  1. Also no cylinder paperwork found on site ( guy who installed it said it was there ) . So now asking builder where it is . Who wants to bet their isn’t any .....
  2. Already done !! . I’ll give him until Monday then call him if no replies. Really want this sorted as he said any screed needs to cure for 30 days before they waterproof.
  3. I suspected as he tapped into the boiler discharge pipe it would all be 15mm ; and it is . So really I want the boiler discharge pipe to be 28mm ( safe side ) and all the pipe work back to the bottom of the tundish 28mm also . That correct ?
  4. Right ! Finally all clear - still waiting for SIG man to get back too me after initial visit
  5. Don’t doubt it’s a simple job . He said fitting the tundish took 5 minutes . So it wasn’t about saving time or money ( his ! ) ; just I guess decided it wasn’t necessary . I’ll take better photos of the pipe work . If that’s the only thing that needs altering then perhaps I can get that done as a seperate job .
  6. ? No point me getting back to him on this . I’ll get it ‘serviced’ by another penis ? ; I can also see if the new guy picks up on that ....
  7. I’m not at the property but he sent me a photo of the tundish installed .
  8. Here’s his reply @Nickfromwales All hot mixers and showers come from the tank apart from the downstairs sink which is supplied by the combi boiler. All the colds come from the balanced cold connection of the pressure reducing valve.
  9. ? I’ve text him about the cold coming off balanced output group . Hopefully the answer is simply “yes”
  10. Just wait ; watch the decline.....
  11. Oh tell me about it . There’s zero support when it goes this wrong . Trust me ; police don’t care ; mental health don’t care ; council don’t care . All down too me ......
  12. I couldn’t give an f what they do as long as they don’t damage my property ! . It cost a small fortune to renovate!!
  13. I just googled it - they do exist . Easier to just stick a Cctv camera in there staring at it :-))
  14. Really ????? you got a link ??
  15. Can I have some wine now to release stress?
  16. Maybe JS ; I can't go back to him and say that. Piss him off too!. So I'll let the photo 'go' .....
  17. The problem is even with a tundish installed it's not visible. I'd have to manually say every 3 months ( not sure what frequency is required ) go and physically look at it. But if that's the 'solution' then so be it. Note for judge in event of accident: I have requested a tundish be installed. I'm not liable in anyway for an explosion via the cylinder as far as I am aware was installed to meet regulations.
  18. Requested cylinder guy to fit a tundish. I see his 'logic' though. But I can't take the risk of a serious issue and by liable. Stained ceiling it is!
  19. Hurt by the absence of a tundish? Again I take your point. But the water ( via tundish or other means ) still leaves the property. I can asked him to fix one. Then when it leaks I'll just get a water stain on the ceiling below indicating there's a problem.
  20. He's just sent me a photo of a corroded tundish left leaking......
  21. I don't like this thread anymore. Can't we talk about defunct walk on glass or leaky underground house roofs like before......?
  22. ?No sleep again. I take your point JS ; but I now have some evidence ( this thread ) . In essense an 'overflow' can occur just as it would with a turdish ; with more chance of me seeing it as it's external. Just aswell I have 2 million liability insurance. ?
  23. Right! You lot ain't going to like this...... ? Spoke to installer. Confirmed he is G3 and paperwork will be with the cylinder (so I'll grab that tomorrow) He said a tun dish could be installed if I want. He has been requested by other customers due to the corrosion and leaks to remove them (said he would send me a photo if i wished). Given this situation i.e. a HMO where nobody cares/checks anything he felt it foolish to stick it in a cupboard where it will never be viewed. It goes into the boiler overflow/expansion pipe (boiler is literally next to the tank) - so any issue will overflow outside which I can easily check. He IS interpreting the rules to suit the situation (which I know you'll all say is wrong). BUT! as a LL I interpret rules and indeed sometimes deviate to suit a situation. But this doesn't make me right! So yes he has adapted to suit the situation (which as I said you could agree is incorrect). Bit like my leaky roof; the standard 'follow the text' solution is no good for that situation. I'm much happier after speaking too him; and will be even happier once I have grabbed the paperwork. He was going back tomorrow to sort out some timer issue ( though I said timers for hot water is largely pointless in an HMO where hot water is required 24/7 ). So! @Nickfromwales if it blows up in the night killing 6 tenants - I'll be legally covered ; as he has certified and commissioned the install. I shall sleep tonight - until of course you all reply........... ( remember I'm just the customer not the bomb maker! ) ?
  24. Spoke to gas safe. There is NO installation that doesn't require a tundish (though he admits without seeing it a bit difficult) He agreed that 'what else' could be wrong and a 2nd opinion might be worth it. Rather than piss the builder off more i.e. let him finish his stuff; I shall wait. Assuming gas guy gets back too me... but it's hard to imagine what he can say "you don't need it mate" - he has no justification. Which means I will need a 2nd opinion and check....... FFS! As usual being done over by trades - that's 3 out of 3 now!