Jump to content
  • entries
    5
  • comments
    45
  • views
    1270

Tour d'horizon: countdown to the start…


Dreadnaught

2377 views

I am hoping to start work on site in May, about two-months later than my original plan. Things may well slip further and I am fine if they do.

 

Currently, the timber frame is being designed, by a specialist frame-designer based in Herefordshire that was recommended by (and contracted via) my chosen local timber-frame company. And the frame designer has just sent me the line-and-point loads (see below), so I have in turn just sent those on to my foundations designer in Ireland so that the insulated concrete-raft foundation can be designed in parallel with the frame. (To save on VAT, I also contracted the foundation designer via my frame company.)

 

In parallel, with this, I am in the midst of arranging a fibre-optic data connection to my plot. I already have electricity connected. The fibre connection comes from a local fibre ISP who have been pleasingly helpful. The connection requires a new overhead wire from the end of the access road about 40-metres to the gable of my neighbours house and thence down to the ground and on to my plot. My neighbour is being most obliging, partly because he also gets a connection and can drop VirginMedia, who has been unreliable for him. To my astonishment, the whole installation will be free as I, it seems, am eligible for a voucher from the government that covers the cost. The voucher does not cover the VAT but the company kindly agreed to absorb that cost themselves (!) when I mentioned zero-rating.

 

I am getting closer to choosing a groundworks team and finalising the details of the groundworks. I am pushing the boundaries of what is acceptable for what is supposed to be a "no-dig" build but it will all be done with expert tree-specialist oversight. I need clay heave protection which will be 220mm thick so digging down about 375mm was needed if my final floor level was not going to be high in the air. For my screw piles, I will probably go for a supply-only deal for the ground screws themselves and have the groundworkers install them with a mini digger (in my presence). I am told that installation is simple.

 

For the installation of the insulated concrete raft, I still have not identified who will be the installer. I am tempted to speak to all the local concrete pourers to see if I can find someone who has experience of insulated rafts. The raft design is going to slightly unusual. Because the insulation is not load bearing and because I have a ridge height restriction and want tall ceilings, the insulation will be thinner PIR rather than the usual EPS.

 

To my distress, the local water company has insisted I make a water connection all the way 40-metres back down in the access road to the 5" water main there rather than 2" main directly in front of my plot, citing "the impact of another service". Oh well at least the water pressure will be good!

 

I need now to apply for my drains connection. I had been waiting on the tree matters to be resolved as it has an impact on the trench routes.

 

For the protected trees around may plot, I have just finalised the Arboricultural Method Statement (AMS) with my tree advisers. This unlocks the chance for me discharge my nine planning conditions, all in one go. It took a surprising amount of time to work out how this is to be done, requiring a counterintuitive use of the planning portal to create a new planning application (!).

 

I have paid deposits for my windows and front door (IdealCombi) and my roof lights (Roof Maker, their passive-house-certified product).

 

Bauder, my chosen warm-roof and green/sedum-roof supplier, has been very helpful with advice on matters such as waterproofing when the rooflights are too close to the edge, and on standard roof-edge details for my architect. As soon as the frame-design is ready, I will be tendering among the local Bauder-approved installers.

 

I have identified my brick-slips cladding I will use (Eurobrick P-Clad) and worked with my architect so the corners and window openings are properly proportioned for the brick counts. I have just booked myself on a slips training-day for 2nd April in Bristol.

 

On my to-do list are signing up for building control, warranty company (reluctant purchase) and buying site insurance. I also need to arrange some bespoke aluminium copings and profiles.

 

The intention is that the frame will go up, the roof will go on, and the windows and rooflights will go in, in quick succession followed in short order by brick-slips cladding. With all of these done and installed, I will have a weathertight shell ready for first fix to start, perhaps around mid-summer time.

 

Hopefully. (I am already dreaming about @nod-style metal framing!)

 

I have been continuing to visit other Buildhubbers, with visits to two people installing Fermacell, and one Buildhubber all the way at the end of second fix. As always, I learn so much from these visits and am gratified by everyone's immense generosity. They are truly inspirational. And thanks to everyone at BuildHub for all the advice I havre received (and will undoubtedly receive in the future). The journey is just beginning.

 

Comments, observations, guidance, suggestions welcome, as always ? 

 

866340081_Screenshot2020-03-06at14_13_44.thumb.png.631195f11064a827779412f44fbee03b.png

  • Like 5

6 Comments


Recommended Comments

A huge amount of progress reflecting, no doubt, what must have been a huge amount of work to get to this stage.  The delayed start may not be such a bad thing given the biblical weather we've been having as many projects have stalled over the last couple of months due to the storms. 

Link to comment

@Dreadnaught I have seen this some of your other posts. I’m keen to learn about your screw piles as this is what I want to do for my new build in Surrey as I wanted speed for install and avoid muck away down a narrow winding country lane.  I have a quote to supply and fit but it was double what I expected. I have and can drive my digger so keen to learn where to get supply only and what size digger and rotary mech is needed. 
I’m looking to start Grd works in June so working hard now to finalise all the elements of the waterproof box incl suppliers and costs etc. 
My build is a 275m2 bungalow with 2 pent roofs (bit like a huf haus)  giving vaulted ceilings inside. 

Link to comment

Hi @Steve247, I too am learning my way with screw piles. But from what I have picked up by speaking to a number of suppliers is that their installation is considered to be quite easy. And that a competent digger driver should be able to handle the torque drive attachment. And a challenge comes only if ground conditions prove to be problematic (so that impenetrable rock is met during driving a given ground screw). 

 

Who provided your first quote (PM me if you prefer). I have a few names of suppliers and we can compare notes.

 

By the way, I like the design that you describe for your build. Sounds great!

Edited by Dreadnaught
Link to comment

Hi @Dreadnaught. I've been reading your blog with interest and I look forward to following the rest of your journey! we're not a million miles behind you in our plans and I have a few questions for you if you don't mind.

 

1. what is the government grant for your fibre all about? we've had our quote from Openreach to put a new fibre connection in running from a pole, under the road and on to our plot. here's their scope of works:

 

Description of works

Second Stage of Work Full Scope of Works

Property is to remain and lived in while they build a new house in the garden which they would like via an underground feed. When the property is completed they will move into the new property and would like to fibre if available. The current property will then be demolished at a later date.

REQUIREMENTS
PHASE 1
Civils to dig in approx. 15m (metre) duct 56 from CP (carrier pole) 1A to boundary of xxxxxxxxxxxx. Customer requires 1 x fibre to property – Openreach to supply details of nearest node to use.
THIS QUOTE DOES NOT INCLUDE FIBRE IN ADVANCE.
TM (traffic management) – ROAD CLOSURE REQUIRED DUE TO WIDTH OF ROAD

N.B - Please note that this survey return is as seen during the survey and that these works may be subject to additional excess costs if any unforeseen or unobserved variations are determined during the execution of those works, or if there has been scope creep or changes to planned work after this survey was produced.

 

for this they're charging us almost £6k inc. VAT

 

We already have a phone line to the existing bungalow which will eventually be demolished but require the new connection to the new location on the plot. can you offer any advice on where I can go to look up this government grant you received?

 

2. We've shortlisted IdealCombi as a window supplier but due to Covid-19 haven't been able to get to see them in the flesh. I assume you did. if so, what do you think of the quality of the windows and, more specifically, the front door? the price difference between the IC front door and an Internorm equivalent is huge! I was just wondering if you'd seen the front door and physically touched it etc to compare the differences with other more expensive front doors.

 

thanks in advance.

 

Tom

Link to comment

Thanks @Thorfun. Likewise!

 

1 hour ago, Thorfun said:

what is the government grant for your fibre all about?

 

This is the scheme: https://gigabitvoucher.culture.gov.uk. A voucher is arranged by the ISP not the final user. I was able to get one by working with ISP and by showing that I work from home, which entitled me to a £2,500 voucher, whereas the more usual one is just £250 or so.

 

My advice would be look for small local broadband companies installing fibre and talk to them. I made a list of the local ones in my city, Cambridge, and might have just been lucky to have found one keen to connect me and a neighbour up. 

 

I have heard the scheme is changing so I recommend being quick. In fact it might have already closed, although I wonder if there will be another scheme to replace it.

 

1 hour ago, Thorfun said:

We've shortlisted IdealCombi as a window supplier

 

I visited them and Velfac (which is related to Rationel). And I am familiar with a few other window manufacturers, like Gaulhofer, InterNorm and Norrsken. I am not one to spend ages agonising over such a choice. My choice of IdealCombi & Velfac over the other manufactures was purely because the of style of window frames, which appealed to me. And once I had chosen the windows, it seemed sensible to include the front door too. In terms of quality, they seemed fine to me but I don't consider myself an expert as these will be the first windows I have ever bought. 

 

In comparison to buying other things for may build, such as the roof windows, Ideal Combi (and Velfac for that matter) were a breeze to work with. Very efficient, helpful and quick. Easy to negotiate with. And I also thought they were good value for money.

 

I've seen your other thread inviting comments on the front door, which I am following with interest. I can't explain the price difference other than with a slight suspicion that other doors may have slightly better insulation and wider range of fittings. Only a guess. I suspect perhaps the biggest issue may be wider margins necessitated by a different sales model using local agents.

 

Hope that helps. 

 

Edited by Dreadnaught
Link to comment

Create an account or sign in to comment

You need to be a member in order to leave a comment

Create an account

Sign up for a new account in our community. It's easy!

Register a new account

Sign in

Already have an account? Sign in here.

Sign In Now
×
×
  • Create New...