Jump to content

Accessible Ablutions 3 - Half Way Photos


Ferdinand

2180 views

This project has now been going for a week, and should be finished with just under another day of work.

 

Tiling and grouting has been done, and it is now just to fit the shower, the loo, and install shower screen and those grab handles etc that we have obtained so far. Then it will a case of experimenting and putting the final touches in as the shower is used.

 

Here are a few slightly rushed  photos taken at this stage.

 

Two runs of pipe installed for the future just in case, which go through to where most of the plumbing related gubbins live beyond the other end of the bathroom.

 

IMG_0823-s.jpg

 

Shower tray protected from the slings and arrows of outrageous fortune.

IMG_0816-s.jpg

 

Access hatch for future maintenance

 

IMG_0829-s.jpg

 

Give it a shout - get on and grout. It's Friday.

 

IMG_0818-s.jpg

 

Nice corner detail

 

IMG_0828-s.jpg

 

Stay out and let it set

 

IMG_0826-s.jpg

 

If anyone has any bright ideas, I need to have a set of hooks about a foot below these. Is there any product that hangs hooks off the other hooks?

 

IMG_0817.JPG

 

We should have wrapped up by Monday afternoon, and I'll aim to do one more piece, with details and costs.

 

7 Comments


Recommended Comments

When's the lift going in for the shower tray?! Sorry couldn't resist with thread title

  • Thanks 1
Link to comment
14 hours ago, Oz07 said:

When's the lift going in for the shower tray?! Sorry couldn't resist with thread title

 

Degrees of Accessibility.

 

We do not need wheelchair access - which would have required rather heavier digging into the slab, including the ufh, than we would do now. And the waste pipes are badly positioned for doing that.

 

If push came to shove we could raise the floor 100mm in the shower / whb / loo are, and have ample space for a 1:12 ramp on the way in, or a 1:18 ramp if we reverse the door. There are also other alternatives; personally I like Ski Jumps.

 

Thanks for the read.

Edited by Ferdinand
Link to comment
59 minutes ago, Oz07 said:

Why can't you screw another set of hooks further down anyway?

 

Unfortunately it is a panel door, and the panel is far thinner.

 

In theory I could screw something right across, but I would prefer to avoid more screw-holes.

 

The best idae I have is one of those concertina racks, but I suspect I have thrown about 3 of those away in enforced tidy-outs over the years.

Link to comment

Why not get a nice piece of wood to match the door and glue it on, I have been using that D4 flooring glue and I bet you would need a hammer and chisel to get it off. 

Link to comment
On 21/06/2019 at 08:01, Russell griffiths said:

Why not get a nice piece of wood to match the door and glue it on, I have been using that D4 flooring glue and I bet you would need a hammer and chisel to get it off. 

 

I have ended up doing that - a 75x25x1800 mm piece of oak was only £9.00 at the local Merchant, and I will just move the existing hooks onto this about 300mm down.

Edited by Ferdinand
Link to comment

Create an account or sign in to comment

You need to be a member in order to leave a comment

Create an account

Sign up for a new account in our community. It's easy!

Register a new account

Sign in

Already have an account? Sign in here.

Sign In Now
×
×
  • Create New...