Jump to content
  • entries
    13
  • comments
    72
  • views
    3638

Week 12 - Windows, doors, battens, roof, …and more insulation.


Very busy again this week - we were probably running at the maximum people we can have on site without contractors getting in each other’s way.  On Thursday we had the carpenters, the insulation team, a roofer and the window installation team on site, and it’s not a very big site.  

 

Windows and doors

The main highlight of the week was the arrival of the windows and external doors on Thursday together with a team of four (from Ukraine, though the windows were made in Estonia).  The installation team led by Alex and Val were on-site by 7:30am and the windows arrived at 8:00.

IMG_1817.thumb.jpeg.827e5a524c45f5e15943c2f667a44ad8.jpeg

 

FEB7F1F8-E54A-462E-924D-16E60C8F6C14.thumb.jpg.510248403f0f696b4337af77a29c23ba.jpg

 

IMG_3641.thumb.jpeg.5a7a52f563bc31e3f125467428dd49c6.jpeg

 

All the windows and doors went in smoothly over the next day and a half.  Barring a factory error, we knew they were going to fit as Alex and Val had done a pre-installation site visit three weeks ago.   There were no factory errors and everything fitted perfectly.  There was no fuss about our difficulties with getting all the requested scaffold changes done (we didn’t) - the team worked around the shortcomings.

 

IMG_1826.thumb.jpeg.58e02da00990e530afd9114a0452deaa.jpeg

 

 

IMG_1827.thumb.jpeg.4efc22b6bf005149a139d4c6b0d330dc.jpeg

 

IMG_1824.thumb.jpeg.c5718480b1dceb523b3f249364818e54.jpeg

 

IMG_1825.thumb.jpeg.bda27d8ceb17e3472847b43a037d7cf5.jpeg

 

IMG_3645.thumb.jpeg.77d1a6d72ad1539d3991cf5ac4df0dd9.jpeg

 

For those interested, the windows are triple-glazed, alu-clad, inward opening tilt and turn, Norrsken P33A units; the doors are S305A alu-clad, composite panels doors and the 4 metre lift and slide, which is also triple-glazed, is Norrsken’s S305A door.  The lift and slide door weighs in at 475kg and was moved by hand down a 500mm wide gap between our scaffold and our neighbour’s fence, then lifted manually into place.

 

Here’s the sliding panel coming in first - it was stood to one side then fitted in once the frame and fixed panel were in place.

 

IMG_1829.thumb.jpeg.65773c887b2042c7062085f72b42b892.jpeg

 

IMG_1831.thumb.jpeg.405194f4deb9dc131a1abbc1df041b5e.jpeg

 

I have to say, we remain very impressed by Norrsken and would recommend both the product and their installation subcontractors.

 

Alex and Val suggested removing the front door, wrapping it and storing it safely, then cladding the frame in ply with a temporary door in place during the remainder of the build.  Seemed a sensible suggestion and that is what we aim to do next week.

 

Here's Dima, Alex and Val from the Norrsken window installation team:

 

IMG_1848.thumb.jpeg.753b33ed55bd011c852a326bf7eb6aae.jpeg

 

Having the windows and doors in is obviously a big step forward but we had progress on other fronts too:

 

External wall battens and roof

Our carpenters Alan and Chris made a start on (and indeed finished) fixing the 50 x 50mm external ventilation battens and have pretty much finished.  (That’s messed up my wallplan - it’s not supposed to be done until next week!).  They also boarded out the plant room walls with 18mm ply - it seems sensible given the amount of kit we need to fix to the walls in there.  Just in time for the electricity supply, which SSE are coming next Tuesday to move into the plant room from the current external meter box.

 

The slate edged, solar panel roof was finished this week too and now only needs the zinc mono-ridge capping/facia to be fitted (tomorrow) for the roofs to be complete.

 

Insulation

The team from Cornwall were back this week for what was supposed to be week two of two, to membrane and insulate the insides of the external walls and the underside of roof (below the blown cellulose layer).  Progress has been slow for a number of reasons and the work remains a long way from complete.  Still to do is the insulation on a couple of high walls and the whole of the roof.

 

Partly, the job has proved a lot more involved than I or the contractors realised.  Also they were delayed this week by other work over-running, sickness, and a funeral.

 

On the one hand, given it’s a fixed price contract, we should not be too worried.  But there is a potential impact on the schedule downstream if this work is not complete by about the 3rd week in September.  And for the next 3 weeks our focus shifts to the floor: fixing the DPM, insulation and UFH pipes, then pouring the screed.  So there is no access inside the house for the wall/roof insulation team until about 8th September.   

 

I can see this getting messy but for the moment we are trying to keep to the current plan which leads to the plastering starting on 6th October.

 

It might be time to fire up Steve Jobs’ Reality Distortion Field (well, it worked for him... until it didn’t).

 

Mistakes - I’ve made a few…

Here’s a good one:  We planned to fit an external blind to the master bedroom window, partly to keep the solar gain down and partly for blackout purposes.   The idea was that the blind would be hidden in the timber cladding, out of sight when not in use.

 

But despite poring over drawings and designs endlessly, I failed to spot that the roof canopy has a return beam that comes in 20mm above the window reveal - so there is no way we are going hide a blind cassette in there.

 

IMG_3639.thumb.jpeg.50bad5ded5b04b3a5947b96e82a35046.jpeg

 

IMG_3648.thumb.jpeg.431a2e2ad2da0612014596cbda8a4042.jpeg

 

I’m not actually sure what that beam is doing given there is no weight hanging off it and surely the roof trusses provide enough of a horizontal tie for the oak post?  It’s probably too much effort to challenge or change now though and Mrs P. and I both feel we can live without an external blind there (and fortunately our Part O Overheating assessment did not take the external blind into account but listed it as an optional improvement).  

 

Other mistakes are either too minor, or too embarrassing to mention.

 

Stress

Yes, I can confirm that running a self-build is pretty stressful - on a par with the stress levels I used to experience running big IT programmes, I’d say.  I won’t deny we’ve both had a few sleepless nights worrying about what’s happening tomorrow, or the day after, or next week...

 

Still, every task done is one we (hopefully) no longer have  to do.

 

  

Dashboard:

 

Contractor days on site this week: 26 (that’s our record week!)

Contractor days on site since build start: 192

 

Budget: No change, running slightly over.

 

Plan: On track to move in by Easter 2026.

 

Issues and worries closed this week:

  • The windows are in! Our scaffold issues haven’t held the window installation up (though the scaffold itself did fortunately hold the window installers up!)

 

Current top issues and worries:

  • Insulation - still lots to do, increasing potential for the dealys to impact our overall schedule.
  • Scaffolding - still a worry, although we do now have a provisional date when the scaffolders plan to take the scaffold down, so fingers-crossed that holds.
  • Scheduling future deliveries: insulation, battening, cladding, render boards, MVHR, UFH kit, ASHP, HW cylinder… all due in the next four weeks.

IMG_3644.jpeg

  • Like 5

10 Comments


Recommended Comments

G and J

Posted

Going great.....very impressive and a good tip re the front door that we will seriously consider copying

  • Like 1
Nickfromwales

Posted

1 hour ago, G and J said:

Going great.....very impressive and a good tip re the front door that we will seriously consider copying

Defo best advice. We always buy a battered upvc door off gumtree etc local to the projects and only swap that out at the very last minute. Have one here atm covered in Passive Purple, so I doubt gumtree will work to get it sold back on now lol. 

 

For the sliders @Benpointer, I usually make a plywood shoe that sits over the threshold and keeps the slider open fully, making sure that trades step on that and not the shiny new threshold with muddy boots etc. You simply lift this on/off at the start and end of each day, and make yourself sheriff of the keys so no numpty can open it and wreck it for you.

 

You need eyes in the back of your head as you get the niceties installed, as otherwise even a simple extension lead getting wound back through an open door or window will remove the paint off the frame.

  • Like 2
Benpointer

Posted

Great advice re lift and slide door Nick.  We'll lock it shut for now because there's currently a 500mm step up from the back and a 300mm step down inside to get in through that door, so it's not an ideal access anyway.  We'll make the ply cover for when the screed is down - early September 🤞

  • Like 1
LnP

Posted

Really enjoying your blog. You're clearly doing a great job of the project management. I hesitate to ask, as you already have enough on your plate, but I'd be very interested if at some point when you have a minute to spare (🤣) if you shared some of your knowledge on how to do that well, what tools you use etc.

  • Like 2
Nickfromwales

Posted

15 hours ago, LnP said:

when you have a minute to spare (🤣)

I’m sure @Benpointer can whittle this down to a few sentences….

 

…..and if he does, whatever he says will be the first ever tattoo I get lol. 

Benpointer

Posted

6 hours ago, Nickfromwales said:

I’m sure @Benpointer can whittle this down to a few sentences….

 

…..and if he does, whatever he says will be the first ever tattoo I get lol. 

Very kind words but I am still expecting that we will hit the rails and run into the smelly stuff at some point, so let's see how we cope with that.

 

In the meantime, the principal attribute of successful project management imo is "Be lucky".   Not too big for a first tattoo Nick 😉

  • Like 2
Nickfromwales

Posted

3 hours ago, Benpointer said:

Very kind words but I am still expecting that we will hit the rails and run into the smelly stuff at some point, so let's see how we cope with that.

 

In the meantime, the principal attribute of successful project management imo is "Be lucky".   Not too big for a first tattoo Nick 😉

May your luck be ever-flowing my good man ;) So far so good is an understatement, you're doing a sterling job and have managed to find some great folk to help you achieve your goals.

  • Like 1
LnP

Posted

12 hours ago, Benpointer said:

In the meantime, the principal attribute of successful project management imo is "Be lucky".  😉

“Luck is when preparation meets opportunity”.

  • Like 1
Benpointer

Posted (edited)

44 minutes ago, LnP said:

“Luck is when preparation meets opportunity”.

It's got a nice ring to it but sadly it's not really fair on those who experience genuine bad luck that no amount of preparation which doesn't involve time-travel would have avoided.  I'm thinking of those who bought, and largely paid for, a timber frame from a company that then went bust; those who planned their groundworks for the summer only to find that particular summer is the wettest on record (in contrast to us)...  We can all think of plenty of similar examples.

 

However, alongside Gary Player's gem: "The more I practice, the luckier I get", it's a great way to highlight that there's often more to apparent 'good luck' than meets the eye.

Edited by Benpointer
  • Like 2
G and J

Posted

6 hours ago, LnP said:
19 hours ago, Benpointer said:

In the meantime, the principal attribute of successful project management imo is "Be lucky".  😉

“Luck is when preparation meets opportunity”.

 Think that actually both apply, however good the plan, sometimes you also need that following wind to fly

Create an account or sign in to comment

You need to be a member in order to leave a comment

Create an account

Sign up for a new account in our community. It's easy!

Register a new account

Sign in

Already have an account? Sign in here.

Sign In Now
×
×
  • Create New...