flanagaj Posted 2 hours ago Posted 2 hours ago To date, the bricklayers and myself included have simply washed mixers out and discarded the washout water onto the ground. I am curious as to what others do as most of the options available for capturing washout are for large sites where they can have dedicated washout bins and recycle the water. For a domestic self build, that approach is not obviously not viable. We don't have any water courses / drains in the vicinity and water table is 60ft below.
Mr Punter Posted 2 hours ago Posted 2 hours ago For concrete I use a sheet of 18mm OSB and some 4 x 2 to form a tray, lined with polythene. Let the concrete go off, then break it up and use it as hardcore. 1
flanagaj Posted 2 hours ago Author Posted 2 hours ago 36 minutes ago, Mr Punter said: For concrete I use a sheet of 18mm OSB and some 4 x 2 to form a tray, lined with polythene. Let the concrete go off, then break it up and use it as hardcore. Ok, thanks. What about washout water from mixers and concrete readymix trucks?
Mr Punter Posted 2 hours ago Posted 2 hours ago Just now, flanagaj said: Ok, thanks. What about washout water from mixers and concrete readymix trucks? Just get them to hover over your tray and crap the contents out. It is a bit messy but it will be fine. Water dries up, concrete sets and can be broken up. 1
Conor Posted 30 minutes ago Posted 30 minutes ago I made sure the washout area was a spot that would be later paved / concreted over. Each time there was a dump of concrete or cement, I'd rake it out flat and level. Ended up covering a good 20m²+ and 100mm+ thick by the time we were done. Concrete pumps produce a lot of waste!
Recommended Posts
Create an account or sign in to comment
You need to be a member in order to leave a comment
Create an account
Sign up for a new account in our community. It's easy!
Register a new accountSign in
Already have an account? Sign in here.
Sign In Now