Not sure. Not seeing anything wrong with the foam, it's been in for nearly 4 years.
-
Icynene LDC-50 Used battens under posi rafter to kill of thermal bridges. U values Pitched 0.13 Nearly flat (12 degs) 0.12 Only issue with spray foam is numb skull installers that install in inappropriate places like holding a roof structure together with closed cell foam and a non vapour permeable membrane. Then wonder why the roof rots.
-
But when you strip out the minerals, via ion exchange and reverse osmosis you change the properties of the water a great deal. So check before you assume anything with respect pH.
-
Our roof is a similar construction, but I tried to go warmcell and they refused to do it. In the end I had all the interstitial condensation calculations done and went open cell spray foam - 300 to 350mm deep. 250m² of roof done in a day and a half. We used normal wood sarking boards with small gaps, no need for counter battens with natural slates.
-
Threaded bits are the same. Salus actuator has two clip on temp sensors for flow and return. Do may be different.
-
A wheel chair user can be in any dwelling and could be anyone, even if you think your able bodied. One fall in the ice, could have you on crutches or in a wheelchair for weeks.
-
MVHR - Frankische E11 Supply air error
JohnMo replied to Street18's topic in Mechanical Ventilation with Heat Recovery (MVHR)
ALL your pipes/plenum should be insulated in the loft - can see plenty in your photos not insulated. It appears to shutting down to protect the heat exchanger, but seems to be doing very early. I would have a read through the manual for the unit. Mine will go into extract only mode if it needs to protect itself, but it never seems to need to. A pre heater as linked to above is the normal way to do it. It can be electric or water based. -
Our last house (1830s build) when we had it rewired we had all the sockets put at minimum 450mm. Way easier to get at, you never know when you may need that extra height.
-
Plastic primer on any existing powder coat that doesn't come off. Then paint the lot.
-
Smallest defect in powder coat and it's rubbish. Water gets in and corrosion starts unseen, by the time peeling starts it's too late. Strip back as far as you can and paint, you may need a plastic primer on powder coat so it sticks.
-
A heating season will bring the pH up apparently.
-
We have now been in the house with MVHR for a couple of years. We had manual over rides for boost and sensors in the MVHR unit. During winter humidity levels are so low, even after a shower boost is never needed. Sensor for humidity is in the hall, humidity this afternoon was 39%, after boiling veg and potatoes for tea, humidity jumped up to 40% (1% difference), after an evening shower humidity up to 40.5%, 30 mins later back to 39%. Boost not used or didn't need to start. MVHR flow rates are set lower than building regs
-
So if your design load is 10kW+ at -3 the demand at an average of about 2 degs will be about 75% of 10kW. So 7.5kW. 24 x 7.5 is 180kWh. So you are getting a CoP of about 2, assuming everything is going into the heat pump. Your trouble is your flowing at 45+ degs. So what temperature do you have into UFH and out and from heat pump and back. Are your radiators only in bathrooms? If so I would look to dual fuel with an electric element and reduce the flow temp of the heat pump down to max mid 30s. This will knock 30% off your electric consumption. Not seen asked but does your heat pump feed a buffer then heating system?
-
I will bow out, obviously wasting my time answering questions as this was answered previously.
-
Extending house which is already too close to septic tank
JohnMo replied to Jimbobjones's topic in Waste & Sewerage
? Possibly, think you may be answering your own question. What other choice would a planner have? They will not turn a blind eye. May open a can of worms you don't want? -
HLP is per m² of the outside surface area not the floor area. It gets further calculations done to it, so not sure it's a good number to use. Just looked at the calculation behind the one posted and that's not that good either. The heat loss parameter (HLP) is an intermediate result from the SAP calculation which describes the specific heat loss per unit of the dwelling’s external surface area, in W/m²K. It includes ventilation heat losses as well as conduction heat losses. It is in that respect a very pure measure of the thermal efficiency of the shell of the building. This is therefore another option for use as a fabric efficiency rating metric.
-
Steel is great conductor of heat. Under block and beam ground will be about 6 degs. Insulation through the floor will make zero difference. The post will be sucking heat from house a very quick rate if not insulated. 25mm PIR insulation and plasterboard. If you have the option to have outside the heated environment, do it. Other insulation is definitely needed
-
Very dependant on flow temp. 6kW is nearer to what they modulate to at low temps. PDHW allows t 2 hrs per day, that will be loads. So 22 hrs to supply all your heating instead of 24 hrs. As said previously use a heat pump cylinder heat to 50 degs. 210 to 250L would be ok for 3 to 4 bed house. Size boiler the same as a heat pump. Say your heat demand is 6kW, (24 x 6)/22. So 6.5kW. UFH gives you quite a bit of leeway on sizing. As the floor will take all the heat you can though at it. I found mixer and additional pump a hinder rather than a gain.
-
There isn't a reason why a house completed in 2022 should need anywhere near 11kW. I'm at nearly 200m² 6m high ceiling in one room, which also floor to ceiling glass, all other average 3m tall. At -9 the house needs around 3kW. Taking away heat recovery ventilation would double the heat load Floors take lots of energy, take a huge amount of time to recover from being cool. Letting house cool takes an age to recover. If house heat loss is say 10kW, an 11kW heat pump needs to run 24/7 to just stand still. Let alone recover from 14 hrs effective off due to thermostat timings.
-
The ASHP install. Lots of heating on/heating off then fingers crossed.
JohnMo commented on TheMitchells's blog entry in Renovation of Ellesmere Bungalow.
So you have basically removed your ventilation and not replaced with it? Mould will be happy, parents health not so.