nod Posted October 27, 2023 Posted October 27, 2023 Had pre plaster inspection done todayĀ So can push on with the boardingĀ 350 boards arriving Wednesday So early night on Tuesday š 1
Chanmenie Posted October 27, 2023 Posted October 27, 2023 9 minutes ago, nod said: Had pre plaster inspection done todayĀ So can push on with the boardingĀ 350 boards arriving Wednesday So early night on Tuesday š What was actually inspected, And why ? By BC inspector came and looked at my roof trusses and said he didnāt need to inspect anything else other than the drains, as all the structural stuff is doneĀ
nod Posted October 27, 2023 Author Posted October 27, 2023 52 minutes ago, Chanmenie said: What was actually inspected, And why ? By BC inspector came and looked at my roof trusses and said he didnāt need to inspect anything else other than the drains, as all the structural stuff is doneĀ Mainly plumbing electrical everything in fans ducting insulation and everything is sealed up To late one e Iāve done the boarding and plasteringĀ
ProDave Posted October 27, 2023 Posted October 27, 2023 It seems to vary a lot.Ā BC inspected my wind and watertight shell.Ā I asked when was the next inspection and they said "completion"
nod Posted October 27, 2023 Author Posted October 27, 2023 37 minutes ago, ProDave said: It seems to vary a lot.Ā BC inspected my wind and watertight shell.Ā I asked when was the next inspection and they said "completion" Wow Ā My site work is always being held up by pre plasterĀ
TonyT Posted October 27, 2023 Posted October 27, 2023 BC inspected my foundation excavation and then came back when the build was finished to do the completion certificateĀ Ā Got to love councils that canāt be arsedĀ
nod Posted October 27, 2023 Author Posted October 27, 2023 13 minutes ago, TonyT said: BC inspected my foundation excavation and then came back when the build was finished to do the completion certificateĀ Ā Got to love councils that canāt be arsedĀ Fourth one for meĀ Same last timeĀ Preston BC are excellentĀ
crispy_wafer Posted October 28, 2023 Posted October 28, 2023 Cor, You don't hang about do you! Ā Pre plaster is my next inspection...Ā BI keeps popping round to have a nose though, because taking too long, popping cards into the post-box, he's more impatient than the wife!Ā Ā 2
nod Posted October 28, 2023 Author Posted October 28, 2023 Slightly off topicĀ I e been suprised by the amount of care LABC Warranty have takenĀ Half the price of Protec 7 visits Looked at everythingĀ Our previous made 3 visisits Inspected the foundations from his car Roof from the groundĀ Ten minutes in out kitchen for the final inspectionĀ 1
Mattg4321 Posted October 28, 2023 Posted October 28, 2023 Itās interesting how it varies. Pre plasterboarding makes sense to me. Check how badly the insulation has been fitted. It was laughable on a job I was on recently.Ā Ā Iāve never heard or seen a BCO checking electrics at any stage. None of them have a clue whatsoever. Perhaps building regs side - part M or holes in joists etc.Ā
nod Posted October 28, 2023 Author Posted October 28, 2023 1 hour ago, Mattg4321 said: Itās interesting how it varies. Pre plasterboarding makes sense to me. Check how badly the insulation has been fitted. It was laughable on a job I was on recently.Ā Ā Iāve never heard or seen a BCO checking electrics at any stage. None of them have a clue whatsoever. Perhaps building regs side - part M or holes in joists etc.Ā they donāt so much check electrics It more holes bashed throughĀ Iāve four sites that Iām doing the dry lining on and BC wonāt let us load them up before they have been inspectedĀ They regularly fail them on sealing up wall restraints membranes and insulation Fire stops is another that is often pulledĀ Ā Once they are boarded out Most inspections are pretty pointlessĀ
Recommended Posts
Create an account or sign in to comment
You need to be a member in order to leave a comment
Create an account
Sign up for a new account in our community. It's easy!
Register a new accountSign in
Already have an account? Sign in here.
Sign In Now