Jump to content

GRP (God-awful Rubbish Period)


canalsiderenovation

7423 views

I'll start with the GRP roof but I'll dedicate this whole blog entry to which I will deem the God-awful Rubbish Period. This probably seems like I'm over exaggerating but there's just been a lot of things combined with work, personal etc and I have really been feeling the pressure.

 

Intially, as they started laying the fabric the GRP looked OK but, despite what I would say is perfect conditions for the GRP going on from what I know through reading on here we, were appalled by the quality of the work. Without bombarding this blog with pics unless you really, really want to see them, just take my word for it, it was bad! I believe I this was subcontracted but as we have not been on site I think it's been done by the builder themselves.

 

Needless to say I was not happy so met with the builder who muttered something about weather and acknowledged it was poor. There has been some improvement but I can't say I'm entirely happy but I believe this will be rectified, hopefully. I also raised the issue of the rooflight upstands not been GRPd to the roof and something is happening with lead flashing so I'm hoping that will be rectified too.

 

Here is the current GRP as it stands, comments welcome because I don't know if I'm being over picky but I want to be prepared for meeting the builder this week so please give me your opinions.

 

IMG_20200916_190741.thumb.jpg.a13dac9609fd465413a131560f0bc652.jpg

 

IMG_20200916_190512.thumb.jpg.cd83db8bc799ea0dcb9d047c78bde5d1.jpgIMG_20200916_190441.thumb.jpg.e21120d31843dc45b19abf8dc52254e0.jpg

 

IMG_20200916_190329.thumb.jpg.9b67b4edba90aeb7bb77c9039615b2e7.jpg

 

Roofing aside, thanks to the people that contributed to the thread on our ASHP and solar @PeterW and @ProDaveothers as I really feel I would have had a complete meltdown. For some reason the idea of fitting a PV immersion controller seemed to cause all sorts of issues and it's literally blown my mind trying to explain to people that should know more than me how to do it and what is needed. 

 

And my final rant, how is it despite giving delivery drivers instructions they still turn it in an articulated lorry the size of a double decker bus.... er no you will not that over a canal bridge! Took delivery of a bathroom suite after it was pump loaded over the bridge with the lorry blocking the farm who were not happy and finally unpacked it to find the whole lot was damaged. Can't get the same items now as they are out of stock but in some good fortune the bathroom company decided it was far too much hassle to collect them again so let us keep them and refund the money so we can flog them to try and pay for an alternate suite.

 

We did finally get all our 12 panel GSE 3.84kw PV system and immersion controller for under £2300 which has now been delivered which is a relief.

If the builders make as much of a dog's dinner of fitting this as they did of the GRP I'll have an absolute breakdown ?

 

 

79 Comments


Recommended Comments



16 minutes ago, epsilonGreedy said:

@canalsiderenovationThe roof is not going to fail calamitously during a single winter so have you considered pausing, getting your sanity back, taking a few months to digest various expert opinion and solutions, then implementing the favoured solution with a surgical roof replacement early next summer. 

 

Not an option unfortunately, whatever solution is needed it needs to happen. We have managed to negotiate an extra month in our temporary accommodation until the end of November already but we have to be back in the house then (and we will probably murder one another if we both have to carry on working from home in the static).....

Edited by canalsiderenovation
  • Like 1
Link to comment
7 hours ago, Nickfromwales said:

Do you think they’d be better off feathering in a fall with layers of mat and gel coat? Doesn’t look like it is “miles off” to me? 

I would run the sheets to within a few inches of the edges, then to fill the height difference between the top of the sheet and the original GPPed roof, with a bit of 1/4 round timber in.  This will make it very easy to 'wrap' the new GRP around.

Any timber that is laying on the old GRP roof will need to be tanalised (or made from anything rot proof) just in case there is some residual moisture.

And those edges need to be ground back and the new GRP laid on top.  Should not need to change the flashing/trim.

 

I don't think this roof will fail and I suspect that the bits that look like they have delaminated are really just where it cured before it was rolled down.

 

Out of interest, how much have they charged for the GRP part of the job?

Link to comment

We have emailed the builder now having considered his option and have stated we want the roof completely replaced, with a fall and insurance backed guarantee. Had he done it right properly all this could have been avoided. He's not going to be happy but like it's been pointed out already he must have known and could have put it right at various points instead of progressing. I only hope that he protects the rest of the house when he takes the roof off....

  • Like 2
Link to comment

I think that's a wise move. My thought was yes his idea may work, but what happens if there's an issue a year down the line cos of the extra layer, is he really gonna be interested in coming back to sort it when he has your money.

  • Like 1
Link to comment

Create an account or sign in to comment

You need to be a member in order to leave a comment