Plot purchased 7th Jan, planning decision in 4 days. Plans are finalised and ready to sign build contract. It's going to be a busy year. Look forward to tapping into people's experiences and hopefully get some good advice.

PXL_20240322_150620029.jpg

  • Like 2
Posted

So you put in for planning before purchasing the plot?  And had the build contract ready to sign!  Good going.

 

What would happen if PP refused?

  • Like 1
Posted
  On 21/01/2025 at 14:00, Rosslyn said:

Plot purchased 7th Jan, planning decision in 4 days. ...  hopefully get some good advice.

 

Expand  

 

Welcome.

My oh my, you're out of the blocks faster than Donald Trump on a double dose of Fentanyl-supercharged laxatives. Long shot... that house looks like one I know in Stonesfield  .... 

Welcome anyway

Posted
  On 21/01/2025 at 14:17, mjc55 said:

So you put in for planning before purchasing the plot?  And had the build contract ready to sign!  Good going.

 

What would happen if PP refused?

Expand  

SODC delayed the planning decision by requesting a Bat survey that had already been submitted, rather odd. I have had positive support so far and didn't want my programme to slip 🤞

Posted
  On 21/01/2025 at 14:56, ToughButterCup said:

 

Welcome.

My oh my, you're out of the blocks faster than Donald Trump on a double dose of Fentanyl-supercharged laxatives. Long shot... that house looks like one I know in Stonesfield  .... 

Welcome anyway

Expand  

No it's not Stones field but a lot of these bungalows are very similar. No time to lose!

  • Like 1
Posted
  On 21/01/2025 at 16:00, Rosslyn said:

No it's not Stones field but a lot of these bungalows are very similar. No time to lose!

Expand  

Hi and welcome. 
 

I worked on a replacement dwelling in Headington, and I have to be honest it is just great to see old, inefficient bags of 💩 from an era gone by being razed and replaced with something great. 
 

That was an ICF build. 
 

Are you allowed a 2-storey replacement or 1.5 with room in roof / other? Bungalows seem (imo) such a waste of a good bit of ground space. 

Posted
  On 21/01/2025 at 16:46, MikeSharp01 said:

Welcome to THE forum for people like us! What is your build method, Brick & Block/ Timber  frame / ICF / SIP / .....?

Expand  

Using Danwood so SIP construction that should take 6-8wks on site.

Posted
  On 21/01/2025 at 17:12, Nickfromwales said:

Hi and welcome. 
 

I worked on a replacement dwelling in Headington, and I have to be honest it is just great to see old, inefficient bags of 💩 from an era gone by being razed and replaced with something great. 
 

That was an ICF build. 
 

Are you allowed a 2-storey replacement or 1.5 with room in roof / other? Bungalows seem (imo) such a waste of a good bit of ground space. 

Expand  

It's described as 1.5 floors but just over 8m high so lots of room upstairs. Lovely big plot so much better house for the location.

  • Like 1

Create an account or sign in to comment

You need to be a member in order to leave a comment

Create an account

Sign up for a new account in our community. It's easy!

Register a new account

Sign in

Already have an account? Sign in here.

Sign In Now
×
×
  • Create New...