SuperJohnG Posted February 18, 2020 Share Posted February 18, 2020 Not sure if this is the right section, but house construction didn't seem to cover it. so please move to appropriate place if required mods, thanks. After numerous iterations we have nearly finalised on our layout. (See below). It made sense for us to move the master bedroom above the garage to aid the flow of the house and we really like the layout. I had however previously avoided this because I assumed we would have issues with being inside the thermal envelope and air tightness and so forth. It will be a timber frame or SIPS build and I am hoping to achieve high levels of air tightness, is there anything I should be looking at or concerned about with our master being above the garage and obviously the garage will be outside the thermal envelope and not very air tight at all. Will the floor construction need particular attention? . any other thoughts. Link to comment Share on other sites More sharing options...
Moonshine Posted February 18, 2020 Share Posted February 18, 2020 6 minutes ago, SuperJohnG said: Will the floor construction need particular attention? yes the floor will need to meet building regs for fire and thermal insulation. Also the door to the mud room will likely need to be a 30min fire door with smoke seals. The bedroom has some long spans over the double garage, so you will need to think about getting the spec of the timber joists right so you don't get too much deflection / bounce. This may limit the floor to ceiling height in the garage, but not the end of the world. Careful detailing will be needed when the garage wall to the house meets the floor for thermal performance. Link to comment Share on other sites More sharing options...
scottishjohn Posted February 18, 2020 Share Posted February 18, 2020 pretty sure you will need alot of thickness+ fire proofing in ceiling of garage and fume proof if over a garage in case of car going on fire also garage floor will need to be lower than house so burning fuel cannot run in as for long runs of bedroom floor joist --close them up and fit more of them ? your architect will know Link to comment Share on other sites More sharing options...
ProDave Posted February 18, 2020 Share Posted February 18, 2020 This is nothing unusual at all. Standard detail for garage ceiling with habitable rooms above is two layers of 15mm fireline plasterboard, the pink one 15mm thick, with the joints taped and filled, and the joints of the two layers staggered. You will have thick joists for the spans you have so plenty of room for a decent amount of insulation. build in a taped air tight membrane under the floor and taped up to meet the wall air tight layers and that's your details sorted out. 4 Link to comment Share on other sites More sharing options...
scottishjohn Posted February 18, 2020 Share Posted February 18, 2020 the drawing shows garage floor same height as house --no step shown --that will not do -must be lower Link to comment Share on other sites More sharing options...
SuperJohnG Posted February 18, 2020 Author Share Posted February 18, 2020 7 minutes ago, scottishjohn said: the drawing shows garage floor same height as house --no step shown --that will not do -must be lower Is this a building regs thing? Link to comment Share on other sites More sharing options...
scottishjohn Posted February 18, 2020 Share Posted February 18, 2020 Just now, SuperJohnG said: Is this a building regs thing? it was when my house was built Link to comment Share on other sites More sharing options...
scottishjohn Posted February 18, 2020 Share Posted February 18, 2020 and air bricks as well Link to comment Share on other sites More sharing options...
ProDave Posted February 18, 2020 Share Posted February 18, 2020 A step down from the house is mandatory (in Scotland) Ventilation of a garage is only mandatory above I think it's 30 square metres. Our single garage does not require any. Building regs do say in that case not to try to seal the building, so I did not fit air tight membrane for instance. Link to comment Share on other sites More sharing options...
Vijay Posted February 18, 2020 Share Posted February 18, 2020 AFAIK it's either a step down or a slope towards the external garage door Link to comment Share on other sites More sharing options...
SuperJohnG Posted February 18, 2020 Author Share Posted February 18, 2020 (edited) This kind of plays with my plans a little. I am hoping for an insulated passive insulated raft - so woudl I put the garage floor in the raft or not - or can I have two levels in a raft? just for clarity - this is in Scotland. Edited February 18, 2020 by SuperJohnG Link to comment Share on other sites More sharing options...
Moonshine Posted February 18, 2020 Share Posted February 18, 2020 26 minutes ago, Vijay said: AFAIK it's either a step down or a slope towards the external garage door you are correct as below (best check the regs to make sure its still valid) 1 Link to comment Share on other sites More sharing options...
Rishard Posted May 27, 2023 Share Posted May 27, 2023 On 18/02/2020 at 14:54, ProDave said: This is nothing unusual at all. Standard detail for garage ceiling with habitable rooms above is two layers of 15mm fireline plasterboard, the pink one 15mm thick, with the joints taped and filled, and the joints of the two layers staggered. You will have thick joists for the spans you have so plenty of room for a decent amount of insulation. build in a taped air tight membrane under the floor and taped up to meet the wall air tight layers and that's your details sorted out. Morning, I’m just going through a similar process with a separate double garage with room above, timber frame. I have the option to carry the airtight membrane under the joists which form the garage ceiling. I have a pitched roof with 2x gables. Would I be best joining the membrane to the external membrane on the timber frame gables as you say? Also, I can detail the rafter eaves so the membrane can carry on up past my joist ends to meet my roof membrane, would this be best rather than turning it in on the joists like a Tony tray? My roof pitch is 45* and the wall plate is on top of my joist ends over load bearing walls. I intend to split my rafters at the joist end point so I can have some ‘dummy’ oak rafter feet as the below garage is oak frame. I have done this detail on a few oak buildings but the airtightness hasn’t always been a priority. This being my own garage, it is, alongside good insulation ect. The point where I split the rafters would be where I can connect up ceiling to roof membrane. Link to comment Share on other sites More sharing options...
Recommended Posts
Create an account or sign in to comment
You need to be a member in order to leave a comment
Create an account
Sign up for a new account in our community. It's easy!
Register a new accountSign in
Already have an account? Sign in here.
Sign In Now