldn't avoid it.  House build delayed by lots of things.  Resulting in our holiday being slap bang in the middle of the timber frame construction.   Reluctantly we left for northern France, asking the build team at MBC to send photos.  They didn't.  [But a friend did, so we knew it was all going up] The problem is that we didn't

Weebles

Weebles

Blink and you miss it (MBC timber frame goes up)

Using a timber frame company (such as MBC) made the frame erection stage of self building quite satisfying.  It only took two weeks to build something that truly looked like a real house.   We did spend more than 7 months in dialogue with MBC over all the little details.  And still we made some quite clanging errors.  More of that in my next post.   It was glorious weather back in July.  [How I wish we weren't in rainy autumn now - we are still not watertight......]  

Weebles

Weebles

That's alot of polystyrene

MBC arrived on site, laid Type 1 and soil pipes pretty quickly and 50mm sand blinding and then set to constructing the EPS raft that is now our slab.  Its been said many times on this site, but I will say it again.  These guys work hard.  They arrived before 7am each day and left at 6pm or later each night.  They hardly stopped.  And after a week it was assembled.  Ready for concrete.                

Weebles

Weebles

Foundation - how deep shall we dig?

The SE suggested digging 900mm deep because the soil survey said we had clay.  And we have trees. I used the NHBC foundation depth calculator and did alot of reading around foundation digs.  Overthinking it all, alot. BC said to dig to 700mm and see what was there.  Guess what?  No clay (well, only a tiny patch amongst loads of gravel). So the SE suggested a new depth of 200mm.  But we are already at 700mm I said.  No problem he said.  Fill it back in, with crushed concrete and th

Weebles

Weebles

Demolition part 2

From this     To this       The demolition guys worked alarmingly slowly.  They didn't bring any machinery in until late on when the slab needed to be dug up.  Unbelievably they were loading the skips by hand, brick by brick, concrete lump by lump.  Anyway, we ended up a bit behind schedule due to them taking 3 weeks longer than planned.   If we were ever going to do this again, which we are not, we would know better.  I would drive a digger into

Weebles

Weebles

Demolition

So, as I am backdating this blog by 6 months I need to catch up quickly.  I covered alot of our demolition in other posts due to the asbestos issues.   The bungalow was encased in plastic sheeting and over the course of three weeks amosite asbestos was removed from the soffits, chrysotile asbestos from the roof tile edging and from inside every internal wall.  We left this job to the professionals and were pleased to do so.  It whacked up the cost of our demolition by about £20K in the

Weebles

Weebles

Our new home

Back in March our new home arrived.     Manoeuvring it into place took more time than we possibly imagined.     And we looked at our snow covered new home from the relative warmth of our 1960s flat pack bungalow and wondered if it was too late to turn back.     Thanks to fellow buildhubbers we got it safely hooked up to gas.  Thanks to You Tube we got it levelled.  Thanks to him indoors it got all plumbed in to mains drainage.  We moved

Weebles

Weebles

Wonky wall update

A brief update on my inward leaning gable that I posted about recently.  Just to recap, I spotted that the gable section of my west facing bedroom wall was leaning inward at an angle and made it look as though there was a problem with the window, which turned out not to be the case.   Over the last couple of days I've been liaising with my timber frame company, MBC, and my window company, Norrsken, to see what needs to be done.  I've taken plenty of photos to illustrate the problem and

vivienz

vivienz

Not so square after all

It's been a little quiet on site over the last 10 days or so which hasn't been a bad thing as I had a nasty cold last week so it gave me an added incentive to stay at home and get some more forward planning done.  One of the downsides, though, is that I only today spotted an issue with the west facing upstairs gable that's only really visible from the top scaffolding lift.   When I first saw it, I thought 'oh bugger, another window problem' and promptly got on the phone to the guys at

vivienz

vivienz

The Build - Nearly done!!

Yes it seems the main phrase for our build currently, is "nearly done" -  As much as September seemed to be a frustratingly slow month progress wise, I am optimistic that we shall see things all come together during October allowing us to move in for November !! Having said that when I look back on the photos that I had taken, quite a bit of progress had indeed been achieved. It is easy to lose sight of such things when you are in the thick of it on a daily basis.   The upstairs i

Redoctober

Redoctober

So near but so far away

That’s exactly what it feels like! Builders have said they have a weeks worth of jobs to do, there’s been a hold up with the staircase, nobody signed it off, the architect came out and did all the calcs and I asked him to contact staircase firm with them, at the same time I emailed them and told them architect was going to contact them but I did feel they needed a visit to see what they were dealing with, this was on August 29th , they never answered me and I took it all was in hand, however I d

recoveringbuilder

recoveringbuilder

×
×
  • Create New...