At the stage of my build now where the insulation will need to be put down for the first floor, my issue is the slab has some variance and I'm not 100% on the best way to deal with it. What have others done to level the slab?

Link to comment
Share on other sites

5 hours ago, Conor said:

Forget the PIR and use TLA. We had loads of variation and had steel beams to deal with as well. Didn't work out that much more and saved a load of labour.

Don’t forget that with TLA you’ll need a bit more to get the same thermal resistance as PIR. Otherwise a great way of dealing with floor variances in the sub-structure.

Link to comment
Share on other sites

On 01/05/2022 at 15:59, Adam2 said:

We used dry sand to level the precast planks under the insulation sheets

I had heard of that being done, its really only one room with ~20mm difference due to need to use a mix of precast and prestressed slabs. Does it work alright?

 

On 01/05/2022 at 16:35, Conor said:

Forget the PIR and use TLA. We had loads of variation and had steel beams to deal with as well. Didn't work out that much more and saved a load of labour.

Debating TLA but they're charging over double what pir would be. Who supplied your TLA Conor?

On 01/05/2022 at 21:54, ETC said:

Don’t forget that with TLA you’ll need a bit more to get the same thermal resistance as PIR. Otherwise a great way of dealing with floor variances in the sub-structure.

Wouldn't be as concerned about the insulation aspect as long as it was level for the underfloor

Link to comment
Share on other sites

12 hours ago, Conalmcn said:

Does it work alright?

Well I hope so 🙂 We had 2 floors in our build with precast planks that had both the usual camber and of course the gaps where they join each other. We just used the dry sand and placed boards on top then plastic then UFH pipes then screeded it - no issues that I can tell. The PIR boards were not rocking around and no obvious hollows. With the screed 55-75mm thick I can't see any small voids which we may have missed causing any issues.

Link to comment
Share on other sites

On 04/05/2022 at 06:53, Conor said:

@Conalmcn alpha flow screeds in Armagh. We dealt with Alan and Kirsty.

 

Once you factor in two days labour for levelling and laying PIR boards, there's not much difference in price. 

That's who I was dealing with. Works out around £1k more than doing pir for me

On 04/05/2022 at 19:07, Adam2 said:

Well I hope so 🙂 We had 2 floors in our build with precast planks that had both the usual camber and of course the gaps where they join each other. We just used the dry sand and placed boards on top then plastic then UFH pipes then screeded it - no issues that I can tell. The PIR boards were not rocking around and no obvious hollows. With the screed 55-75mm thick I can't see any small voids which we may have missed causing any issues.

Maybe worth going down that route then. Had debated using plasterboard washers and screwing it into the slab to keep it tight 

22 hours ago, Iceverge said:

 

Why the insulation on the first floor? 

For the underfloor heating pipes

Link to comment
Share on other sites

3 hours ago, Conalmcn said:

For the underfloor heating pipes

 

Unless your house demands very rapid heat response because of high heat losses via poor insulation and airtightness I suspect the insulation won't achieve anything.

 

For clarity we're talking about a floor above a heated room? If so just use the money and put more insulation elsewhere.  

  • Like 1
Link to comment
Share on other sites

11 hours ago, Iceverge said:

 

Unless your house demands very rapid heat response because of high heat losses via poor insulation and airtightness I suspect the insulation won't achieve anything.

 

For clarity we're talking about a floor above a heated room? If so just use the money and put more insulation elsewhere.  

I need it to clip the underfloor pipes onto. I dont need it for insulation as such. Its a 200mm concrete slab. Do you mean I shouldn't have any heat source on the first floor?

Link to comment
Share on other sites

I did question the real benefit of having pir on upper floors and was advised to keep it to make hearing more responsive. 25mm PIR is not that expensive so just carried on even though I feel it has little benefit as the aim is for the whole house to be same temp anyway inc floor structure but at least is something to clip ufh to!

  • Like 1
Link to comment
Share on other sites

On 06/05/2022 at 11:53, Conalmcn said:

I need it to clip the underfloor pipes onto. I dont need it for insulation as such. Its a 200mm concrete slab. Do you mean I shouldn't have any heat source on the first floor?

F389B068-F70F-435A-91D1-3660380CAEC6.thumb.jpeg.0e7c4eed780d9921db2aa5f1f5105807.jpegC6767E17-DDFE-438E-B61D-E0C5A26A1F70.thumb.jpeg.2b0170d9a35a00b789db1b46e6ddefae.jpeg

 

Gas nailed onto concrete, with clip rails.

  • Like 1
Link to comment
Share on other sites

On 01/05/2022 at 16:35, Conor said:

Forget the PIR and use TLA. We had loads of variation and had steel beams to deal with as well. Didn't work out that much more and saved a load of labour.

Hi @Conor, can I ask who you used for supply of the hollowcore slabs?

Link to comment
Share on other sites

Create an account or sign in to comment

You need to be a member in order to leave a comment

Create an account

Sign up for a new account in our community. It's easy!

Register a new account

Sign in

Already have an account? Sign in here.

Sign In Now
×
×
  • Create New...