Hi guys,
I just wanted clarification on an issue I'm facing with my building control company. A bit of background info:
I had an inspector assigned and he made the first couple of site visits for foundations and drainage. He was happy with what the builders had done so far and was happy for the builders to continue the work.
As my house extension requires a large amount of steel beams and steel columns, we asked for a site visit to check the steels out once they were in place but were told that the inspector does not come out until the roof frame has been erected.
I stated that there were a lot of steel beams involved and modifying something later on would be nearly impossible, so the inspector asked me to send him lots of pictures of the steel beams. Once he had reviewed these pictures, he told my builder he was happy with the steel work and that he can continue the building work.
A little while later, we had constructed the first floor walls and the roof frame and so requested the next site visit.
But we were told by the company that the assigned inspector was off on long term sickness. After chasing the company for a couple of weeks, I eventually spoke to a manager and told him the situation was causing a delay to the work, as we couldn't proceed without the site visit to approve the roof.
The manager reluctantly agreed to do the site visit himself and on the day he arrived, he must have had a bee in his bonnet about being called out to the site.
Foregoing his rudeness and bad attitude, he decided to look at previously approved items and attempt to find issues with them.
He questioned the drainage that was approved on site by the original inspector and then decided to find faults with the steel beams and how the frames were constructed.
After he left, he reported these issues and requested updated technical drawings and new structural engineer documents for the drainage, the steel works and the roof construction. It seemed like he was deliberately trying to find faults with work that would be difficult to modify, as we have built upon these after originally having the work approved. This has already set me back around £5000 in delays, material costs and additional fees for architects and SE.
So the question I have is, if an inspector has made a site visit and verbally approved the drainage and there is no reported issue with this can a different inspector later come and find issues with this?
Similarly, if an inspector has reviewed photos of the steel works and has refused to come out on site but has told the builder the steel works look fine and you can continue with the work, can a different inspector come and report faults after the builder has built walls and the roof frame on these beams?
It seems to me that if the process of inspection can be altered at a later date then what is the actual point of having these site inspections at specific stages of the work?
Any help or advice would be greatly appreciated.
Shuja