flanagaj
Members-
Posts
1192 -
Joined
-
Last visited
-
Days Won
2
Everything posted by flanagaj
-
I really need to hire a pump as otherwise, there is going to be a lot of manual raking
-
I have just called around to get a quote for 24m3 of C25 and have quotes from £120/m3 to £191/m3 Given that concrete is something that you don't want to get wrong, is there anything I should be aware of here as that is a massive difference.
-
It was quite fortuitous. I heard a knock on the door and the BCO was stood there. Turns out, that he got the wrong Thursday, but he was ever so helpful and fully understood about inspecting the rear trench and allow us to crack on.
-
So, on that basis it should be viable to pour in one hit
-
Plan was to pump the footings in one go. 24m3 of concrete. Is this not possible?
-
I have started to realise that using the TA recommended by my brother in law was not the best decision. He has drawn the footings as below (300mm strip) My plan is to increase the depth of the footing by another 225mm. This means I would have effectively 3 courses of block below FFL. I want to avoid having to put soil pipe through the trench and ideally want to have the pipe go through the blockwork via lintels. Otherwise, I need to get some oversized pipe in place for when we pour (next Friday). The invert level of the lowest IC is 550mm below FFL, so I cannot go too shallow, otherwise, I will have to put the soil pipe through the trench footing.
-
Can I ask why you had the vertical rebar in the foundations?
-
I eventually found a chap with a nice 2022 3CX JCB. He graded the whole site today and has told me he'll pull the footings in 2 days next week. Can you tell me a bit more about the other points. Especially, around the concrete line pump. I have calculated that I need 25m3 of C25 concrete and the furthest point from the truck will be 16m, so I assume a pump is the way to go. Will building control be happy to inspect the footings before they are all fully completed as it will be difficult to go back over the rear footing once it has been pulled and the other footings are done.
-
-
I am slightly confused. I thought an IC is used for rodding the main drain run, but to also be able to rod the branch line pipework that connects in to the IC. If I remove the two IC to the West of the building, how would you rod the branches?
-
I'm going to bin off the chap I've lined up. He like many, are mainly landscaping / patio contractors. So probably not the best choice for getting footings pulled quickly.
-
Point taken. I think I've chosen wrong people for this job as there are telling me 10 days all in. I agree with you. It's a 2 day job with a decent machine. One groundworker who I didn't use, recommended i pulled and poured the garage first and then pulled the house footings and then joined the old and new footings with rebar resin bonded into the earlier poured footing.
-
I've got a 3 ton dumper. Hadn't considered a 5 ton machine as that would make quick work of it.
-
Ouch. That looks like a world of pain.
-
My original plan here for excavating the footings is as follows. 1). Pull the North footing to depth. 2) Pull the 6 vertical footings to within 1.5m of the South footing 3). Pull the south footing 4). Join up the remainder of the vertical footings with the south footing If I do this or do get the groundworker to do this, it would mean that the North footing will be exposed for a few days before the concrete is poured. Would people do it this way or would you pour and shutter multiple times to avoid leaving footings exposed for a few days?
-
Sorry. I am due to start tomorrow and have 2.7t excavator arriving in the morning.
-
I haven't got anything booked in so no big deal if we postpone
-
We are due to commence development tomorrow, but the weather forecast is looking wet and now I'm wondering whether to just get started and deal with the consequences should any arise, or do I push it back and accept more delay. Just not sure what to do.
-
😂 I'm not sure what people were thinking.
-
With the US/Israel's illegal war in Iran, I'm getting concerned that they are going to create a potentially massive economic shock and we are going to see rampant inflation again like during COVID. What are others anticipating?
-
£280 per man
-
I cannot propose anything as I am trying to understand how I'd have a back inlet gulley when I have an ACO in the same place. TA obviously didn't consider this detail.
-
I'm not paying cash in hand, and said groundworker is charging £280/day in Hampshire
-
I used a groundworker recently and he didn't bring any tools. He and his labourer were constantly asking if they could use this and that. So many of tools ended up covered in mud. In the end I did say "do you not have your own tools". It's a conversation that I shouldn't need to have.
-
It's a kitchen sink, so I guess that will be deemed food waste. Looks like I'll have to have another IC on the drainage run.
