Big Jimbo Posted April 5, 2019 Posted April 5, 2019 The only conditions attached to my Planning Permission is Materials. Cladding, Render, and Roof Tiles. I've put in to discharge these. Do you think i would have a problem if i started digging my foundations while i wait ?
nod Posted April 5, 2019 Posted April 5, 2019 11 minutes ago, Big Jimbo said: The only conditions attached to my Planning Permission is Materials. Cladding, Render, and Roof Tiles. I've put in to discharge these. Do you think i would have a problem if i started digging my foundations while i wait ? Yep I thought mine were being discharged on the Monday I had all the plant there Sunday They were delayed for a week and I was told to remove the plant off site
Ian Posted April 5, 2019 Posted April 5, 2019 15 minutes ago, Big Jimbo said: The only conditions attached to my Planning Permission is Materials. Cladding, Render, and Roof Tiles. I've put in to discharge these. Do you think i would have a problem if i started digging my foundations while i wait ? it depends on the wording of the condition. If there is a requirement for you to discharge the conditions before you make a start on site then the the conditions will say so very clearly.
nod Posted April 5, 2019 Posted April 5, 2019 3 minutes ago, nod said: Yep I thought mine were being discharged on the Monday I had all the plant there Sunday They were delayed for a week and I was told to remove the plant off site The barmy thing was It was the type of slate they were rangleing over Which wouldnt have effected us till much later on
Carrerahill Posted April 5, 2019 Posted April 5, 2019 (edited) 51 minutes ago, Big Jimbo said: The only conditions attached to my Planning Permission is Materials. Cladding, Render, and Roof Tiles. I've put in to discharge these. Do you think i would have a problem if i started digging my foundations while i wait ? It depends on what they have applied to your PP - the condition type will be listed. Are they pre-commencement or pre-occupation conditions? If the former you don't actually have planning yet if the latter you can start - there is also performance conditions which don't need discharged but yours is material so your going to be one of the "pre" options. Edited April 5, 2019 by Carrerahill
Carrerahill Posted April 5, 2019 Posted April 5, 2019 37 minutes ago, nod said: Yep I thought mine were being discharged on the Monday I had all the plant there Sunday They were delayed for a week and I was told to remove the plant off site So you must have had pre-commencement conditions. OP may have pre-occupation - which for material finishes tends not to stop commencement as founds etc. will not be seen.
Carrerahill Posted April 5, 2019 Posted April 5, 2019 33 minutes ago, nod said: The barmy thing was It was the type of slate they were rangleing over Which wouldnt have effected us till much later on I would suggest they are pre-occupation then...
Big Jimbo Posted April 5, 2019 Author Posted April 5, 2019 Thanks folks. Yep. Pre-commencement conditions, so i had better wait.......... You can bet i will get to the end of my 8 weeks and the twat won't even have looked at them.
Russell griffiths Posted April 5, 2019 Posted April 5, 2019 I e mailed our case officer stating that the choice of materials won’t make any difference to my foundation work starting and that we would provide samples ASAP, but wished to start work, he agreed in writing so we started we are just up to wall plate height and still haven’t discharged that condition. He didn’t think it was a problem as long as we don’t fit anything without sign off. 2
nod Posted April 5, 2019 Posted April 5, 2019 2 hours ago, Carrerahill said: I would suggest they are pre-occupation then... No commencement conditions
nod Posted April 5, 2019 Posted April 5, 2019 2 hours ago, Big Jimbo said: Thanks folks. Yep. Pre-commencement conditions, so i had better wait.......... You can bet i will get to the end of my 8 weeks and the twat won't even have looked at them. Wise decision unless like Russ you can get it in writing I rang mine everyday for a month trying to get mine agreed I think telling get the Harvey plant removed was payback
PeterW Posted April 5, 2019 Posted April 5, 2019 @Big Jimbo have you got all your CIL paperwork in then..? Or are you CIL exempt..?
Big Jimbo Posted April 5, 2019 Author Posted April 5, 2019 29 minutes ago, PeterW said: @Big Jimbo have you got all your CIL paperwork in then..? Or are you CIL exempt..? Exempt Peter. Although one i start i'm going straight back into planning for 2
hallega Posted April 16, 2019 Posted April 16, 2019 Because I started my build without planning (naughty...slap wrists) I am being charged CIL on two 2 storey linking additions to my silo's....O'h well, luckily it's not a fortune as they are small areas, about 9sq m. Lesson learnt....it could have cost me a fortune if the whole build was subject to CIL!
Recommended Posts
Create an account or sign in to comment
You need to be a member in order to leave a comment
Create an account
Sign up for a new account in our community. It's easy!
Register a new accountSign in
Already have an account? Sign in here.
Sign In Now