Bitpipe Posted May 24, 2016 Share Posted May 24, 2016 When we started the project, the architect suggested we use an independent assessor. Have to say, this is one of the best decisions we made. They were cheaper than LABC (who price on the completion spend but this excludes kitchens, bathroom fittings etc so could be manipulated to be what you need) and are super responsive but also light touch. There was a paper exercise up-front to supply all the detail drawings and calcs (these came direct from MBC and the structural engineer who designed the basement) and then details on other elements. Their first major inspection was when the rebar was in, ahead of any concrete pour. Seeing the quality of the work meant they didn't need to come back until the frame was erected. Next visit was after first fix and we'll see them again near the end. We've been able to negotiate away an external soil vent stack (their suggestion) and use of fireline plasterboard everywhere plus had sensible discussions on fire doors, escapes etc. I'd say that they have saved me money and been a good checkpoint for some issues. One golden rule though - whatever the outcome of a phone conversation - always get it in writing! Link to comment Share on other sites More sharing options...
jack Posted May 24, 2016 Share Posted May 24, 2016 Our experience has been good too. The guy we had was remarkably hands-off, but provided input when asked. I was really surprised when he said he didn't want to see us after the frame went up until completion - I think he was really happy with the way we'd been doing things. Link to comment Share on other sites More sharing options...
CC45 Posted May 24, 2016 Share Posted May 24, 2016 We used LABC & they've been great - not seen the chap since before windows went in about a year ago & he doesn't want to see anything until first fix starts. Depends so much on individuals really. cc Link to comment Share on other sites More sharing options...
daiking Posted May 24, 2016 Share Posted May 24, 2016 Can you trust your contractors though? Link to comment Share on other sites More sharing options...
Bitpipe Posted May 24, 2016 Author Share Posted May 24, 2016 Meant to add that our guy was aligned with a warranty firm who gave us a very competitive quote initially (and he would have done the inspections for that also) but when we came to start work a year later, they had shot up in cost so we used Ark (Zurich backed) who were cheaper and require no inspections at all. Link to comment Share on other sites More sharing options...
swisscheese Posted May 24, 2016 Share Posted May 24, 2016 Good to see this post, as I'm just thinking about this very topic. The LABC (actually 3 LABC's working together) and a local Independent I am thinking of using seem pretty close in terms of price, and after a brief chat, the independent seems to have a good local knowledge as well. The Independent is also on a approved list of an Inspectors of the Warranty firm I have been recommended. The price on the Warranty may or may not be decisive when it comes down to it. Link to comment Share on other sites More sharing options...
PeterW Posted May 24, 2016 Share Posted May 24, 2016 Out of interest, who's warranty have you gone with..? Link to comment Share on other sites More sharing options...
swisscheese Posted May 24, 2016 Share Posted May 24, 2016 Currently looking at CRL for the Warranty, though I have not received a quote back from them yet. Link to comment Share on other sites More sharing options...
HerbJ Posted May 24, 2016 Share Posted May 24, 2016 (edited) On 24/05/2016 at 11:24, jack said: Our experience has been good too. The guy we had was remarkably hands-off, but provided input when asked. I was really surprised when he said he didn't want to see us after the frame went up until completion - I think he was really happy with the way we'd been doing things. Same for us. Initially, I sent him regular progress reports and photos and expedited him to visit the site. He hasn't to site been for months and I now don't expect to see him until completion. It seems they soon get a very bgood idea of the quality of build, adherence to BR, etc and make a decision about their requirements for visits, Edited May 26, 2016 by HerbJ 1 Link to comment Share on other sites More sharing options...
Recommended Posts
Create an account or sign in to comment
You need to be a member in order to leave a comment
Create an account
Sign up for a new account in our community. It's easy!
Register a new accountSign in
Already have an account? Sign in here.
Sign In Now