flanagaj
Members-
Posts
1292 -
Joined
-
Last visited
-
Days Won
3
Everything posted by flanagaj
-
I purchased 4.8m x 2.4m A242 mesh sheets without flying ends. the way the sheets have to be laid means that there are some areas with 3 sheets overlapping. We are having a 150mm slab and the chairs raise the mesh 40mm off the bottom. I don't suspect that it is an issue, but just wanted to check as I don't want BC failing the inspection on Thursday and then having a mad panic to try and come up with a solution to fix the problem.
-
One other question. Do I finish the slab at the back of the inner leaf blockwork or should the slab come through the opening and finish level with the exterior leaf. If I do the later, do the bricks that close the cavity just sit on top of the lean cavity fill (left image) or should they sit on the concrete slab (right image) Eg, if you were looking at eye level from the front would it be the left or the right image below
-
Garage is attached. You are most likely correct that the cold bridging will be negligible and I can close off as per the diagram.
-
But how do you thermally break with PIR. Do you have a drawing or an image that shows this?
-
Can someone cast there eye over the image below and tell me whether this is the correct way for building the garage reveal. I want the garage door to sit behind the opening, but unsure how the internal block leaf will tie into the returning brick course and whether the cold bridging will be problematic. My plan was to then use a granite setts between the two reveals and up to the garage slab / DPM upstand.
-
Unfortunately, the brickie the groundworker recommended has retired and the JCB driver who dug the footings just keeps his head down and doesn't recommend trades.
-
Basingstoke
-
That is my concern as well. I think I have talked myself out of it already.
-
I've concluded that a combination of being height of summer and a job half finished is enough of a reason why those who come around to view our project never come back with the quote that they say they will. We have had 5 now, who have chatted for nearly an hour and left saying they'll have a quote to me in a few days, to hearing nothing more. Very frustrating, as I'd prefer a "not interested ..." I have just received a quote with respectable QS aligned numbers from a company that on closer inspection is nothing more than a intermediary contractor that must simply have bricklayers on their books that they subbie out. It's akin when I used to IT contract, the service was provided through an agency. We may have no choice on this as before long the mortgage company is going to start asking questions. Has anyone gone down this approach and if so, what due diligence can I do to ensure that whoever does the brickwork does it to a good standard. It does make me nervous.
-
I can vouch, that even living on site. Trying to project manage a build whilst holding down a full time job is very difficult. We are struggling to find trades and I suspect this is down to trades getting nervous when they see the project is being managed by me. As a result I have spoke with my employer and am fortunate that once the masonry work is completed up to plate, I am going to a 3 day week. I hate using trades as it is, as my experience is that a great many are xxxx and as it's not their property, they are not fussed about doing a great job, lke you would. If you really want a good start, I would advise that you get your plans quantity surveyed. I used estimators as they also provided a schedule of works. Although you will struggle to probably achieve the build in the same timescales as they indicate, it certainly helps you to understand estimated timescales for each stage and which trades will overlap. For example, the brickie will not be pleased if he gets to first floor and you haven't got anyone to get the floor joists in and the Cabodek flooring down. Same goes for having the materials for each stage ready too. Good luck and nobody said building a house was easy (unless you have deep pockets and just write the cheques and occasionally pop a hard hat on)
-
In that case, it will look utter xxxx
-
Given I have been probably wasting far too much time and energy worrying about getting the detailing right in relation to our required 'Basic' Radon protection, I am now wondering whether I should scrap the proposed purchasing of Visqueen pre formed corners and instead just adopt the good old tape approach. I am not sure whether many people use the pre formed corners and given that the garage door opening pair and garage side door pair are ~ £240, I am struggling to justify the expense. If I can adopt an approach of cutting DPM pieces and overlapping and jointing with tape, does anyone know of a resource that shows how you can form internal and external corners.
-
Sorry, but what are kerb units?
-
We are having a Radon membrane (but I suspect the same applies for a simple DPM) and am just about to put my order in for pre formed Visqueen units. As the floor slab protrudes across the 350mm wide inner leaf/cavity and outer leaf, I am confused as how you stop the slab getting damp from rain water falling on the outer part of the slab which sits outside the garage door, which then creeps internally inside the garage. Below is an image of the pre formed corners, but even if you did not have pre formed corners and cut and taped the DPM around the opening, you still have the issue of the slab running continuously through the opening and outside. Do you simple cast the slab in two sections and have a dpm upstand on the inside and have rebar mesh poking through to the 350mm wide opening section?
-
Principal Designer and completion certificate
flanagaj replied to flanagaj's topic in Building Regulations
I am not worrying about this now. I did further reading and it appears that your architect can only sign as Principal Designer if they oversaw the works. As a self builder who is managing all trades, then it becomes your responsibility. I see now, why taking lots of photos and always referencing the LABC manual is crucial. As you become the Principal Designer. -
I was looking at the SE calcs for the lintels and they have only done loading calcs for the 4.4m patio doors and that for the double garage. There are obviously loads of other lintels for cavity wall and internal. Is this common practice or have they done half a job?
-
Principal Designer and completion certificate
flanagaj replied to flanagaj's topic in Building Regulations
Considering the TA we used didn't visit site and won't come to site, that's going to be an interesting conversation. -
Principal Designer and completion certificate
flanagaj replied to flanagaj's topic in Building Regulations
If you have a physical copy of the LABC regs that you refer to for required works, then surely that must satisfy part of the requirement. Still, good to know that I can sign it myself. What is the actual point of the signed document though? -
Can anyone provide some guidance here as I read a post on FB about someone unable to get a completion certificate as their architect was unwilling to sign off as principal designer (no idea what that means). In a nutshell, we did the following. 1) Architect A did planning drawings and secured us planning. 2) Technical Architect B did building reg drawings and submitted them to planning. 3) LABC signed off the drawings and gave us an inspection schedule. 4) Warranty provider has also given us their inspection schedule. I thought that so long as we satisfy 3&4 then we'll get a completion certificate and everything is fine. But I think that maybe I've missed something crucial?
-
I am obviously overly complicating these things. It's not my intention, to but I spent nearly 2k on Visqueen membrane, pre formed corners and top hats as I thought it needs to be done with precision. I get the impression that it's a case of just do a Heath Robinson job on it. The PIR tip is useful and I naively thought it needed to be flat and smooth. Having been a furniture maker in a previous life, this hackery is not something I am used to.
-
That does seem like the logical approach. Do you know whether the SCC can be easily worked so it provides a suitable surface for Radon membrane / insulation. My concern is that the concrete slab is laid and the surface resembles the Alps and then needs remedial works to get it flat enough for PIR / Radon. My plan is to put the the Radon membrane on top of the slab and a sacrificial DPM below the slab. The utilities are quite high and if Radon membrane goes below the slab, it's going to be a hatchet job sealing around the pipes, due to the fact that at that level I am either on the start of the curve of the rest bend, or sat directly on the rest bend collar. Going above the slab puts me on the vertical and will mean I can use the top hats for sealing.
