flanagaj Posted 21 hours ago Posted 21 hours ago We are in a Radon zone and require 'basic' protection. I contacted Visqueen to ask if they offer a design service, so I can understand the junction details. They came back an said they do offer a design service and it's £3000. I'm going to ask if they have added an extra zero by mistake 😂 I doubt they have, so I thought I'd ask what did those of you do who also found they needed Radon protection measures. I might consider an alternative supplier, if that's how they treat potential customers.
ETC Posted 21 hours ago Posted 21 hours ago I think someone’s taking the piss. Contact their local rep. They should be grateful to get the business.
flanagaj Posted 21 hours ago Author Posted 21 hours ago 4 minutes ago, ETC said: They should be grateful to get the business. That was my thought too.
ETC Posted 21 hours ago Posted 21 hours ago I’ve never had an issue. My rep was always happy to mark up my drawings. 1
ETC Posted 21 hours ago Posted 21 hours ago …..in any case your agent should be able to follow the Visqueen standard details…….. 1
Russell griffiths Posted 7 hours ago Posted 7 hours ago If I’m right you are having a cavity, check the details for this area in particular. 1
Oz07 Posted 3 hours ago Posted 3 hours ago How deep can these radon membranes go. Is there any reason they can't go flat below the insulation layer and just end up with membrane spanning the whole envelope of building. No corners etc. Any spine walls laid on top.
ETC Posted 42 minutes ago Posted 42 minutes ago Build up the sub-floor blockwork to the underside of the sub-floor. Fill the sub-floor voids with hardcore (maximum 600mm). Lay a 1200 gauge membrane - this is the standard gauge required by BC - over the complete footprint of the works. Overlap and seal all joints in the membrane. Install top hats to all service pipes and seal the top hats to the membrane and service pipes. Set up for a 150mm sub-floor slab bearing 100mm minimum onto the sub-floor blockwork. Place a 600mm wide strip of A252 anti-crack mesh to the perimeter of the works and across all internal walls. Install a stepped DPC to the perimeter of the works and build as normal. Membranes to be no lower than 225mm below FGL.
Recommended Posts
Create an account or sign in to comment
You need to be a member in order to leave a comment
Create an account
Sign up for a new account in our community. It's easy!
Register a new accountSign in
Already have an account? Sign in here.
Sign In Now