gwebstech Posted July 16, 2019 Share Posted July 16, 2019 (edited) Hi all Im getting ready to pour my concrete into the trench weve dug. The trench is about 1m deep, the building notes say 700mm conrete into that, then build the substructure from either 7n concrete blocks and or engineering bricks. Seeing as laying the initial first courses in the superstructure is slow and time consuming (ie expensive as i cant lay bricks well) im wondering what the maximum depth of concrete i can pour in? i know the engineering bricks/blocks have to be filled with concrete to strengthen them, but am i determined by where the DPC will be and the concrete cavity fill has to be a certain depth below the DPC? Can i put more concrete in and save a couple of courses of bricks? thanks Edited July 16, 2019 by gwebstech Link to comment Share on other sites More sharing options...
bassanclan Posted July 16, 2019 Share Posted July 16, 2019 I guess you mean deep trench fill concrete strip foundations. If the build is brick/block then there's no reason not to pour the concrete to say 100mm below the top of the trench Link to comment Share on other sites More sharing options...
gwebstech Posted July 16, 2019 Author Share Posted July 16, 2019 Hi yes it is trench fill But in my notes from the architect it says that its cavity filled with concrete to either 225mm below DPC or 150mm below, im not sure which is rigt and why it states 2 differing options thanks Link to comment Share on other sites More sharing options...
Temp Posted July 17, 2019 Share Posted July 17, 2019 NHBC say 225mm cavity below dpc. Can be reduced to 150mm if there are weep holes.. http://nhbccampaigns.co.uk/landingpages/techzone/previous_versions/2011/Part5/section1/sitework.htm 1 Link to comment Share on other sites More sharing options...
Temp Posted July 17, 2019 Share Posted July 17, 2019 If building a brick outer, block inner cavity wall you usually arrange for both inner and outer to end up at same height at the dpc which is typically at least 150mm above ground. Bricks and blocks are different heights so some combinations achieve this and some dont (unless you cut blocks). Plan ahead and this determines the ideal height(s) to fill the trench to below dpc. Link to comment Share on other sites More sharing options...
nod Posted July 17, 2019 Share Posted July 17, 2019 12 hours ago, gwebstech said: Hi all Im getting ready to pour my concrete into the trench weve dug. The trench is about 1m deep, the building notes say 700mm conrete into that, then build the substructure from either 7n concrete blocks and or engineering bricks. Seeing as laying the initial first courses in the superstructure is slow and time consuming (ie expensive as i cant lay bricks well) im wondering what the maximum depth of concrete i can pour in? i know the engineering bricks/blocks have to be filled with concrete to strengthen them, but am i determined by where the DPC will be and the concrete cavity fill has to be a certain depth below the DPC? Can i put more concrete in and save a couple of courses of bricks? thanks Our footings were between 1500 and 1800 deep There was a delay in starting which meant a November start The whole site was flooded So I took the decision to full fill the trenches This saved me time and money 1 Link to comment Share on other sites More sharing options...
PeterW Posted July 17, 2019 Share Posted July 17, 2019 We backfill with EPS and weak mortar below DPC and use a step DPC with weeps above to close this cavity off. Only downside about bringing your trenchfill up to the top is you have to make sure that you have enough space over the top of the founds to get any drainage or other services out through the wall as you will be very high up. Alternative is you sleeve the pipework and reinforce appropriately. 1 Link to comment Share on other sites More sharing options...
gwebstech Posted July 17, 2019 Author Share Posted July 17, 2019 thanks for the help guys Link to comment Share on other sites More sharing options...
joe90 Posted July 17, 2019 Share Posted July 17, 2019 (edited) We backfilled with extruded polystyrene insulation to avoid a cold bridge (see https://www.greenbuildingstore.co.uk/golcar-passivhaus-ground-floor-foundations/. Edited July 17, 2019 by joe90 Link to comment Share on other sites More sharing options...
Recommended Posts
Create an account or sign in to comment
You need to be a member in order to leave a comment
Create an account
Sign up for a new account in our community. It's easy!
Register a new accountSign in
Already have an account? Sign in here.
Sign In Now