Jump to content

Blogs

We need to be trussed up…

Blogging: an activity where the perpetrator converts trivia into prose and in doing so reorganises their own otherwise disordered mind.  Possible side effects: perpetrator enhancing feelings of self importance; boredom amongst those reading; history being rewritten.    I find it interesting to contemplate why I don’t have quite such a burning need to blog at the mo.  I’ve always enjoyed working with wood and metal and power tools.  And that’s what I’ve been playing at for the last thre

G and J

G and J in The house itself.

Week 13 - Floor insulation, electricity, battens, and… scaffold down!

Floor The main focus this week has been laying the DPM + 220mm PIR floor insulation + 50mm upstand insulation round all the walls, then the UFH perimeter expansion strips and the vapour separation layer ready for the UFH pipes.   It’s proved intricate work.  Ken our first fix plumber assisted by local builders Barry and Jordan together have been working hard to complete the task by the end of August so that the liquid screed can go down during the first week in September.  

Benpointer

Benpointer in General

Getting there, and time to sell up

Don't Panic - we're not selling what we've been building.   Back at the end of April (I thought it was longer ago than that - time either slowed down or we sped up, not sure which) SWMBO had just had a toe joint fused together to try to resolve a long period of pain following the critical infection she got over 3 years ago. We're pleased to say that it seems to have done the trick, and she has now rejoined me in getting the house ready for habitation.   I left you all with an

BotusBuild

BotusBuild in Moving

Week 12 - Windows, doors, battens, roof, …and more insulation.

Very busy again this week - we were probably running at the maximum people we can have on site without contractors getting in each other’s way.  On Thursday we had the carpenters, the insulation team, a roofer and the window installation team on site, and it’s not a very big site.     Windows and doors The main highlight of the week was the arrival of the windows and external doors on Thursday together with a team of four (from Ukraine, though the windows were made in Estonia).  T

Benpointer

Benpointer in General

August Update

Summer nearly over?!! That was quick! Weather has been brilliant though! So where are we 2 months on? Here we go:    Bathrooms are tiled and ready for plumbing the fixtures in. The plumber returned briefly and I now have a working toilet! Portaloo returned! Just no running water, well kinda! I got the water connected to the mains but it's not plumbed upstairs or anywhere yet. I put a speedfit valve on the 25mm mpde mains coming into the house so I can at least use it to fill buckets, b

mike2016

mike2016 in kitchen

Phase 2 floor pour

Time moves on and so does the build, albeit much slower than most of the builds featured in blogs.   Over the past 4 months we have dug out, cleared and prepared our 2nd phase ready for the groundworks, as in all the stuff that goes in the ground, costs lots of money and is never to seen again.    The next wall to be replaced and the old roof to be removed. This is one of the original walls, but it only had 200mm foundation so was not saveable.    

LSB

LSB in summer 2025

Week 11 - Solar PV panels.

A quieter week this week but good progress nonetheless.   The main build focus this week has been on the south-facing single pitch roof which is to be covered using in-roof solar panels with slates around the boundary, then zinc facias to match the rest of the roof.   It seems the zinc roof guys don’t do slate roofs and the slate roofers don’t do zinc, so two roofing teams required.  Fortunately, both teams have been excellent: professional, tidy, friendly and turning up when

Benpointer

Benpointer in General

Nearly a complete walls up….

On your marks: Get set : Wait!   Day 1 of panel erecting was rained off.  Humph.  I tried to pretend to be human again by popping into town with J for a spot of bargain hunting (for stuff we don’t need, natch) but inside I’m still a self build automaton.  My recovery won’t really start till we move in methinks.   Next day we start the day by admiring my new paddling pools. The previous week I carefully swathed the piles of panels with tarps before it rained oodles.  Good theo

Week 10 - Membranes, cellulose, zinc roof.

A longer than usual blog - we’ve had a lot going on this week.    We definitely reached site capacity with five vans and seven contractors on-site on Thursday and Friday.   Seven pallets of cellulose bales arriving mid-week didn’t help space management either.     The whole week got fairly stressful but somehow we seem to have got through it.  Phew!   Membranes The plan was for the team from SW Insulation to fit the VCL membrane to the vaulted ceilin

Benpointer

Benpointer in General

We have a plot!

After many years of searching, we finally have a plot!   Our offer on this plot was accepted in March 2024 and we've only just now completed. But we're excited that it's finally done and we can move forward.   Next steps:   We have an architect already and a set of draft plans. We'll be working to finalise these plans and take them to planning. The site has detailed planning permission already, so we'll just be looking to vary the design -- and not significantly so

AshleyFae

AshleyFae in General

Week 9 - Zinc roof.

As mentioned last week, the zinc roofers asked if they could start a week early(!) and so, on Monday morning along they came - Brian and Tom from Wessex Metal Roofing in Salisbury.  The first couple of days were mainly rolling out long zinc profile sections from the back of their van, then these proceeded to be fixed on to the 18mm ply sheeting that Alan the Chippie had laid the previous week.     Three triple-glazed electric Veluxes arrived from the builders’ merchants (I f

Week 8 - And pause... or not.

Last week our timber frame structure shot up.  This week was supposed to be the second week of a two-week frame installation but the team finished on Tuesday, having worked through the weekend.  And off they went, but not before I persuaded them to stand still for 30 seconds for a snap for posterity.  So here they are: Brandon, Jake and Callum - Great work guys!     Their early finish allowed our chippie Alan to press on with the 18mm ply required over the roof for the zinc

Still not quite to damp…

Forgive me holy Bill Dub, it has been many weeks since my last confession: and in that time I have uttered much profanity and at times, I have edged a small way towards despair.  I used to think I was good at working alone, and I sort of am when I have confidence that I have a good idea of what I am doing.  The other thing about working alone is that it’s dangerous - especially with net access and faceache marketplace.  Guess who now has a fridge freezer in the site hut (vital, darlings) and a b

Week 7 - We have a house!

…well, the shell of a house at least.   What a crazy week.   We chose the factory-built timber frame route because we like the idea that the shell goes up within a few weeks.  But the pace of progress this week has been startling.   The frame erection team of 3 arrived at 7:30am on Monday. A big yellow crane arrived at 8:00, with the frame arriving on an artic by 9:15.  First off: a careful check shows that the frame fits the footings. Hurray!  In fact the footings were withi

Week 6 - Scaffolding - and budgeting.

A relatively quiet week this week - the lull before the storm (hopefully not literally!)     The scaffolders arrived to put up a single-lift all around the exterior on Thursday and Friday (and Saturday morning as it turned out).  I say single-lift but there were due to be a couple of hop-ups for the gables on the south-facing roof.  However, at one end the gable is over a canopy roof which means the first lift is 2m away from where the gable will be.  We've left that one off for now -

Week 5 - Block and beam floor.

We’ve had another very good week of progress by the groundworks team and they are pretty much done now bar some further levelling of the paddock area and one or two other minor details.  We are really pleased with their work and the Building Inspector is pleased too, thankfully, so our foundations are all signed-off 👍.   Bizarrely, it’s only now that we can submit the “Commencement Statement” for our construction to Building Control, which I duly did this week.  Also bizarrely, we are

Week 4 - Out of the ground, just.

Great progress by the groundworks team in sweltering conditions this week - laying concrete blocks in the sun when it’s 30deg C and 80% humidity can’t be any fun at all.     Despite the heat, by the end of the week our foundation walls are in and ready for the block and beam floor this coming week.  We can really see the house take shape now, although quite a few of the foundation walls are just there to support floor beams and won’t appear as internal walls above the floor.

Inside to outside to inside again

With a few hot days I decided to plunge into fixing the outside drainage. These had been marked the wrong way around on the surveyors map which carried onto the Architects drawings which made its way into the construction drawings and the groundsworker dutifully connected up as per these last year. It was only a few months ago I noticed backflow of sewage in what I thought was the storm drain and discovered the difference between 4" sewer lines and 6" storm drain lines!! Unfortunately the 4,000

Week 3 - Drains and other hidden things

The groundworks team have been putting in the Sewage Treatment Plant and drains this week.  We’ve chosen the Klargester Biotec+ 2 STP and that arrived on schedule from Tanks Direct on Tuesday.    Also this week the concrete pads were dug and poured for five oak posts that will support overhanging roof canopies - the Building Inspector asked us to put in 1m x 1m x 1m pads which seems excessive for 150mm x 150mm oak posts taking point loads of 5-10kN but it was that or pay the SE for (p

A pause for breath… (& to take stock of cost of foundations…)

Well, sort of.  Working physically hard is sooo emotionally easy compared to the frenetic whirlwind of strip foundation digging and filling.   If that means that to you, I sound an emotional fruitbat then I commend your perceptivenes.  I find it impossible to predict in advance the bits that will be most stressful.   In the last two weeks I’ve had all but two days on my own on site, as Steve has been on his hols.  So it’s background organisation tasks and planning for the most part.  T

Week 2 - Foundations

The excellent SE we contacted on Thursday to design the depth of our foundations came back on Friday with the answer - deeper than we wanted at 1.95m in the corner closest to the neighbouring oak (15m away) but his quick response has saved the schedule.  We need to add clayboards in the corner nearest the tree but overall it could have been a lot worse.   His rapid turnaround was brilliant and it meant we were able to crack on this week.  The groundworkers had already discounted Monday

Week 1 - Breaking ground

Our groundworkers arrived on site as promised on the Tuesday after Spring Bank Holiday.   Raining all day of course!  Though tbf it’s fairly light rain.  They made a good start removing a concrete slab left over from a long-demolished, clearing the oversight and creating a temporary spoil dump site on the paddock.   Three issues this week:   An unexpected armoured cable is discovered on day two - our groundworker Marcus is unsurprisingly cautious.  Quick call to our electrici

Let the fun begin!

We’re starting our build so I thought I’d attempt a blog.  I can’t promise to keep it up throughout the build but I start with good intentions.  Apologies for the inevitable typos along the way.     A bit of background:   We have previously done a lot of alteration and refurb projects for our various homes over the years, the most recent a major eco- refurb and extension of a 1960s bungalow.      Last year we decided to bite the bullet, sell the house, buy a plot an
×
×
  • Create New...