dan_cup Posted 19 hours ago Posted 19 hours ago (edited) Hi, we are going to have LVT laid on the whole hall and kitchen section incorporating the new concrete and old suspended floor. our joists dip into this corner (floor boards are in a bad way as kitchen units have been on top for years) so I need to level up (sister some 5x2 onto the old joists sitting them proud?) you can see the run off from the concrete edge getting larger. i will then replace the T&G with 18mm (or more?) ply glued and screwed. Should I just butt upto the concrete, pass over the top so the SLC can butt upto it, or something else?? cheers Edited 19 hours ago by dan_cup
Nickfromwales Posted 17 hours ago Posted 17 hours ago If you have room for 22mm P5 boards, then do the base layer with that. Then go over with a thin layer of plywood as the binder for the LVT to go on to. Set the plywood binder to be higher than the concrete, and then feather the concrete into that with the SLC to get you snooker table flat; you need to be spot-on for LVY as it shows everything when the light is on it. Yes to sistering to get the joists ready for the P5, and use glue and structural screws to do this link, inserting them at a slight angle to use the whole length of the screw. Use resin wood glue, plenty of it, to join the two together forever. 1
Nickfromwales Posted 17 hours ago Posted 17 hours ago Concrete screw the last joist into the concrete floor to lock them to each other.
dan_cup Posted 11 hours ago Author Posted 11 hours ago 6 hours ago, Nickfromwales said: If you have room for 22mm P5 boards, then do the base layer with that. Then go over with a thin layer of plywood as the binder for the LVT to go on to. Set the plywood binder to be higher than the concrete, and then feather the concrete into that with the SLC to get you snooker table flat; you need to be spot-on for LVY as it shows everything when the light is on it. Yes to sistering to get the joists ready for the P5, and use glue and structural screws to do this link, inserting them at a slight angle to use the whole length of the screw. Use resin wood glue, plenty of it, to join the two together forever. Cheers Nick, my floorboards now are measuring 21mm so P5 would work. my builder that’s been doing the extension part suggested I use 18mm ply, biscuited at regular spacing to create the strength along the edges. This would also be the final layer of the LVT. the flooring people are, as you suggested, talking about a thin layer over the board I fit. So I’m all over the place with what to do! the P5 does seem far more affordable that 18mm ply. But is it as strong? cheers
Nickfromwales Posted 10 hours ago Posted 10 hours ago 22mm P5 is used in every new build, so yes, it’s perfectly fine. Listen to the LVT installers and not the builder, he’s wrong and they’re right. You need the plywood binder as the final prep before the LVT goes down. Go 22mm + 6mm, and then ask the LVT installers to level (aka feather) the self leveller over the concrete section to suit. Don’t let the builder do it. 1
saveasteading Posted 9 hours ago Posted 9 hours ago 9 hours ago, dan_cup said: joists dip into this corner ( Do you know why? We should overcome the reason for this at the same time. 1
dan_cup Posted 9 hours ago Author Posted 9 hours ago 36 minutes ago, saveasteading said: Do you know why? We should overcome the reason for this at the same time. Honestly not sure, the whole house seems to run off in this direction. From the sink side the boards are level with the concrete, by the end of the arrow there’s a 30mm drop.
saveasteading Posted 4 hours ago Posted 4 hours ago Some houses are built like that because the builder couldn't use a spirit level. Others move quite a lot more than we would like to think. So in your case, there is no sign of rot at joist ends? That's OK then.
dan_cup Posted 3 hours ago Author Posted 3 hours ago 51 minutes ago, saveasteading said: Some houses are built like that because the builder couldn't use a spirit level. Others move quite a lot more than we would like to think. So in your case, there is no sign of rot at joist ends? That's OK then. Yes at the end I’m interested in the joist are good, solid and firm inside the brick wall slots. On the opposite side by the sink two or three were in poor condition so my builder has already ran new ones sistered and onto dwarf wall and into the wall pocket.
Nickfromwales Posted 2 hours ago Posted 2 hours ago 1 hour ago, dan_cup said: Yes at the end I’m interested in the joist are good, solid and firm inside the brick wall slots. On the opposite side by the sink two or three were in poor condition so my builder has already ran new ones sistered and onto dwarf wall and into the wall pocket. May be a good time to spray treat with woodworm / rot preventative chemicals, if it's getting all covered over for the forseeable. 1
saveasteading Posted 2 hours ago Posted 2 hours ago 22 minutes ago, Nickfromwales said: spray treat with woodworm absolutely. I was going to say to use treated timber, but spraying the existing joists is wise. Woodworm and rot.
Temp Posted 10 minutes ago Posted 10 minutes ago Would it be possible to jack up the joists and put packing (or just DPC) under the ends?
Recommended Posts
Create an account or sign in to comment
You need to be a member in order to leave a comment
Create an account
Sign up for a new account in our community. It's easy!
Register a new accountSign in
Already have an account? Sign in here.
Sign In Now