CalvinHobbes Posted December 26, 2022 Share Posted December 26, 2022 Looking at the stages as given by building control,when does commencement actually begin? Do we have to tell building control before the old house comes down? (No cil in NI). I had it in my head building control got involved from foundations up. Link to comment Share on other sites More sharing options...
Declan52 Posted December 26, 2022 Share Posted December 26, 2022 Don't think they care about that part if its a complete demolition. But it does no harm to phone them up and touch base and explain that your starting the demolition and hope to have the digger in X amount of weeks doing the founds and what's the best number to get you on. Most of them are pretty sound here once they see your doing things the right way. 1 Link to comment Share on other sites More sharing options...
Conor Posted December 26, 2022 Share Posted December 26, 2022 No, just make sure you have your planning sorted. Don't need BC until you sif your founds / drainaged 1 Link to comment Share on other sites More sharing options...
ETC Posted December 26, 2022 Share Posted December 26, 2022 Commencement is digging (a) foundation(s) and Building Control need to see the trenches before concrete is poured. Not interested in demolition but could be involved if a dangerous structure being demolished. Planning could be interested but not BC. 1 Link to comment Share on other sites More sharing options...
Recommended Posts
Create an account or sign in to comment
You need to be a member in order to leave a comment
Create an account
Sign up for a new account in our community. It's easy!
Register a new accountSign in
Already have an account? Sign in here.
Sign In Now