flanagaj
Members-
Posts
1190 -
Joined
-
Last visited
-
Days Won
2
Everything posted by flanagaj
-
Thanks all for putting my mind at rest.
-
One more final question before I close the topic of my concrete footings. Do I mist spray them, or just leave it?
-
😂 That's what my wife tells me. At this rate I'll peg out before the end of the build.
-
Pump was supplied by the concrete company. I think it's been a long day and when things don't go smoothly, you wonder what other corners may have been cut. Damn, I'm catastrophising again.
-
The volumetric was comparable at £140 m3
-
I'm sure it's fine. They are 525mm thick. I've asked the company to provide exact details of the 3 loads, as I want to know exactly what they did. I won't hold my breath though. I was wondering if I should cover the concrete and be mixing it or should I simply leave it. The brickie is scheduled to start laying on Thursday?
-
That's interesting. We never requested extra water and I've just checked the ticket and the driver checked that box. My wife who had nothing to do with the pour, signed it without thinking 😮💨
-
I just asked for C25 and as we used a pump, I assumed they'd do the mix accordingly as it was clear it was for footings. It was a volumetric supply and mixed on site, not ready mixed.
-
Just looking at the ticket and they ticked extra water added via customer request. We never requested extra water be added and I'm not sure if this is the default when you use a pump?
-
We got it sorted eventually and the two final trucks arrived together, but the buggers fleeced us and the driver went to my wife and she signed the ticket and we apparently used 29.5 M3, but my calculations were 24m3
-
It’s really frustrating. When you have ordered a certain quantity, they surely know that you need to get it all poured within a given time frame.
-
Order the concrete and was told that there would be two trucks arriving. One truck turns up pours and then we’ve been waiting an hour and still no second truck. We’ve covered up the concrete, but I’m getting concerned now.
-
Yeeessss we bloody done it.
flanagaj replied to Russell griffiths's topic in General Self Build & DIY Discussion
Lovely looking place Russ -
I am going to fire up the mini digger tomorrow at 7am and sort it out. We also don't have mesh. BC signed off the footings so too did warranty provider.
-
My wife and I discovered the channel below yesterday and it was uncanny similar to our story. Brilliant! When I see a man using a mini digger themselves, then in my eyes, they are a 'self builder' https://youtube.com/@self-buildfromplottohome?si=Migc64pM6lMZmcC8
-
As previously mentioned, I'm a catastrophiser and worry the house will collapse.
-
But this isn't a step. The footing is sloping down 200mm over a 6m run
-
I can't show a photo and maybe I wasn't clear, but the variation means that the concrete depth at the front of the garage will be 200mm thicker compared with the back of the garage as the finished top level needs to be the same height. I'm just concerned that the front of the garage will be bearing more weight down onto the ground than the back of the property and as a result, it will settle more.
-
I should have been more forceful here as I think the excavator driver I hired has monumentally xxxx up. We didn't pour our footings on Friday as the JCB broke down which caused a 1/2 days delay. We are scheduled to pour tomorrow am at 1000hrs, but whilst putting the pins in for the top of the concrete, I have spotted that the dug footings are 200mm deeper at the front of the attached garage than the back. The garage has a stepped footing relative to the house. If I am correct, this is a big issue and although the garage is single storey, I am sure the 200mm depth variation will just cause significant settlement variation and I have no choice but to shutter up the garage and pour it another day. The footings where the attached house is going are +/- 20mm I was contemplating getting up early and try and correct the depth variation myself. If I didn't have a working hours planning condition, I'd have done it this afternoon. Any pearls of wisdom?
-
If an internal soil pipe comes down the wall and exits the house via a rest bend, is the invert level of said waste pipe governed by the thickness of the floor build up, eg screed, 150mm PIR, 150mm concrete slab, sand blinding, hardcore? Or are those layers irrelevant by the virtue of exiting straight out the house? I am also scratching my head as to how I use a rest bend and Radon barrier to hat on said rest bend when the bend radius is quite large and the Radon membrane is underneath the concrete slab. This will mean that for the barrier hat to be sitting on the vertical pipe, the invert level is forced really deep. I had no intention of having to run a deep invert just because of a Radon membrane.
-
I do have a piece of ground that I can just dump the slops on. Someone suggested knocking up a plywood 1m2 sized container that they can use.
-
The brickie and his labourer are now coming along to assist.
-
What's the pea shingle for?
-
I'm already feeling very apprehensive. Being a catastrophiser, doesn't help matters.
-
So, I'm doing it with just the wife and I. We are having a pump though, so hoping that will negate any problems.
