Jump to content

Insulting block and beam flooring in preparation for ASHP run UFH


MaxEmery

Recommended Posts

Good morning all, 

 

I've read what I think is every forum post about insulating suspended floors and in particular insulating block and beam floors but I still have some questions. 

 

Our house is a 1982 built B&B floor semi on a split level due to the slope of the site. Naturally the floor is not insulated. As the heating was very restrictive microbore and getting a bit old we decided underfloor heating would be the solution to allow efficient heat pump install and reduce the clutter of large rads in what is quite a modest home 75sqm. 

The house is pretty airtight and I plan to make this even better. We are replacing blown glass with new low U value units and installing triple glazed bifolds in place of the thin double glazed sliders, the cavity wall insulation has been inspected and is dry and clean with no cold spots and the loft has 300mm or 400mm of glass wool depending on area so heat loss should be fairly low (predicted 50w/m2 at -4C)

 

We have so far taken the floor back to the block and beam. The blocks are undulating by a fair bit but a laser level set to the highest points tells me I have about 100mm to play with at a minimum before I have to start replacing front and side doors. 

 

Option #1 is to smooth the floor with sand and cement lay 50mm of Kooltherm which I was able to get quite cheap (already bought) and then lay 100mm centres UFH followed by 9mm of floor coverings. Heating tables suggest that at around 30-35c flow temps our estimated heat loss of 50w/m2 will be covered. My initial hope was that low flow temps would lead to less heat loss down and negate the need for more insulation alas I think others experience here says otherwise. 

 

Which brought me to devise 

Option #2A same as above but with EPS beads filling the subfloor which varies from about 250mm below beams to 500mm. At the moment this is sand covering the earth with no apparent DPM but it is very dry and the site means the risk of flooding is 0 and runoff should also be very low risk. With new EPS beads installed DIY cost is around £1000 waterproofed ones from a cavity wall installer closer to £2k.

 

Option #2B same as #1 but with 100mm of PIR glued or attached in some way to the underneath of the beams. At the moment I have been toying with plastic insulation nails fixed from below (issue with access once insulation is in place) or insulation wall plugs from above with screws inserted through the blocks holding the PIR up and then EPS beads poured into the remaining space. With seconds insulation and new EPS beads cost is around £500.

 

Option #2C I'm very much open to ideas! 

 

 

Link to comment
Share on other sites

27 minutes ago, MaxEmery said:

subfloor which varies from about 250mm below beams to 500mm.

Struggling to see how you fix pir under this floor.

If the block levels are only very locally high, then pir may crush locally and so save you the screed and increase the pir thickness.  That's all I would do as eps beads underneath is rather experimental.

Link to comment
Share on other sites

The idea with fixing the PIR under the floor is lift sets of blocks. Glue the PIR to beams with sticky foam, screw insulation wallplugs to the PIR boards, then drill through some of the blocks, countersink and put a screw through the block and into the insulation wallplug. Does that make any more sense? 

 

The alternative would be to do similar but from below. Glue the PIR in place, drill through it and into the blocks above then use plastic insulation screws (link below) to secure the PIR to the blocks to stop them falling back down should the foam glue fail. 

 

Are you saying that if the PIR was to crush in those locations that would be acceptable? 

 

RAWLPLUG INSULATION FIXINGS 160MM X 10MM

 https://www.screwfix.com/p/rawlplug-insulation-fixings-160mm-x-10mm-250-pack/140KF?kpid=140KF&cm_mmc=Google-_-Datafeed-_-Screws%2C Nails and Fixings?kpid=KINASEKPID&cm_mmc=Google-_-TOKEN1-_-TOKEN2&gad_source=1&gclid=CjwKCAiA0PuuBhBsEiwAS7fsNRKI8RiltXHWW7uWQUCltczqTyv04E_uUTRjh__rMEZEp5MQpEUOyhoC3IoQAvD_BwE&gclsrc=aw.ds

 

 

 

Link to comment
Share on other sites

54 minutes ago, MaxEmery said:

If the PIR was to crush in those locations that would be acceptable? 

Yes. Over a tiny area the effect is minimal and directly proportional. So if a 100mm x 50 mm bit of block was sticking up 10mm, the pir could crush there and so you hsve still 90mm of pir. A small reduction, and heat is still retained. Meanwhile the remainder has the full thickness of pir instead of screed.

Perhaps put down 10mm or 20mm of eps first as it will crush more readily and make full use of what depth you have. "About 100mm", could be 100 pir on 20 eps for example.

 

Great to be thinking of other solutions but they don't seem practical so far....i have thought through adding insulaton underneath  before but discounted everything to date. It would be great to find a solution, and a big market opportunity.

Link to comment
Share on other sites

45 minutes ago, saveasteading said:

Perhaps put down 10mm or 20mm of eps first as it will crush more readily

I really like this idea and it would save much of the need to cement and screed which was likely to a be a pretty big time sink to get right and EPS would be easy to carve away in areas where the floor was massively out. Thanks for the help. 

 

I do have some cavity boards arriving which are currently destined for the garage but I'm going to give my plan a go and see how things are. I'll be sure to report back on the findings. Like you say I suspect its going to be impractical but given I have access now and probably never will again I'm keen to work through all options before committing to just 50mm of kooltherm. 

  • Like 1
Link to comment
Share on other sites

  • 2 weeks later...
Posted (edited)

As promised...

 

It's a slight pain to do but it does seem to be working so far. 

The current process I'm using is:

Lift a section of blocks. 

Measure and mark the boards so I know where they will touch the beams.

Spray a little water on the areas that need foam to help it adhere. 

Apply the foam and wait the 4 odd minutes for it to go sticky. 

Wrangle the board into position and support it with a brick to keep it in contact with the beam above.

About 30 minutes later the foam seems fairly well set but I've left the bricks in place lightly touching the insulation just to be safe. 

 

Issues

 

I don't yet have a satisfactory way to mechanically fix the boards to the blocks so any ideas would be very welcome.

There really isn't the clearance to get a  fixing in from below and the insulation wall plugs I bought aren't really up to the job of holding the boards if the adhesive gave up unless I commit to 6 or so per board which adds a fair bit of time faff and expense. 

At the moment I'm tempted to leave the bricks I used to prop them up temporarily in place permanently it'll take 1 per board centrally on each which I can't see causing an air circulation issue. A cheaper option would be a cut up scrap section of insulation but not totally sure Its sensible to leave the PIR in contact with the sand subfloor. 

 

Speed wise it isn't the worst. Working solo I can do about 5 boards an hour each board being .52m².

 

cost for me is likely to be as follows:

£3 per m² for the insulation (defective cavity wall boards from seconds and co 1.50 each 100mm depth)

£1.50 per m² for the sticky foam 

£1 per m² for the bricks assuming I run out of the ones kicking around in the garden

£2 per m² for EPS beads to fill in the void left above the insulation and below the blocks

 

I feel like this is well worth it for less than £10m² and could be a viable option for many retrofits.

 

Other notes are that far more of the blocks (maybe one in 10) than it initially appeared are cracked so this is a bit of added expense. 

 

I fully appreciate that I'm going to be reducing my floor void to levels that are not recommended. However the vent bricks will remain open and accessable and the floor will still have ventilation. I've bought 4 humidity sensor probes which I'll install that I can check on occasion to make sure things aren't getting out of hand humidity wise and if they are I figure I can install some ventilation fans to replace the vent bricks but I really don't see this being necessary. 

 

If people do think of anything I might be missing please do let me know. 

IMG-20240308-WA0001.jpg

Edited by MaxEmery
Add photo
Link to comment
Share on other sites

Create an account or sign in to comment

You need to be a member in order to leave a comment

Create an account

Sign up for a new account in our community. It's easy!

Register a new account

Sign in

Already have an account? Sign in here.

Sign In Now
×
×
  • Create New...