Boris Posted November 27, 2019 Share Posted November 27, 2019 If you had 2 carpenters working on pre made door liners (just screw the parts together). Cutting out MDF for window boards (no routing out to shape yet) what would you expect the 2 carpenters to do in one day ? If you paid by the job rather than the hour, again what would you expect to pay ? TIA Link to comment Share on other sites More sharing options...
ProDave Posted November 27, 2019 Share Posted November 27, 2019 Last time I tried standard "just screw together" door liners were never the right size. Last time I employed carpenters was to hang my expensive oak doors into the oak door liners I had already put in place, and 2 of them hung 6 doors in a morning, so about an hour per door each. Link to comment Share on other sites More sharing options...
nod Posted November 27, 2019 Share Posted November 27, 2019 If the liners are on solid walls One per man hour including making up the frame wouldn’t be unreasonable Fitting to studs at least half as many again Oak type internal doors One per man hour including latch and handle would be reasonable These are site Joiner targets There can be a massive difference between all trades that are used to site work and the others JOBBERS But will also depend on the day rate you are paying On a house there is hardly anything that can’t be quantified and priced Link to comment Share on other sites More sharing options...
RichS Posted November 27, 2019 Share Posted November 27, 2019 The time taken to hang a door will vary greatly depending on how good the frame has been installed, also the weight/size of the door. if hanging internal doors I always hung all the doors first and then went back and sorted out the furniture. Link to comment Share on other sites More sharing options...
Oz07 Posted November 27, 2019 Share Posted November 27, 2019 I must be slow as f,,,k and I've been making a living at it! I wouldn't aim for any more than 4-5 oak doors in a day inc furniture or around 8 just swinging. I think 8 per day inc furniture and they could be a bit rough @nod Probably agree on the liners. Maybe a touch longer. I'd make em all up first, stop have a morning cuppa, then start fitting. In answer to op question maybe 8 liners fitted and all your window boards cut ready to fix inc ends routered if out of sheet material Link to comment Share on other sites More sharing options...
Boris Posted November 27, 2019 Author Share Posted November 27, 2019 I will be exact. 6 window boards cut to fit, out of MDF, no shaping. 2 Pre made liners screwed together, NOT fitted. This took 2 carpenters 1 day. My OH could do this on his own. Link to comment Share on other sites More sharing options...
Onoff Posted November 27, 2019 Share Posted November 27, 2019 (edited) @Boris, don't know if you've chosen your furniture yet but these magnetic catches are magic imo. I just fitted them to a couple of cheap doors for now (oak later). As this little video shows. No chance of catching your hip or clothes as you pass: Edited November 28, 2019 by Onoff Link to comment Share on other sites More sharing options...
nod Posted November 27, 2019 Share Posted November 27, 2019 1 hour ago, Oz07 said: I must be slow as f,,,k and I've been making a living at it! I wouldn't aim for any more than 4-5 oak doors in a day inc furniture or around 8 just swinging. I think 8 per day inc furniture and they could be a bit rough @nod Probably agree on the liners. Maybe a touch longer. I'd make em all up first, stop have a morning cuppa, then start fitting. In answer to op question maybe 8 liners fitted and all your window boards cut ready to fix inc ends routered if out of sheet material 1 hour ago, Oz07 said: I must be slow as f,,,k and I've been making a living at it! I wouldn't aim for any more than 4-5 oak doors in a day inc furniture or around 8 just swinging. I think 8 per day inc furniture and they could be a bit rough @nod Probably agree on the liners. Maybe a touch longer. I'd make em all up first, stop have a morning cuppa, then start fitting. In answer to op question maybe 8 liners fitted and all your window boards cut ready to fix inc ends routered if out of sheet material I fitted our OAK TYPE doors in two days 14 in total Piece of P*** If you have a jig I must be as fast as F*** ? Link to comment Share on other sites More sharing options...
bassanclan Posted November 27, 2019 Share Posted November 27, 2019 57 minutes ago, Boris said: I will be exact. 6 window boards cut to fit, out of MDF, no shaping. 2 Pre made liners screwed together, NOT fitted. This took 2 carpenters 1 day. My OH could do this on his own. On the face of it that sounds way too slow, more like a mornings work for one person. It's worth asking them what problems they encountered as they didn't seem to make much progress Link to comment Share on other sites More sharing options...
Onoff Posted November 28, 2019 Share Posted November 28, 2019 Even I'm quicker than that! ? Link to comment Share on other sites More sharing options...
ToughButterCup Posted November 28, 2019 Share Posted November 28, 2019 9 hours ago, nod said: [...] Do you have to pay more if the screws are all lined up properly? 1 Link to comment Share on other sites More sharing options...
SteamyTea Posted November 28, 2019 Share Posted November 28, 2019 3 minutes ago, AnonymousBosch said: Do you have to pay more if the screws are all lined up properly? Depends how bad the OCD is, really bad cases you get a grant to employ them. Link to comment Share on other sites More sharing options...
Oz07 Posted November 28, 2019 Share Posted November 28, 2019 (edited) No he does that for free @AnonymousBosch but the gap at top of hinge to hang coat off is extra! Edited November 28, 2019 by Oz07 1 2 Link to comment Share on other sites More sharing options...
Temp Posted November 28, 2019 Share Posted November 28, 2019 14 hours ago, AnonymousBosch said: Do you have to pay more if the screws are all lined up properly? Many many decades ago I was at a military camp trying to win camp competition for best turned out room. Running out of ideas to improve things we removed every screw we could find. Not all were brass so we had to "acquire" some so they all matched. The brass heads were polished to a high shine and the slots aligned. As i recall we got extra rounds on the range :-) Link to comment Share on other sites More sharing options...
Carrerahill Posted November 28, 2019 Share Posted November 28, 2019 On 27/11/2019 at 22:13, Boris said: I will be exact. 6 window boards cut to fit, out of MDF, no shaping. 2 Pre made liners screwed together, NOT fitted. This took 2 carpenters 1 day. My OH could do this on his own. So are we talking 6 pieces of MDF cut from a sheet(s)? Presumably plunge saw and guide rail type stuff? As an amateur working in my garage, I'd cut them with the Fes plunge-saw in about an hour I'd of thought including fully measuring & noting each window, then laying it out and cutting it and setting up the extension cable, dust vac and saw! If I could do it on my table saw - run them all to the same width then use the sliding mitre-saw to cut to length I reckon maybe 30minutes! I'd probably screw together 2 pre-made liners in 15-20 minutes. Are you paying them an hourly rate? I'd be keeping an eye on them and pulling them up, or simply throw them off the job if you can. If a job price then leave them to it. They might blitz things on the last day. Are they working for a firm? Link to comment Share on other sites More sharing options...
Recommended Posts
Create an account or sign in to comment
You need to be a member in order to leave a comment
Create an account
Sign up for a new account in our community. It's easy!
Register a new accountSign in
Already have an account? Sign in here.
Sign In Now