flanagaj
Members-
Posts
1224 -
Joined
-
Last visited
-
Days Won
2
Everything posted by flanagaj
-
I cannot comment on the sewage as we have a sewage treatment plant, but we simply requested the water company installed a new connection to a temporary building supply. They came along and inspected the trench a water stand pipe and then connected us up. Once that was connected you can then take a T off the supply to the caravan and then when ready connect up to your house supply.
-
Rest bends haunched. Pea shingle layers done as described. Picking out obvious foreign objects impossible.
-
The excavated soil from the foul drainage trench is very flinty and I wanted to ask whether I could backfill the trench using said soil if I cover the foul drainage with 100mm of pea shingle or should I get someone in to screen it first. Trying to avoid unnecessary expenditure, but also possible problems in the future.
-
On paper it looks fine, but I'd just check Part H document to ensure the falls work ok with the arrangements connected to each run.
- 1 reply
-
- 1
-
-
foul waste Foul drainage. Remove inspection chamber?
flanagaj replied to flanagaj's topic in Waste & Sewerage
Foul drainage installed with my own fair hands š -
foul waste Foul drainage. Remove inspection chamber?
flanagaj replied to flanagaj's topic in Waste & Sewerage
Thanks Mike. Thatās why this site is so helpful. I hadnāt considered doing it that way š -
Should builder correct bottle gulley mistake?
flanagaj replied to flanagaj's topic in Waste & Sewerage
Unfortunately, heās got a big ego and apparently knows more than I do. Iāve reached a stage where I cannot lose another bricklayer as Iām already starting to lose the will to live. In his defence, he is well known in the area for high quality work. The bottle gulley was used to avoid having to have a 450mm inspection chamber or an internal rodding point. -
The image below shows the inspection chamber at the beginning of the run. As the first toilet comes in on the branch and the main leads off to the external SVP which is solely there for the sewage treatment plant, Iām concerned that Iām potentially going to get a blockage as there is no flow coming down the main run. if I remove the inspection chamber, I can then route the pipe into the main channel of the next chamber. This will enable the pipe to be rodded. I am then not sure how Iād then branch off for the external SVP?
-
Electrical conduit for bringing armoured cable into house?
flanagaj replied to flanagaj's topic in Electrics - Other
With regards to the 100mm ducting. Do you simply just put a bend in it or do you buy a preformed smooth bore bend? If such a thing exists. -
Electrical conduit for bringing armoured cable into house?
flanagaj replied to flanagaj's topic in Electrics - Other
25mm2 The cable will be from the meter to the CU in the house. -
I have been putting in foul drainage this week and now need to put the conduit in for the 2 * 23 KVa cables that will come under the lintels and into the plant room. I do have a 54mm diameter hockey stick and was wondering whether to just put two of those in, or am I better off using another type of conduit? Thanks
-
Our plans clearly state that our sink waste was via a back inlet bottle gulley. Exactly as the image from Wavin below shows. The builder ignored my plans and instructions and decided to not put lintels in for the soil pipe to exit through the property. I then had a long argument with him regarding this and he said that you don't do this and a bottle gulley is used in the old school way, with the sink waste exiting through the wall. He's talking complete tosh and I have just sucked it up. The one benefit is that it means one less hole in the Radon membrane to have to worry about the detailing for getting it sealed correctly, the downside is an ugly pipe (albeit on the Northern side) which is just a path at the back that you don't really notice. But it's really niggling me and I am wondering whether coring a hole through the wall is going to cause other issues later on?
-
I'm going to do this job myself.
-
Just checked and their spec just states hardcore (looks like a lifted and shifted spec)
-
Just a general question for those who have been there and done that. I need to order 30m2 of type 1 or crushed concrete for the ground bearing slab. That equates to 72 ton and type 1 is £33.50/ton Recycled crushed will probably save me half that amount, but I wanted to ask what people's thoughts are on type 1 vs recycled. The ground below is flinty as anything and then it goes to chalk, so I don't think there are any concerns about settlement.
-
At my wits end with brick layers. Advice please.
flanagaj replied to flanagaj's topic in Bricklaying, Blockwork & Mortar
I will do that tomorrow morning first thing. And try and be diplomatic so he knows that I want it to that level. It's not bloody rocket science is it. The JCB driver who dug the oversite was within +/-10mm -
At my wits end with brick layers. Advice please.
flanagaj replied to flanagaj's topic in Bricklaying, Blockwork & Mortar
This is probably why I always seem to rub people up the wrong way. That's a diplomatic approach. Even when I did get my laser level out to prove that it was off, it went down like a lead below and was basically dismissed as my laser level must be off. I even then went to the lengths of checking both his and my laser level (both of which are correct) I was hoping for a "fair point, it's off and I will rectify the problem", but it's basically been left. -
I've refrained from posting on here for fear of asking stupid questions, but I have concluded that on this occasion, I really could do with some guidance. As you know, we let our first brickie go as his work was substandard. We waited nearly 8 weeks for the new one to start and he started Monday. He is making good progress and aside from not listening to me or reading drawings where service lintels are supposed to go, it's ok. However, when he started, I was really surprised that he did not build up the corners of the house using a laser level, to ensure that the height of the first course would be correct. Instead, he started at one end and made his way down the 24m length. He is now at dpc level on the internal leaf and he is 22mm out from one end of the house (excluding garage) 17m to the other end. Alarm bells are ringing in my head again and I don't know whether I should raise the issue. It's driving me mad that I have to deal with such incompetent individuals. I also had to explain to him that he had missed out the lintel for a back inlet gulley. His response "you don't run a soil pipe into the back of a bottle gulley. You put the sink waste through the wall and into it." Clearly, he is wrong, but I am just the dumb IT Programmer who knows feck all. Just after some help here, as I really don't want to sack another builder and start again.
-
Air hooks for Radon membrane
flanagaj replied to flanagaj's topic in General Self Build & DIY Discussion
The membrane isn't the issue. It's the cavity tray that has to be there. Maybe full fill under compression will happily stay suspended in the cavity. The drawing has a vertical membrane against the inner leaf, so using wall ties will mean breaching said membrane. -
I was given the following schematic diagram by St Goblain in relation to their suggested approach for a Radon membrane. Just wondering whether anyone know how you go about suspending insulation in the cavity with using wall ties? Visqueen are also showing a similar detail of insulation just suspended in thin air directly below the cavity tray.
-
Ok, I'll have a look. Considerably cheaper too.
-
I have a Topcon laser for exterior groundworks, but am now thinking of getting a 3 * 360 degree green laser level. I was looking at the premium Leica Lino L6G, but wanted to ask whether there are similar offerings that offer the same functionality, but slightly cheaper. Like a lot of my tool purchases, I will sell them on at the end of the build.
-
After the debacle of the last builder, who just couldnāt admit his work was rough, I decided to get https://www.tmcoatesjcbplanthire.co.uk/ back in to dig down the oversite ready for the next brickie that we have managed to get on board. Tim is an absolute legend and goes above and beyond when it comes to excavation tasks! here is a picture of our site (Iāve demolished the abomination left by the last incumbent)
-
It was a full plans application and yes we have planning. Nothing has changed in relation to the drawings and the builder who was partially retired bit off more than he could chew. I felt sorry for him, but the drawings clearly showed 7N blocks below DPC. The fact that he struggled to lay them accurately is not down to me. The joys of hiring trades in an area where you know nobody.
-
He said he was happy to do cavity blockwork. I'll ask the next bricklayer whether he'd prefer trench blocks.
