Great_scot_selfbuild
Members-
Posts
409 -
Joined
-
Last visited
Everything posted by Great_scot_selfbuild
-
This feels a bit high - what’s the opinion here? Just before receiving this, I’ve been looking at running the pipework from plant room to the end points, then this came in (I’m now definitely considering running the pipework myself). Approximate scope: First fix plumbing pipework install. Only installing a mains connection point in the plant room (leaving the UFH / DHW / ASHP to others). 260sqm, 4 bed house with kitchen sink, dishwasher, freezer with water/ice dispenser, downstairs WC, washing machine, family bathroom & 2 en-suite. Doesn’t include bathroom installation (just pipes to the correct positions in the wall). Labour cost £2,750.00 for all pipe installation (not bathroom install) Materials cost £1,780.00 For all materials as above based on 28mm copper main to plank room plus fittings and stop cocks plus 22mm hep2o pipe and fittings for the hot and cold runs with 15mm hep 20 and 15mm copper spurs. Also, isolation valves to toilets, sinks, bath and showers. Thoughts? Experience elsewhere?
-
We’re approaching the point of having the plumbing first fix done and I’m not getting the confident feeling from our plumber - they’re asking for the design of the plant room and system configuration. It seems they are skilled as the practical work when told what to do, but now I’m looking into what a design should look like. I’m not expecting our principal designer to provide a design of the plumbing pipework, and although I’m looking at alternative plumbers, I now want to see some examples of what to expect as to a design / configuration of the plumbing pipework. If it’s not that complicated (which I don’t believe our system is) then in order to get a neat and tidy install that we’re after, I’m wanting to work out a design even if it’s just a means of me assessing whether the plumber we contract proposes something similar or miles off. Help me educate myself - TIA
-
@garrymartin Out of interest, how is this calculated? In terms of ‘enclosed in insulation’, I’ve just been thinking this over, how enclosed is enclosed (if this makes sense). Our situation: There will be 75mm batt insulation in the 89mm stud walls (3m high), then cables running above the insulation in the ceiling space (425mm deep posi joists, with 100mm acoustic insulation), and then out into the plant room.
-
Part of the challenge - we haven't decided yet, but equally this could change in the future anyway, so I'm just looking to install the wiring to be the most robust / good design we can. If it future-proofed the design I'd even go for 10mm, but if this is HUGE overkill and only really needed for industrial systems, then I don't want to waste the money. Based on me searches, I'm inclined to run separate 6mm radials. I assume a double oven is one (not two) cable, and a warming drawer is another(?)
-
I'm looking to make sure we document our electrical design and detail of all the layout. I have a very useable and functional method I'm using at the moment, but would like to know what it 'should' look like. We have a principal designer and this detail is exactly what I expect to be provided, but I'll be honest - on some of the nitty gritty drawing detail like this, I think it may fall short of expectations. Hence, I'm interested in: 1. Is there a layout / standard style that an architect would produce (to be clear, our PD isn't an architect - we couldn't afford to use our architect from planning phase for the construction drawings). 2. Are there other methods that anyone has found to be preferable / useful / look good. Thanks
-
We're laying first fix wiring with our electrician but the only size cable we have on site (at the moment at least) is 1.5TE (light), 2.5TE (power) and 3CE (blinds). I've not yet seen any radial circuits for the key appliances that I would expect to have on a dedicated circuit. Having done some searching and ChatGPT (but never fully trusting it), responses come back referring to oven/hobs on a 6 or 10mm2 cable and appliances could be on a fuzed spur from a ring, but radial is preferred. I'd much rather have more robustness in our design for the sake of a small cost of some cable whilst all the walls are open. Looking for a second opinion from those who know about this stuff. Detail: Induction hob, cable run = 25m double oven & warming drawer, cable run = 30m TIA
-
Any advice / experience on laying a floating floor LVT system. I'm aware of the requirement to leave a gap at the edge underneath skirting board, but we're wanting to have it flush at a couple of locations. Would appreciate advice on the following scenarios: 1. Flush/right up to the edge of the sliding door and windows which make up 3 sides of an open plan kitchen/dining room (all other edges of the flooring will have a gap around the edge concealed by skirting). 2. Flush up to a well mat at the front and rear doors. Can we take it right up to the edge of the mat, or is there a trim that would neatly act as the edge of a mat well and provide a cover over the edge of the LVT? Thanks in advance.
-
I’m busy installing PIR flooring insulation (on top of beam & block floor, to then have a dry screed laid on top. We have the DPC down, and it’s all going together fairly well. I understand expanding foam is typically used to help fix them all together and generally fill the odd gap (none are large). I’m worried about the foam getting underneath and lifting the boards. 1. How much foam is typically needed (assume the sheets are tight together)? 2. Any tips on installing the foam? 3. Do I need to be worried about the foam lifting sheets, or will it only really expand where there’s a gap for it to? TIA
-
Great to hear. We've had our Internorm door fitted and LOVE it. Definitely felt like a luxury spend, but we went by a similar logic - few bits of the house will have such a guaranteed impact. No fingerprint scanner though... 👏
-
@SimonD I'm interested in doing my own calculations on this. Whilst I head off and do some searching, can you help me expedite this by directing me to any resources / reference material that takes me through the process specific to sizing UFH to a room / heat loss etc? It sounds like this should be a lot easier than trying to dig out my thermodynamics notes from 20+yrs ago (I hope... never was my favourite, but now I'm more motivated 🤣). In an earlier post which evolve into a focus on the UFH layout / sizing I had actually asked about this - I was wanting to understand if I should be looking to tailor the UFH pipe spacing and design to each room, which largely received the response "it'll all end up at the same temperature, so don't bother" (I'm heavily para-phrasing). However, I do like to learn a new aspect of engineering and although I have no available time, I'll happily sacrifice some of my sleep to work this through myself. Would be grateful for a steer... (btw I did look up Rob Berridge and in the YouTube interview he mentioned that he provided training material but I can't find it; I've reached out to him, but no response yet). I'm still waiting myself. This sums up so many of my frustrations. How are the general public (i.e. me) meant to know enough to challenge the information we're provided. I've surprised myself at how much I've spotted, been brave enough to question and then, disappointingly actually, found out I'm right and something needs to be changed or corrected! (from architect designs, timber frame structural elements, roofing construction and roof light installation). Micro rant over. Thanks for this - I will be re-visiting the ASHP / heat loss calcs (though I know it's 'just numbers plugged into a software tool' - hence my interest in learning the calcs).
-
Well I have been pleasantly surprised by the UFH supplier - they understood my request to increase the spacing between the supply / return pipes, replace the utilities area and have re-done the design. Where they're still bunched close, I'll insulate so that there is an exposed pipe every 150mm. Here's the revised drawing for those who will be interested. UFH-FHW CAD Drawing Rev 2.PDF
-
Great to hear - thank you. Our ASHP installer is complying with the MCS requirements (which doesn't allow MVHR to be taken into account, and only goes down to 35deg flow temp), however, he knows exactly what we want and, importantly, he has done exactly the same in his own house, so there's making sure it can achieve the MCS sign-off, but able to modulate down low enough to run efficiently as very low flow temp. They even audited his house as luck would have it and it still met the requirements for the BUS grant, so after being initially frustrated at the MCS / BUS restrictions, I'm happy I've found an installer who understands how to comply with it whilst delivering what we want.
-
They knew exactly what we planned to do and we gave a very clear requirement. I'm getting very used to this 'quality' of output from the suppliers / distributors etc. now though. Speaking to my builder, it's entirely 'normal' and he spends a large amount of time fixing design issues on site. Unfortunately it also only works on windows and I'm loathed to by a PC or try and set up a virtual machine on my Mac just for this; this was why I went with a supplier who would be paid to do the design (having provided them with all the necessary information). #sigh... Is this a personal recommendation of this one, or has it turned up on a search (just wanting to make sure I understand before I look around). Thanks for the nudge. This is a good enough reason for me I think
