  1. Thank you all. In regards to 100mm insulation, I have what I have now. I've not had the best of the experience with the build from the design stage onwards. Two architects and both didn't advice me of having more than 100mm insulation. thank you.
  2. Hi So we're close to installing UFH in our self build. We have 170mm to FFL, which doesn't quite add up. 100mm insulation 50mm liquid screed 3mm (to 5mm) floor tile adhesive 10mm floor tile thickness Total 163mm How do we gain the remaining 7mm? Perhaps this could be gained by applying more screed and/or floor tile adhesive? Thanks
  3. Thank you for the comments. It'll be Oak. Thanks
  4. Hello We're building a self build detached house. The plasterer says the internal door casing need to be fitted first before boarding and skimming. The joiner says, the casing should be fitted after plasterboard and skimming. Should internal door casing be fitted before or after plasterboard and skimming? Thanks
  5. @joth I like to make it clear that we (builders or I) did not cut corners on building regs. The builder called out the building regs. officer (local council) at agreed stages. Furthermore, I too called him out to discuss, which he told me were non building regs. issues. On his first visit. I remember asking him to be as strict as possible with applying building regs. knowing that his recommendations/suggestions would be good for the build. I remember him saying that a building either complies with building regs. or it doesn't. He did ask us to fit steel catnic lintels on top of the first floor bay windows to accommodate a wall plate to achieve the angle of the pitched roof. It seemed like an overkill as it hardly took any weight but we complied. I had to get structural engineer involved and the catnic lintels had to be fabricated on site. Cost me a lot of money and over 2 months delay. I'm an inexperienced self builder. Had he highlighted any other building regs. issue, we would have complied.
  6. Thanks, if that's the case then did you have your name on them?
  7. Hi To reclaim VAT, what address should show on the invoice from builders merchant, the site address or my current resident address? Thanks
  8. Qualified architect designed it. According to the builder., his drawings/design was 100% better than the previous architect's drawings. Not had a good experience with the self build from the start. (luckily I didn't go with a turnkey builder, who stayed quite for 2 months and came back to me and reduced the price by £130K, yep £130,000. Initially was recommended by a stone quarry. He built many houses. I asked a few owners and they said they would recommend him and were happy with his work).
  9. Going through the photos, I see that insulation up to first floor did get taped up but not after. (This damage was caused by some teenagers)
  10. Thanks. It's an option. I'll give that a serious thought.
  11. Not sure what I can say other than to put up a brave face, again Thanks, will add insulated plasterboard to the internal walls. Not sure I can add more insulation to the ground floor. To FFL is 100mm insulation, 50mm liquid screed and 10/15mm tiles. Extra insulation between trusses shouldn't be a problem.
  12. I don't know much details about the the other build. Just shows how inexperienced I am. If I had even a little bit of advice about putting in more thicker insulation in cavity I would have. I remember asking the builder about putting in 75mm insulation in cavity wall but he said it's usually 50mm and you need 50mm void for air circulation. Therefore, I went with 50mm Kingspan. The SAP is 52 pages of calculations and numbers, too much jargon. I don't think I'll understand any. I don't think I can do much about the cavity wall insulation now. Perhaps I can use insulated plasterboard? On the ground floor, we planned 100mm insulation with UFH. I have read people putting in 200mm insulation but I can't do that due to FFL. First floor to have 25mm insulation with UFH. In regards to roof/attic room insulation, I have planned 200mm insulation between joists, 100mm and 50mm between trusses and then plasterboard.
  13. This is normal up in West Yorkshire. I am aware of another new build 2022 completion, also used 50mm insulation in cavity walls. 100mm block, 50mm insulation, 50mm void and 100mm stone. Thanks joth, aren't you using a hot water cylinder? I thought the ASHP will come on to heat the hot water cylinder when it falls below set temp.? I need to read up on ASHP.
  14. What do you mean by "no room can "call for heat" on its own"? If there are two rooms and each room is a zone, then both rooms/zones can call hot water/heat as and when needed to maintain the different temperature set for each room?
  15. You wall construction looks like 300mm, that's going to cost you in expensive insulation and labour time to correctly (they wont)detail it. Have you already got building regs ? Yes, 300mm cavity wall. 50mm Kingspan insulation in cavity wall. Also, 50mm insulation in internal cavity wall adjoining garage, which builder said I don't need but I still went ahead with it. Building control officer is happy with everything so far.
  16. Drawings attached. The roofer has started slating the roof today. He reckons it'll take him 3/4 weeks.
  17. The thickness of first floor structure, plasterboard, blocks, 25mm insulation, 50mm screed and floor covering (tiles likely). A lot of people here are suggesting no UFH on first floor and no zoning to save cost. I will take this on board and discuss this with my other half. Inexperience. We wanted to build the house quickly and install UFH on the first floor. Nobody, from architect to the builder, advised us against B&B on first floor. So much for the quick build, almost 2 years from starting site clearing to just starting roofing. The architect took a few years to design the house and still messed up the levels then eventually decided to go with another architect. The rise of material prices over the past couple of years and scaffolding (has been up for over a year now) cost has eaten a large chunk of my budget. Not had the best of experience with anybody yet. The best advice/help I've had is from buildhub community. Thank you Buildhub community.
  18. Thank you all. I think it's better to put ASHP on future list along side solar panels. Thanks
  19. Thank you all. Need to rethink the upstair UFH. How do I calculate/get the heat loss calculation? Thanks
  20. Hi Re-considering ASHP for a self build house including UFH on two floors. How much would it cost to install a ASHP (5 residents, 3 wet rooms and UFH)? Thanks
  21. I've not had the best of any trade so far inc architects, could say I'm a victim of cowboys. Architect(s) designed it (long story, many years long) but I've not had much input. Probably, people took advantage of my naivety/inexperience. We had the SAP calculations report done. I'm looking for a most efficient build but within a tight budget as the build is over a year overdue, which has eaten up a lot of my budget I did initially consider ASHP and solar panels but can't now with the limited budget What is the widest pipe spacing that can be used?
  22. Thank you for the comments/suggestions. There's no ASHP. We'll be using a boiler and a hot water cylinder. The GF and FF are beam and block so heat rising from downstairs to FF will be blocked or kept to minimal by B&B. A bit naive/inexperience to got with B&B FF but it's fitted now. I just feel that if I don't use zoning there we'll be unnecessary heating empty rooms when kids are out. I suppose the heating in bedrooms can be turned off/down during when not required?
  23. Hi I'm looking for some advice regarding UFH design and zoning on both GF and FF. I have received the attached pipe layout plans for GF and FF from Wunda. I know a lot of people here don't prefer zoning but I think zoning will work for me. On the GF, we have an L shape open plan room and I have split that into three zones. The utility room is a secondary kitchen (demanded by my other half). Should it be zoned? In regards to FF, I think I've definitely over done the zoning. I prefer each bedroom to be zoned. Should the the hallways and bathrooms be zoned. How can this initial UFH design be improved? Any suggestions/comments are highly appreciated. Thanks
  24. Hi Thanks @Redoctober for sharing the photos back in 2019. I hope you don't mind me using your UFH photos posted elsewhere on buildhub. We will be laying liquid screed first and then plastering as suggested by many and as shown in the photos by @Redoctober. We will too be screwing the manifold to MDF board and then screwing MDF board to concrete block wall. All good so far. However, I'm unsure about how the plastering (dot and dab and skimming on a concrete block wall) will be done behind the manifold MDF board? If it's just as simple as tilting the MDF board forward then will that damage the screed or pipes/connectors? Thanks
×
×