Bramco
Members-
Posts
777 -
Joined
-
Last visited
-
Days Won
1
Everything posted by Bramco
-
The lane the other side of the dyke has no owner - it's an access lane for people owning land along the lane. 7 houses and a farm and on the opposite side fields. I'm taking the email from the flood authority that I mentioned above as permission. The internal drainage board don't manage the dyke, it's too small. And while we might have a 'yes' from the flood team, there's the Env Agency rules and building regs. Do we have to comply with them all, or is there one that trumps the others? Simon
-
Hi, We have a dyke at the front of our property which used to run all the time when the gypsum mine at the end of the village was still working. Now it's dry, except for exceptional rainfall. The ground is clay with poor but permeability rates are nearly acceptable at the front of the property. Our SE has designed the drainage system as 2 massive soakaways. 26m3 each. So you can imagine the price we're being quoted by our contractors. Also, it seems ridiculous that we're contemplating burying a massive amount of plastic in the ground. It's environmentally crazy! The dyke btw now only runs when we get a biblical rainstorm overhead for a few hours. If you took the rainfall catchment area that contributes to this, then our development would be tiny. We're talking several sq kms against a normal house and patios. I contacted the flood team at the County Council and asked if 'we can simply run a pipe from a manhole at the front of the property straight into the dyke?' Their response was 'Providing there is no increase in flood risk as if problems were to arise from any additional flows, from a civil point of view you would be responsible as you made changes to the flow of water. Or the asset is not a highways asset. Yes you can connect.' It's not a highways asset btw. I should add that further downstream on the dyke, are a bungalow and 3 houses that all discharge into the dyke. The dyke eventually discharges into a brook which normally has water in it but that's a mile or so away. I think I need to convince BC that discharge to the dyke is OK but who do I have to persuade (BC or EA) to take a pragmatic view on this and what evidence do I need? Are there consultants who can help? Simon
-
LPA Missed Deadline on Non-Material Amendment
Bramco replied to harry_angel's topic in Planning Permission
It does beg the question though whether anyone would ever check that things hadn't been done according to the planning conditions, given they take 4 months to answer and NMA. We amended window locations and cladding layout and some other minor points like security lighting has to be agreed - 'there will be no security lighting'. We didn't mention a reasonable height increase on the highest section of the build.... ? and things were done in 28 days. What were you trying to amend? I guess if these were really minor things, then would they ever try to enforce the submitted plan, or simply shrug their shoulders and say, 'actually we'd have passed that if you'd submitted the plans with those changes.' Simon- 17 replies
-
- 1
-
-
- planning
- planning permission
-
(and 1 more)
Tagged with:
-
er yes..... In the current house we installed a heat bank with solar thermal (long time ago, wouldn't dream of it now) and I had to draw a very simple diagram for the plumber to follow - which he did perfectly. Electric install I did myself. It's been great especially since we installed PV and a diverter. All the trades working on the extension basically looked at the heat bank as if it was a starship. Having said that, the house is now up for sale and I can see a lot of viewers building in the cost of ripping everything out and putting a 'nice big' combi in.... And they'd be missing out on free hot water for 4 or 5 months a year... Simon
-
@IanR Thanks Ian - we may not make it under the old scheme anyway but gaming the system sounds like a great way to avoid doing what I should be doing by building an expert system..... Your experience with Eco East Anglia sounds like you found the right installer. Simon
-
But if your build is highly insulated, airtight etc, then the RHI ain't going to be worth having as against the extra costs of the MCS install. But it's almost impossible to find installers who will do a non RHI install, Everyone adds on this chunk regardless - and some who behave like the old double glazing salesmen taking money from gullible people. So I guess, where I'm going is - which are the installers out there who will give a proper quote based on supply and install with no frills? Simon
-
I've never understood why companies ask £10-£12k for an install when the parts are about half that. What value does an 'MCS install' provide? Simon
-
We had a room heat loss analysis done by a consultant which checked out very well with Jeremy's spreadsheet. Similar U values to yours. Our peak hat loss is expected to be just over 5kW at -3.6C so roughly in the same ball park I guess. No experience yet as the TF is only just nearing completion. Simon
-
Patio drainage without soakaway?
Bramco replied to ashthekid's topic in Landscaping, Decking & Patios
Is there an equation for working out the size of a soakaway based on the area to be included and the permeability of the soil? At what point can you realistically get BCO to agree to draining the area into the main sewer? Our plans include a HUGE soakaway that will bury loads of plastic in the ground at a v large cost. We'd love not to have to do this (or put more money in the ground, the foundations cost enough!) Simon -
So we've just had tender returns and it looks like the renderers have quoted to render the whole building which will be mainly metal clad with some timber cladding and only the rest rendered...... Think they have just measured up the whole house and quoted for that. Our QS has a trade intelligence index after years of experience. To quote, she said: 'Renderers are the most stupid, plumbers not far behind, electricians show a spark of intelligence.' There must be more to the league table and I wonder what the trades think of QS's? Simon
-
We started about 2 months ago and I'd forgotten they'd said they would put us on the urgent list after my 2nd call. And we'd about given up and had decided to use a 4G/5G router instead. So it was a surprise last week when I was given a date for a surveyor to visit. Well before the date, on a wet morning he called, he lives locally and could pop round. After a bit of discussion he agreed that if we would put the duct in, they would connect from the bottom of the pole outside the property. It's a private lane with a grass verge where the pole is. He asked me to pace out how long the duct would be and to let him know how many corners there would be and he'd get the ducting etc. delivered. They would call before delivery. Of course they didn't, but all the gubbins arrived yesterday. Think I'll ebay it if we go the 4G/5G router although it can't be worth anything given they hand it out willy nilly. Simon
-
MBC Frame - Windows - When to order ?
Bramco replied to bob the builder 2's topic in Windows & Glazing
Express in Leeds and Roofmaker in Leicester. Lots of reasons for selecting them rather than any other suppliers. For example we hate the bump at the top of Velux rooflights..... Our build will be roofed and clad in black corrugated metal - so not sure that weight is an issue for us. Also because our sliders are quite wide, MBC have designed steels above all of the openings and we have a guaranteed 2mm deflection on these openings. Sounds like a good plan, I'll talk to the window installers when they start to see if we need to do something similar. Simon -
MBC Frame - Windows - When to order ?
Bramco replied to bob the builder 2's topic in Windows & Glazing
You need them in as soon as possible after the TF erection is completed. Any delay can delay your airtightness test because the build needs to be wind and watertight before that. We ordered from the plans - although having said that, they were the plans from the architect. MBC designed the frame based on the structural openings in the architect's plans and these were what we signed off on. They are then contractually obliged to build to the signed off spec. If they don't, they have to fix it. What this means is that you have to juggle the lead times of the windows people with the information you are getting from MBC about their start date on site and likely completion date. For us the windows had 10 week lead time, so they were ordered as soon as we had the dates from MBC. Unfortunately like some others on here, we received an email from MBC about 10 days before the build start date that unfortunately they had had an issue with wood deliveries and they couldn't start until 4 weeks after the original date. That's when the fun started. The rooflight company wanted a stupid amount of money for storing the rooflights after the agreed delivery date, so we could only delay them by a week. The plan was that MBC would start on the garage and it would be up and completed by the end of the 1st week of the build. Unfortunately the steels didn't arrive, so there was nowhere to store the rooflights safely - we have found a safe spot now. The garage is likely to be the last thing completed... With the windows, it depends on the supplier and whether they are doing the install. If they are doing the install as well - which is our case - then if there is no slack in their overall installation program, then you may find you are at the back of the queue again with a long delay. We were fortunate in that they could delay us by a month. MBC should finish the build this Friday (yee haaaa) and the windows will be delivered and installed on Monday week, so 10 days after MBC finish. To give you some reassurance, I went over all the structural openings with the architect last weekend checking the measurements. They are all within a few mm of the spec and don't forget that the window manufacturers all allow for some tolerance of up to 10mm, these things aren't a friction fit. Simon -
A lot of 'intelligent' thermostats are unsuitable unless you've got the right type of system. The Nest thermostat was designed for the US market and I'd be surprised if the intelligence works with our systems. But then, our heating regs make you put a central thermostat AND trvs on radiators. So the radiators will slowly turn themselves down as the room gets up to temperature - but if the room where the central thermostat is gets too hot (sunny day) they might open up to accept more heat but it won't be forthcoming because the central one has turned the system off. Madness. Simon
-
Kevin hi, Just re-reading this thread and realised that you are also cladding your build in corrugated steel - can I ask who is doing this for you? We've found a couple of companies but are still looking around. Simon
- 26 replies
-
- sips
- heating system
-
(and 2 more)
Tagged with:
-
Hi, now I understand the comment! ? However, I should have added I guess that the UFH is built into an insulated slab and the house is almost PassivHaus levels of insulation, so we'd be following the advice from other members with similar construction to heat the slab once or twice a day and not use thermostats for every room. So there shouldn't be an issue of the ASHP turning on and off. Simon
-
Hi, We'll be following the advice to fit a buffer store between the ASHP and the UFH in our new build and it occurred to me that the size of the store required might be dependant on the volume of water in the UFH pipes. We have 12 loops, each about 100m in length. Would 50l be enough, too big, or just right? Simon PS apologies if this has been asked before
-
Here it is -> From what I understand it's a lot easier than it used to be - ASHPs have been improving over the last few years as manufacturers add new features and the rest have to catch up. So they are all quite similar in terms of features (someone will no doubt be along in a while and say the opposite!). From reading the forum though some are apparently easier to program than others - although once programmed, you probably won't have to use the interface again in years, so maybe even that isn't really an issue. Simon
- 26 replies
-
- 1
-
-
- sips
- heating system
-
(and 2 more)
Tagged with:
-
The digger driver doing our culvert snapped the BT line to next door - Openreach have a 24 hour service to fix things like this. I bought him a fridge pack of Magners cider and he seemed OK.... Our roofs and the cladding on the 2 storey section are black corrugated steel - one contractor has mentioned up to 16 weeks lead time..... We used an M+E consultant to do heat loss calcs - there is a spreadsheet on the forum which you can download and dial in your U values for roofs, walls and floors etc. - I had used this earlier and it confirmed what the consultant's report said. Gas would be an arm and a leg as there isn't any down our lane. Even so, I think we'd be having an ASHP installed. We're having PV installed and when our car packs in, will replace it with an EV which by that time, we should be able to use as a house battery - so should be relatively self sufficient. There's lots on ASHPs and RHI etc. on the forum. If you can't find the heat loss spreadsheet, let me know and I'll find a pointer to it. I'll PM you about where we are in case you want to cycle or drive over to see our build. Simon
- 26 replies
-
- sips
- heating system
-
(and 2 more)
Tagged with:
-
Hi Kevin, We're very local to you. Our timber frame is going up at the moment - the first lorry load arrived on Tuesday. Hope you had an easier ride from Rushcliffe than we did with your planning. If only they'd done their job properly, we'd have been in the new house before Covid and missed all the current shenanigans around shortages of materials and labour and the cost increases... Are you doing the rest of the build yourselves, or have you contracted a builder? Simon
- 26 replies
-
- sips
- heating system
-
(and 2 more)
Tagged with:
-
Hi Dan, I didn't want to say it's complex. My understanding is that it requires special cabling - so adding to the cost. The industrial shields (link above) is Pi based - but then you'd need to be installing HA or something similar and then of course you have to manage that over time. And there are alternatives to Shelly, like Moes and Sonoff. I've used quite a bit of Sonoff kit and it seems to work fine although if you don't want things to go through their service, you need to reflash with ESPHome, Tasmota or similar. There's an interesting Kickstarter just started from Sonoff which I saw today -> https://bit.ly/3BDX7eM. It's a wifi panel with a lot of functionality built in. Sonoff NSPanel Smart Scene Wall Switch. I've backed it as they looks as if it might be something I could use. About £50 with shipping.
