goodchippy66 Posted July 21, 2022 Share Posted July 21, 2022 im stuck waiting on engineers calcs for an internal steel and possible concrete pads under the opening of the original back wall so cant pour the slab, im adding 2 mtrs on the back of an existing extension and obviously bc want to see type 1 sand dpm x2 insulation etc etc but i cant do that yet . wil bc mind if i start on external brickwork as im waiting cheers Link to comment Share on other sites More sharing options...
Jenki Posted July 22, 2022 Share Posted July 22, 2022 My suggestion is ask them. But I would also say, that usually as long as they can see what is done, they usually fine. They are not bothered with the order of jobs carried out, just that it conforms to regulations. I always have a kick off meeting with BC to get a feel for them and them a feel for me, this usually allows for some discretion / photos as proof in these situations. Link to comment Share on other sites More sharing options...
goodchippy66 Posted July 23, 2022 Author Share Posted July 23, 2022 On 22/07/2022 at 08:32, Jenki said: My suggestion is ask them. But I would also say, that usually as long as they can see what is done, they usually fine. They are not bothered with the order of jobs carried out, just that it conforms to regulations. I always have a kick off meeting with BC to get a feel for them and them a feel for me, this usually allows for some discretion / photos as proof in these situations. thanks for the reply, yes il call her monday i think, i want it right bottom line without any extra demo Link to comment Share on other sites More sharing options...
Temp Posted July 23, 2022 Share Posted July 23, 2022 In case relevamt.. BC typically want to see the bottom of any foundation trenches before they are filled. Otherwise take lots of photos of anything they won't be able to inspect later. Link to comment Share on other sites More sharing options...
TonyT Posted July 23, 2022 Share Posted July 23, 2022 Don’t you have to notify that works have commenced on site with 7 days notice? after that if they aren’t coming to site.. that’s their problem. just take lots of photos as evidence. Link to comment Share on other sites More sharing options...
Conor Posted July 23, 2022 Share Posted July 23, 2022 Have you submitted drawings and have they been approved? In that case you should get them out at the normal foundation stage. If you've not submitted drawings and/or got approval, I wouldn't start. I did this a few years ago and got a stern word of "advice" from the BCO. Link to comment Share on other sites More sharing options...
Jilly Posted July 23, 2022 Share Posted July 23, 2022 Are you going Full Plans or on a Buildi g Notice? Link to comment Share on other sites More sharing options...
Recommended Posts
Create an account or sign in to comment
You need to be a member in order to leave a comment
Create an account
Sign up for a new account in our community. It's easy!
Register a new accountSign in
Already have an account? Sign in here.
Sign In Now