I kin of expect my operating point to be at a head of 3m which is better suited to the Ecocirc M (3m constant pressure setting) than the Ecorcirc L (2m & 4m constant pressure settings]. However, 2m3/h would put it right near the maximum flow rate for the Ecocirc M at 3m head. Running the pressure 33% higher (at 4m rather than 3m) would put up the flow rate by 18% [1.33^(1/1.76)=1.18] and the hydraulic power by 57%, probably the electricity consumption too.
-
Here's a video of just attaching it to the stringer https://youtu.be/Pmyaw2TPUhk
-
Thanks How far does the first step of the upper flight overlap the half landing frame? I've designed it so that the riser is flush with the frame edge and it's only the nosing overlapping. That doesn't allow for any intermediate (internal structural) open stringers to notch on to the landing frame which would be nice for support. I hope that makes sense.
-
JAS Timber offer a service of cutting the mortice and tenon for you, but they are in Lancashire which is far from me in Cambridge. https://www.jastimber.co.uk/newel-mortice-stairs-1-tenon
-
Below is an example of the Newel / Stringer mortice and tenon. @dnb I see you've just installed a Stairbox kit with half landing. How do they do it? Is it a tenon on the stringer into the newel post? http://www.builderbill-diy-help.com/building-stairs.html
-
I know you can buy kits etc, but I've always wanted to make the stairs myself and I plan to do it in the way they typically do in the US. Make a rough stair and then clad with the trimmings. That said, I think it makes sense to use nice timber for the Stringer. I have created some CAD and the plan is to create a half landing frame, that the stringers attach to and the OSB half landing goes on to. Currently I have Newel posts just notched onto the half landing frame and the upper stair stringer, but I think I would like them to form uprights of the half landing frame by extending all the way to the ground. That may be too ambitious and increase my chances of making a hash of it. If I was to do it, the upper stair stringer would need to bolt onto the Newel, rather than notching onto the top of the half landing frame. Perhaps it would be better as a tenon into the Newel, but that would be an interesting tenon to cut and I don't have a morticing machine either. I think the Newel posts and the nosings are the only bits that are eluding me at the moment. Currently the stringer is 45mm x 220mm timber. Going is 220mm and Rising is 195mm. Newel height currently arbitrary.
-
The Lowara pumps actually have some additional goodies over the Grunfos: Constant pressure mode (modes 1, 2 3) as well as proportional-pressure (A, B, C) and constant speed modes like the Grunfos (I, II, III) Option to have a display and Bluetooth (adds about £30 ex VAT) Best-in-class energy efficiency (EEI ≤0.18) vs Grunfos EEI≤0.23 Both state Sound level ≤ 43 dB(A) Lowara are also about half the price of the Grunfos. So even if they don't last as long, they could be a better option.
-
The Grunfos UPS2 does pretty much what I want in terms of pressure / flow control (see below). When an UHF loop shuts off with an old style pump, it will maintain the same flow rate by upping the pressure which isn't what you want as it will increase the flow in the other loops. I want the differential pressure at the UFH manifolds to remain constant. If there was no head loss in the manifold feed/return lines, that would mean I wanted a pump that has a constant pressure output. However, since there is head loss in the manifold feed/return pipes, the pump needs to make a slight reduction in output pressure. I guess that is what UPS2's proportional-pressure control is intended to achieve, but I think it may be a little bit too sloped. In my example in the first post, there was 3.1m of head loss associated with the loop and its feed valves and 1m of head loss due to the manifold feed/return pipes at the furthest manifold. If half the loops shut off, manifold feed flow rate would half and the pressure drop in those pipes would go down to about 0.3m head loss. I have probably overestimated the 'loss at manifold' as it makes sense for that to be near zero for the longest loop and higher for shorter loops to try to balance. If it is zero, then I would need a proportional-pressure control curve which was linear from (0m3/h, 2.1m) to (2m3/h, 3.1m). PP1 looks to go from (0m3/h, 2.1m) to (2m3/h, 4m), so I guess that would increase the flow slightly in loops when valves shut off. It gets complicated by the different flows and lengths to different manifolds, but hopefully not too much. I have one manifold (3 ports connected) that is in the plant room, so has very short feed/return pipes. This feels better served by 22mm pipes and perhaps a manual orifice/valve. Even if the manifold differential pressure changes by 50%, an unrestricted loops flow would change by 26% [1.5^(1/1.76) = 1.26] so power delivery would rise by around that same figure, perhaps 30%. Orifice pressure vs flow relation is similar to pipe, so OK modelled by the 1.76 power. Of course, if I go the @JohnMo route of having no actuators, it will be balance and forget. Very tempting! I watched a good Heat Geek video about how shutting off a zone can mean that you up the heat demand in the still active zones (due to uninsulated internal walls), which ups the flow temperature, lowers the COP and actually costs more. Many variables, like house geometry, but it does make sense.
-
I'll use the pumps they have supplied for the ASHP side of the low loss header, but I need a pump for the UFH side of the low loss header.
-
It's all UFH. 12 loops upstairs and 13 downstairs.
-
Different floors, but I am hoping that doesn't matter
-
ASHP kit has come with two LOWARA 25-8/130 pumps and the supplier's schematic shows these on the flow and return pipes to the actual ASHP itself (from the low loss header). The schematic then shows a pump on each manifold feed pipe after the low loss header. These pumps I am trying to common up into one pump and I'll need to balance the valves at the manifolds to achieve this. I reminded myself of the no actuators thread earlier and it's a good one. I think I'll be trying to do something like that , keeping the overall flow the constant and varying the flow temperature
-
I'm going with a slightly different setup to many by having a single circulation pump in the plant room rather than a pump on each manifold. I'll need to have a bypass in case all the valves suddenly close, but I presume the bypass is a pressure relief, so is normally closed and only opens when the pressure is too high and allows time for the pump to switch off. Flow Rate: We're installing an 11.2kW Ecodan. A major input to the pump sizing will be the dT flow to return which I'll assume is dT = 5C. Based on that I can work our a flow rate as F = P_Heat / (Heat_Capacity * dT) = 11.2kW / (4.2kJ/kg.K * 5K) = 0.47kg/s = 1.92m3/h. Pressure (Head): This comes down to the amount of pipe work you have and isn't a function of how high you house is (water goes up and back down). The flow rate dictates the resistance to flow which is the head. The main losses that came to mind were loop, at manifold and manifold feed: Loop: I've taken the longest loop and take that as a fraction of the overall loop length of the system and it works out as 6% (yes, I have a silly number of loops). That means it will have a flow rate of 6%*1.92m3/h = 0.12m3/h = 0.032kg/s. I don't have data for 16mm UFH pipe but 15mm Hep2O is probably a good proxy and they publish that. In other considerations I worked fitted a line to that data which gives Head_Loss_KPA_Per_M = 79.9*(FLOW_IN_KG_PER_S^1.76) = 0.187 kPa/m. My longest loop is 110m long so that works out as a pressure drop across the loop of 110m * 0.15kPa/m = 20.6kPa = 2.1m head loss. At Manifold: due to valving etc: Guestimated as 1m head loss. I expect/hope this is an overestimate but would depend on how we have the balancing valves set etc. Manifold feed: I've taken the manifold with the most loops which is also the furthest on it and take that as a fraction of the overall loop length of the system and it works out as 48%. That means it will have a flow rate of 48%*1.92m3/h = 0.92m3/h = 0.256kg/s. For 28mm Hep2O Head_Loss_KPA_Per_M = 2.89*(FLOW_IN_KG_PER_S^1.76) = 0.263 kPa/m. This manifold is 36m round trip from the plant room (difficult routing) so that works out as a pressure drop across manifold feed and return 36m * 0.21kPa/m = 9.5kPa = 0.95m head loss. The sum of those three head losses is 2.1m + 1m + 0.95m = 4.05m. There will likely be other losses, but hopefully the 'at manifold' figure is pessimistic. I think conventional wisdom is to go with 6m of head loss capability. A Grundfos UPS2 25/80 (180) should work. The 25 number represents the fitting diameter, 80 represents the maximum head (in kPa) so 8m, and the 180 is the distance between fittings. Operating at 4m head and ~2m3/h should give an efficiency of around 45% which whilst not peak is near. That pump is more powerful and expensive (twice) than a Lowara ECOCIRC L 25-8/180. That pump doesn't have efficiency data though. Oversizing the pump (e.g. Grundfos Magna1 32/80 (180) not shown below) could push it lower of its efficiency curve. Grundfos UPS2 25/80 (180): Lowara ECOCIRC L 25-8/180:
-
Is It Worth Insulating UHF Manifold Feeds/Returns
MortarThePoint replied to MortarThePoint's topic in Underfloor Heating
I can happily do that for the DHW 15mm and 10mm pipes, but the void is too cramped for 19mm insulation on 28mm pipe unfortunately. -
Is It Worth Insulating UHF Manifold Feeds/Returns
MortarThePoint replied to MortarThePoint's topic in Underfloor Heating
Below is a table from BS 5422:2009 which assumes 60C pipe and 15C ambient. Looking at 28mm pipe it has a minimum thickness of 16mm for 0.035 W/m.K which is the best you can hope for from PE and 20mm for 0.040 W/m.K which is perhaps more realistic. At a 35C average flow/return temperature moving from PE13 to PE20 reduces the loss per metre by 20% from 3.8 W/m to 3.1 W/m, but both are massively under the maximum permissible heat loss of 10.07 W/m. -
Is It Worth Insulating UHF Manifold Feeds/Returns
MortarThePoint replied to MortarThePoint's topic in Underfloor Heating
@Nickfromwales I'm going to route my UFH feed and return pipes through the ceiling void (~60mm high) to the manifolds. Flow temperatures are expected to be around 35C. Am I reading part L correctly that I wouldn't be able to use the 'standard' 13mm PE insulation the likes of Screwfix sell? With a low flow temperature, it doesn't make sense on paper to use phenolic, or 20mm thick PE. Appears that the regs disagree though. -
Is It Worth Insulating UHF Manifold Feeds/Returns
MortarThePoint replied to MortarThePoint's topic in Underfloor Heating
Need to check building regs, but insulation looks mandatory: https://www.nhbc.co.uk/binaries/content/assets/nhbc/tech-zone/nhbc-standards/tech-guidance/8.1/pipeinsulation.pdf Part L: What's draconian is the insistence on using 60C for the consideration. PE needs to be much thicker than Phenolic for he same loss so that 10mm figure rises to around 20mm for PE. -
Is It Worth Insulating UHF Manifold Feeds/Returns
MortarThePoint replied to MortarThePoint's topic in Underfloor Heating
I've got three manifolds: 2.5m, 8m and 15m from the low loss header. Doubling as flow and return gives a total of 5+16+30=51m. I pessimistically rounded up to 60m. Payback times should be independent of length in this calculation. -
On another thread I think I worked out that there is little point in insulating domestic hot water pipes unless you have a circulatory system. Cold water pipes should be insulated to avoid condensation. I've been wondering about UFH manifold feed and return pipes and did some calculations I thought were worth sharing: I adapted the pipe insulation spreadsheet from the CheGuide.com. The table shows the amount of heat lost in the feed/return pipes. 'Recovery Factor' represents the usefulness of heat that is lost since it isn't truly lost, it is staying within the heated envelope, but in the wrong place. I intend to have a relatively uniform heat and so most of the heat will be 'recovered'. Various insulation scenarios are considered with the resulting annual cost of lost heat as well as the cost of the insulation (material only). The payback time for insulating PE 13 (e.g. ScrewFix) is just 3.4years. The payback time of upgrading from PE 13 to Phenolic 15 Shiny (e.g. Kooltherm) is 38years. That ignores interest/inflation. There is no consideration of the carbon costs, either of lost heat or insulation manufacture. 'Cost of heat' is based on £0.30/kWh electricity an a COP of 300% which is hopefully pessimistic, but who knows these days. Not everything comes down to cost obviously, but using 13mm PE insulation looks to offer the best compromise for my system based on a relatively low 35C average flow/return temperature (e.g. 38C flow, 32C return). I hope to have lower temperatures than that, in which case the payback times go up higher. If however you run your ASHP flow temperatures at 65C, the payback time of upgrading to Phenolic 15 Shiny would be about 13 years.
-
Opinions on best way to drop a ceiling
MortarThePoint replied to Thorfun's topic in General Construction Issues
With 12.5mm PB, I'd use battens at 400mm centres. Minimal extra cost/weight/time. -
Opinions on best way to drop a ceiling
MortarThePoint replied to Thorfun's topic in General Construction Issues
There are some expensive profiles out there to do this. First link has an installation animation. ~£35/m seems steep to me, but may be the easiest way to go. https://www.darklightdesign.com/led-profilelement-dsl-profile/ https://www.ebay.co.uk/itm/273214350882 https://www.iluminize.com/en/shop/product/4604-led-drywall-profile-dsl-2m-long-for-floating-surfaces-with-a-substructure-363#attr= -
Opinions on best way to drop a ceiling
MortarThePoint replied to Thorfun's topic in General Construction Issues
Is the loft living space? If it is, and the house is 3 storey, you will need this ceiling to be fire rated. That shouldn't rule out the battens, but you'll need to something neat with plasterboard (PB) to achieve a fire seal. Lots of strips of PB probably. Also check the fire properties of the LED strips as they may have a minimum distance to timber. PB in the way should solve that though. Something like the image below. If the plasterboard was 12.5mm then you could use 50mm x 38mm battens at 400mm c/c. If using thicker or thinner plasterboard, you could change batten thickness accordingly. Plasterboard strips can be screwed through with long PB screws, ensuring at least 25mm into timber. Also through the bottom most sheet and through the strips. Use a continuous bead of FireStop sealant between strips. You would probably want to use a plasterboard edge bead. No idea if this would meet regs, so you'll need to check that. Is there any indication as to how big the gap dimensions need to be. -
I was planning to use a tanking kit in the shower but not the rest of the room (e.g. not near bath).
-
Wife is full of opinions but not decisions so probably makes sense to S&C. Also, not a fan of D&D.
-
Good question. Not given much thought but intended to use waterproof tile adhesive and waterproof grout. Any recommendations?