ETC
Members-
Posts
1654 -
Joined
-
Last visited
-
Days Won
9
Everything posted by ETC
-
Raised Patio & Building Control/Safety
ETC replied to Jimbo37's topic in Landscaping, Decking & Patios
- 18 replies
-
- 1
-
-
- raised patio
- external steps
-
(and 1 more)
Tagged with:
-
Building Control Inspector Changes Previously Approved Inspections
ETC replied to Dabooj80's topic in Building Regulations
Of course it does. It’s certainly not a good reflection of BCOs. -
Building Control Inspector Changes Previously Approved Inspections
ETC replied to Dabooj80's topic in Building Regulations
In my experience: While BC won’t ask for as-built drawings - but if changes are noted on site BC - for example to structural steelwork - BC will ask for updated design information from the SE including calculations. Rarely ask for as-built drainage or as-built cladding specification but will check what has been built on site and if found to be completely different - fire safety or thermal performance for example - will ask for amended information to be submitted. -
Building Control Inspector Changes Previously Approved Inspections
ETC replied to Dabooj80's topic in Building Regulations
Technically BC - certainly here in NI - do not give stage approval and as the old song goes - it’s not over until the fat lady sings. That is to say the works are not approved until the Completion Certificate is issued and if a BCO does see something on a further inspection that doesn’t appear correct it can be picked up. It’s not fair and it stinks of incompetency by both the original and subsequent BCO. Having said all that it’s very bad form for an inspector to re-inspect works previously inspected by a colleague. Why someone would want to give themselves extra work to do is beyond me. When inspecting steelwork BCO will normally compare what is on site with what has been designed by the SE. If something on site looks odd or off it’s flagged up with the applicant but again in this case it would need to have been very much off or looked ver odd for the original surveyor to miss it and for the next surveyor to pick it up. Same thing with the drainage. I’m sorry - and even though it sounds absurd - I’d do whatever the second surveyor asks for. To do anything else you’d be flogging a dead horse and giving yourself additional stress. I would however ask the second inspector why these things weren’t picked up originally and let him know that the process has had a financial implication for your project. -
Building Control Inspector Changes Previously Approved Inspections
ETC replied to Dabooj80's topic in Building Regulations
Really? The paperwork needed to reflect what was built - why? -
Can you post a couple of pictures?
-
In the sketch any water hitting the house wrap will come into the extension.
-
The sketch doesn’t seem to tie up with the photograph. The battens in the photograph project over the blockwork below. Or have I missed something?
-
The 100mm floor difference is to stop liquid fuel entering the house from the garage. If you haven’t got the height either put a concrete lintel at the door or an ACO drain.
-
While there may be thermal bridging issues trickle vents should have been installed for background ventilation and may have helped with reducing mould build up.
-
What’s your problems? Sounds like you have it figured out. Door needs to be 1/2HRFR with a self closer and can open into the garage. If you’ve got 100mm floor difference you’re home in a boat. I wouldn’t be to too worried about the door width either tbh. Speak to your local BCO - you might be surprised.
-
Insulating our attic trusses
ETC replied to Barryscotland's topic in Lofts, Dormers & Loft Conversions
I’d normally expect to see a minimum of 100mm PIR between the rafters an a minimum of 62.5mm insulated plasterboard under the rafters. I’d forget about the “walls” and insulate right down to the eaves and overlap with the wall insulation. Don’t forget you will need 25mm eaves ventilation (Glidevale FV250 or other equal) and 5mm ridge ventilation. If you intend to make the first floor habitable don’t forget about FR and sound resistance to the intermediate floor. You will also need 22mm plywood flooring (which should extend to the eaves) and 10kg/m2 plasterboard to the ground floor ceiling as well as 100mm of sound insulation - 10kgm3 - between the floor joists. 450mm mineral wool insulation above the flat ceiling will be fine - I normally see 300mm. Looking at your photograph I’d also expect to see diagonal bracing to the roof and chevron bracing rather than diagonal bracing to the uprights as well as a bit more longitudinal bracing. Perhaps this was taken before the trusses were complete? Are your trusses cut in the middle? Looks strange. -
Not a great detail. Tricky to get right on site especially if you need radon protection. There are other simpler ways of doing this. Visqueen do a set of details which uses a combined DPM/radon barrier.
-
What are your thoughts on this project estimate?
ETC replied to James Frome's topic in Costing & Estimating
I think you need to get a handle on what professional services you are being provided with for the fee you are paying/have paid if you haven’t already done so. I presume you have a contract for services and an itemised cost of the professional services provided? Apologies - I am presuming the cost estimate was prepared by your design team? Your letter looks good and I think it lays out your total final budget that you have and are prepared to put to this project. Again - I presume the design team (architect, QS and SE etc) are taking this project to completion and hand-over with a full professional service including contract administration and inspections? While I appreciate that the cost estimate is not firmed up I think you are on the right track with your letter and it should concentrate their minds going forward. I would suggest that the cost estimate is revised on a regular basis as the production information is put together so that you get an as accurate as possible cost estimate before you tender your project. You mention an extension - get that element costed separately in your cost estimate documents so that you can easily extract it from the cost estimate either before you tender or a bill of reductions exercise. Don’t forget CDM any any costs associated with that. Good luck. -
https://99percentinvisible.org/article/one-one-full-scale-floor-plans-help-architects-walk-clients-designs/
-
What are your thoughts on this project estimate?
ETC replied to James Frome's topic in Costing & Estimating
Having looked at the floor plans and for that size of a building and making a stab at the extent of the works required I still think the fees were far too high. While I appreciate that restoration works tend to be more labour intensive for everyone including your architect I would have expected 10% to include a complete design team (if one was needed) including a QS for the complete duration of the project. Having looked at the cost breakdown there are quite a few Provisional Sums which make me wonder how detailed the drawings are and how much information the materials specifications actually have. I would love to see the drawings if you are minded to post them - I’d love to see what a set of drawings that cost £50k actually look like. As an architect I pride myself in making sure everything is specified to within an inch of its life before a QS gets anywhere near it. I really think that having so many Provisional Sums in a cost estimate is really a cop out and looks like someone throwing costs at a project and covering their back side. For what it’s worth I would take a deep breath, circle the wagons and look at getting some advice from another architect and/or QS. A second opinion as it were. -
What are your thoughts on this project estimate?
ETC replied to James Frome's topic in Costing & Estimating
I think your architects fees are way over the top. -
'False ceiling' at roof apex/ridge for ventilation?
ETC replied to GlanMenai's topic in Heat Insulation
Read the BBA Certificate. -
'False ceiling' at roof apex/ridge for ventilation?
ETC replied to GlanMenai's topic in Heat Insulation
https://www.dupont.co.uk/content/dam/dupont/amer/us/en/performance-building-solutions/public/documents/en/BBA-DuPont-Tyvek-Supro-Roof-underlay-Warm-non-ventilated-roofs.pdf -
Do extension foundations need to go to house foundation?
ETC replied to m13eys's topic in House Extensions & Conservatories
Strip foundations for an extension should - in most if not all case - go to the bottom of the foundations of the dwelling. If you think about it logically - if the foundations of a house are taken to a certain depth to get good ground why wouldn’t the extension foundations go to the same depth? I’m sure a structural engineer would be able to justify an alternative option. -
How to detail PIR at the wall cavity / wall plate in this situation?
ETC replied to Oxbow16's topic in Heat Insulation
Insulated plasterboard? -
Getting my head around Part B and K for our windows
ETC replied to MikeSharp01's topic in Windows & Glazing
I wouldn’t like to test the legislation in court. BC would lose. -
Getting my head around Part B and K for our windows
ETC replied to MikeSharp01's topic in Windows & Glazing
I agree - a lockable EEW is a death trap. Unfortunately BC cannot reject an EEW if it has a lock on it. Presumably it’s more important to keep a burglar out than to let someone escape in an emergency. I have had this conversation many times with my colleagues in BC and although we cannot reject a lockable window we sometimes ask the applicant to think seriously about putting a lock on a window. If they want a lock we would suggest one that you can push and turn a handle on the inside. -
Are eco joists the same as posi joists
ETC replied to CalvinHobbes's topic in General Construction Issues
Footpath and sidewalk. Same thing different manufacturers. -
Getting my head around Part B and K for our windows
ETC replied to MikeSharp01's topic in Windows & Glazing
The NI Guidance shows a minimum height of 800mm above FFL for an EEW. Rarely enforced as long as guarding or a restrictor stay is fitted to the EEW.
