How long will a concrete floor take to dry enough to build on?


CalvinHobbes

Recommended Posts

4 days for non reinforced OPC ( ordinary Portland cement) slab

 

watch it doesn’t dry out to quicky with the nice weather we are having

 

watch the edges of the slab they may still be prone to damage

Link to comment
Share on other sites

What @TonyT Says. I had to spend the first day or so spraying our slab down as it was in full sun 20c+ weather. You'll know if its drying too fast when you see white patches forming and a crumbly / flaky surface.

Link to comment
Share on other sites