I have recently had some plumbing work done for central heating. The pipes shown are for three radiators, 2 upstairs and one routing to a downstairs radiator.

I would be grateful for any thoughts on this installation.

Plastic Pipe run.jpg

Metal plates.jpg

  • Like 1
Link to comment
Share on other sites

I am assuming from the way he has cut blocks to fill the gap, that the notches in the joists were there already?

 

It looks like a good job, a metal cover plate to stop nails or screws going into the pipe, recessed so the boards go down nicely, and a little bit of insulation so the pipes won't click and bang as they heat and cool.

Link to comment
Share on other sites

Thanks ProDave.  I cut the wood blocks as over the years, plumbers had cut the notches excessively. Fortunately a structural engineer did some calcs to confirm given the span of the beams, the meat remaining in the joist was OK. I put the blocks in to give some land for the floorboards to be screwed into. Now I can;t do that through the metal!!  Was thinking of putting some wood either side of the notches so I can have something to screw into. I don;t want the floorboards to creek and have to lift them up again.

 

Link to comment
Share on other sites

Post a picture of how the floorboard joint will land with regards the notch so we can see the issue.

 

It sounds like you need to get a screw closer to the pipes than the plate will allow, if doing that you have to be SURE you miss the pipes.

Link to comment
Share on other sites

I will put some timber on the joists about 30cm long 10 cm deep approx 25mm thick. The notch will be 20mm deep and 50mm wide so as close to the pipes as possible. I mark everything so make sure I clear the notch by 15mm. At least this to ensure the screw wont be too close to the edge.

 

Link to comment
Share on other sites

Yes a really neat job, but being the devils advocate I would have drilled holes centrally in the joists and threaded the,

 pipes through them (which you can do with plastic but not copper), then filled the existing notches fully so floor boards can be secured. (Sorry). I am a convert to plastic this being one of the many reasons.

Edited by joe90
Link to comment
Share on other sites

24 minutes ago, joe90 said:

Yes a really neat job, but being the devils advocate I would have drilled holes centrally in the joists and threaded the,

 pipes through them (which you can do with plastic but not copper), then filled the existing notches fully so floor boards can be secured. (Sorry). I am a convert to plastic this being one of the many reasons.

I’m guessing that there was already cut outs there 

Link to comment
Share on other sites

Plastic is the right approach, and insulting them as they pass through the wood is a great idea!

 

Drove my mad in my first house when they didn't do this, and every morning it's wake me up as the heating came on. Really bugged me.

  • Like 1
Link to comment
Share on other sites

They’ve used JG Speedfit, and as always there are no circlips installed behind the collars….. This is why I only use Hep2O (Wavin Hepworth) push fit in every permanent installation I do, and have done so for the last decade.

JG has the ingenious flaw of slowly undoing itself over time, and this will be 20X more of a concern with heating as it’s going hot-cool-hot-cool so will expand and contract for the rest of its serviceable life. 
Get the circlips (collets) LINK fitted before the boards go back down and sleep soundly. 
Copper is king, always will be, but modern push fit is perfectly acceptable when installed CORRECTLY. 

  • Like 2
Link to comment
Share on other sites

Create an account or sign in to comment

You need to be a member in order to leave a comment

Create an account

Sign up for a new account in our community. It's easy!

Register a new account

Sign in

Already have an account? Sign in here.

Sign In Now
×
×
  • Create New...