Alan Ambrose Posted 2 hours ago Posted 2 hours ago OK another tech question... We have a 50mm services void. I was planning to run horizontal cable trays, mostly high-up (2.5m above the floor) and split into mains & ELV / data (either using one split tray or two separate trays). Then a few vertical drops to light switches etc, also in trays if I can. And then fill any remaining void with, say, mineral wool. Question is - how do I avoid the mains crossing the data or is that OK? Something like this: Mains ------------------------!------------------------------- Data ------------------------!---------------!---------------- ! ! ! ! Mains Socket Network Port
garrymartin Posted 52 minutes ago Posted 52 minutes ago Perfectly fine. Crossing has fewer issues than running in parallel, and even that is not a big deal given the number of cables and voltages we are talking about in residential construction. 1
Recommended Posts
Create an account or sign in to comment
You need to be a member in order to leave a comment
Create an account
Sign up for a new account in our community. It's easy!
Register a new accountSign in
Already have an account? Sign in here.
Sign In Now