So, The surveyor from UK power networks came to the plot today. Cost to provide electrical supply will be about £6.5k. The total distance they need to dig to bring the supply to a box on site. is..... Anyone want to guess. About 20 feet As it happens the difference in price between 1ph and 3ph would be minimal. Does anyone know if there are other organisations that can competently do the dig part at a better price.
-
Cost to get Utilities installed
Post and beam replied to IronMike's topic in General Construction Issues
Also building soon in Hertfordshire, off a country lane. I spoke to UK power networks just this week and theya re sending a surveyor on wednesday to quote for the temporary supply & subsequent house supply. No cost for this survey and they will provide a written quote. No brainer really just ask them to come and survey your plot. I dont know about water, they have not responded yet. -
Possibly, yes. But having said he was experienced and then later in the conversation exposing the fact that he actually was not i think i am justified in letting the gentleman pass.
-
I wish. More like about £5k now. Welfare facilities for the archealogists. Open ended upwards from £5k if they decide they want to do more. One firm wanted to reserve the right to call a sight meeting with the county archealogist at £95/hour billed to me when and if they decided to do so. You will understand why i am wary of the whole circus.
-
Just to be clear, the village is already an area of archealogical interest. Dont know who decides that but it means a desktop survey wont cut it. It turns out that the convention the county uses ( Hertfordshire) is 'trench 5% of the area of the site in the area of the footprint of the project'. The people i have consulted are aware of this but i was not. They have to submit a written submission of work ( the WSI) it gets approved by county, they dig the trenches and we all hope that nothing is found. Guiding principle seems to be. Anything found will likely mean more work is required and i will have to pay for it, and accept the inevitable delay. They decide what needs to happen with no recourse from me and i just write them a blank cheque.
-
I agree, up to a point. If the guy puts himself forward as competent then i expect them to be.
-
I asked a prospective builder about ASHP and MVHR. It was clear from his response that he thought it 'new fangled technology'. In my head the meeting ended at that point. He was a nice genial old boy and i am sure he could build me a solid driveway. Just not the house. I am still looking
-
Obviously the type of seal on a sliding sash window is going to be less effective than a traditional casement. But how much less effective? I have been investigating masterframe sash windows, they look good. But if they are not compatible with a highly airtight build then i need to abandon them as an option. Is anyone else using them and achieving good ACH figures or is the whole idea stupid?
-
Or get someone like Potton to turn the planning drawings into something that can be built. Although Potton are relatively expensive they would do all that is required to get the thing built right.
-
When the power company surveyor arrives i want to be as informed as possible. Do i need to ask for/demand a specific current capacity. EV capability or anything tht i am currently ignorant of. The house will be a 200m2 detached. I need an ASHP. If its not too expensive i might request an EV capability. Is there a specific location in the house that the CU has to go or is it down to me. What have i forgotten? Thanks in advance as always guys
-
Hello - Self build on the coast of Scotland
Post and beam replied to Clubtropicana's topic in Introduce Yourself
Nice rendering -
Yep, complete Bo!!ox. Is it likely that architects designed ' just enough' strength into Multi storey car parks.
-
Do you have a leak? Dirty water sounds a little worrying
-
Fogg What i can say about my Potton experience is that the planning permission submission that they talk about is not part of their house design service. It is a referral to agents of theirs and cost me £2.5k. Then £6.5k for trial pits/foundations design.
-
I am having a Potton House built soon. Have planning permission and a design from their older style range. A couple of others on here as well. Your design is very modern looking.
-
Thats a real shame for the OP. My 'standard' permission requires start within 3 years. I asked, and digging the footings is the minimum recognised as starting.