Hi update, house now built, just some cladding and slips to do outside - waiting on material.
Ended up with triple glazing as suggested, made and installed by Wood Kraft in Elgin.
Once the foundations were completed it took another 11 months before we were in.
Spec
Private water with our own borehole, mains gas, septic treatment plant.
Triple glazed throughout
MVHR
Durisol walls, parge coated internally (sand, cement and lime mix) for airtightness, floor to wall junction with liquid airtightness paint, battons and plasterboard. External a mix of stone slips and Scottish larch.
Posi rafter roof structure, battoned and counter battoned 100mm to give 350mm insulation space and then spray foam insulation. Passive House systems Reflective vapour airtightness layer, further battoned and plasterboard. Roof finished in slates and sarnafil EPDM standing seam and 3.1kw PV.
Floor slab buildup, strip foundations with 100 to 150mm reinforced C34 concreted slab, 200mm of PIR insulation, UFH pipes throughout, at 300mm spacing, finished 100mm concrete with 70mm insulated perimeter.
Work completed by myself
Floor insulation
UFH
All plumbing except gas
Durisol block work
All battons to wall and roof
Internal stud walls
Parge coat
Vapour control on roof internals (all ceilings match roof line)
PV install, except electrical hook up
Installed all bathroom s (x3)
External cladding and currently doing stone slips.
MVHR install
Project managing and organising sub contractors who completed - ground work, roof structure, sarnafil and slates, electrical, windows, joiner for plasterboard and
second fix joinery, taper for plasterboard.
Images are a before and after