flanagaj Posted 19 hours ago Posted 19 hours ago I had our plans estimated and it gave me a figure for labour up to plate height. So far, they have ranged from 10k over the estimators 20k figure, up to a staggering 45k over. I really don't know how to proceed now as we have had 4 quotes so far. It's a very simple brick and block rectangle, built using stretcher bond.
G and J Posted 19 hours ago Posted 19 hours ago Sorry for the potentially numpty response, but assuming you mean first floor wall plate, for comparison. 55 linear metres in Suffolk to first floor height, ie just ground floor from below damp, brick plinth average 4 courses, then blocks, labour only 12.5k. Excellent work. From your pictures, in previous posts, your brick work is going to be huge part of your overall design so may be "simple" but the quality required is going to be high...........was your estimate realistic, are your quotes labour only? On the former we had a take off done, and they assumed pretty basic everything (apart from a contractors profit!)
Mr Punter Posted 18 hours ago Posted 18 hours ago Keep going with the quotes. What did your estimator base their price on?
Great_scot_selfbuild Posted 18 hours ago Posted 18 hours ago 1 hour ago, flanagaj said: I had our plans estimated and it gave me a figure for labour up to plate height. So far, they have ranged from 10k over the estimators 20k figure, up to a staggering 45k over. I really don't know how to proceed now as we have had 4 quotes so far. It's a very simple brick and block rectangle, built using stretcher bond. @flanagaj I can highly recommend Adam Chandler - https://chandlerhp.co.uk/services/house-builds/ (based in Basingstoke) Best of luck, stay positive! 1
flanagaj Posted 17 hours ago Author Posted 17 hours ago Here are the estimates that I received from Estimators. Excavation & Foundations - 7 days (2GW + 1 Labourer) Foundation Masonry - 5 days (2B + 1 Labourer) Brickworks - 15 days (2B + 1 Labourer) My theory is that if estimators can't be that far off when it comes to estimating costs for a build.
crispy_wafer Posted 16 hours ago Posted 16 hours ago Do you think those labour rates are accurate for your region? Materials are quite easy to cost up, but humans cost lots these days!
flanagaj Posted 3 hours ago Author Posted 3 hours ago 13 hours ago, crispy_wafer said: Do you think those labour rates are accurate for your region? Materials are quite easy to cost up, but humans cost lots these days! They use local labour rates. A brickie is not usually on more than £300/day. So I said 2 brickies and a labourer for 20 days at £800/day. That still only equates to £16000 for 20 days work. So the quotes of 30k, 42k and 60k are just a joke. Anyone would think I was hiring a legal team. 1
Oz07 Posted 3 hours ago Posted 3 hours ago What estimator did you use. 3 weeks sounds a bit quick to me but I've not seen or can't remember the plans or elevations. Whats your quantities or brick and block. If you were to allow maybe 75 pence a brick and 2 quid a block down your way does that get you somewhere in the ballpark? Very rough and im not sure of rates your way. With regards to getting some decent quotes try to get an introduction or reccomendation off other trades or previous customers. That way your not a cold calling random you're ringing them up saying I know X who's extension you built or I know X plumber who has worked with you guys says you do a decent job etc
flanagaj Posted 2 hours ago Author Posted 2 hours ago 5 minutes ago, Oz07 said: What estimator did you use. 3 weeks sounds a bit quick to me but I've not seen or can't remember the plans or elevations. Whats your quantities or brick and block. If you were to allow maybe 75 pence a brick and 2 quid a block down your way does that get you somewhere in the ballpark? Very rough and im not sure of rates your way. With regards to getting some decent quotes try to get an introduction or reccomendation off other trades or previous customers. That way your not a cold calling random you're ringing them up saying I know X who's extension you built or I know X plumber who has worked with you guys says you do a decent job etc Quotes are labour only and they have allowed 20 days for the job. It's a straightforward rectangle build with gable ends, face brickwork on lower ground floor and then block upstairs. The issue I have, is that if I just say "Oh well, let's just pay 10k more and get going", if that same thing happens for all trades, then I am in real trouble and we'll have to sell the house once it's built.
G and J Posted 2 hours ago Posted 2 hours ago Our rate in East Anglia (likely to be cheaper) 900 per day 2+1. Our 55 linear metres to first floor took 14 days, majority block and they were lightening quick. (This was also round a timber frame, so apart from garage not structural/load bearing). We employed on day rate, they came recommended, if they had "qouted" they would have put some "saftey" in for time. Our bricks Ibstock blues are nothing particularly special and they we just under 1 a brick to us (not list) and that was a good deal. How many days do you quotes think it's going to take?
Russell griffiths Posted 2 hours ago Posted 2 hours ago Show us a picture of the build, your times seam woefully low.
Recommended Posts
Create an account or sign in to comment
You need to be a member in order to leave a comment
Create an account
Sign up for a new account in our community. It's easy!
Register a new accountSign in
Already have an account? Sign in here.
Sign In Now