Hold onto your hats!
After such a very long time of planning, waiting, more planning, plotting and scheming, the real and tangible world is now hurtling towards me at a pace. MBC got in touch this morning to advise that the slab insulation and the MBC team will be on site on 31st July. That's next week. Eek!
Now, I don't know exactly what else is going to happen and whether that's the start proper of the slab going down, but I'd say it's a pretty positive sign of it. Once I have more detail on the schedule, I'll publish on here. For anyone wanting to see the piling in action, I strongly suspect that Thursday will be the final day (we are due a bit of rain there Friday morning, too) and I'll be around if anyone wants to visit.
I now need to get my scaffolding booked and finalised - it looks like I'll need it soon.
5pm update: it's the full team arriving to do the slab on 31st July, followed by the superstructure on 14th August.
Update 24/7/18 on MBC dates. Insulation and MBC team now due to start foundation on 2nd August, possibly 3rd, with superstructure due w/c 20th August due to over-run on current job.
- 4
4 Comments
Recommended Comments
Create an account or sign in to comment
You need to be a member in order to leave a comment
Create an account
Sign up for a new account in our community. It's easy!
Register a new accountSign in
Already have an account? Sign in here.
Sign In Now