July 20, 20251 yr Back in the day (a long time ago )when I was a labourer, we were a gang of three. 2 brickies and myself. Estimators online are stating that below DPC, internal sleep walls and then DPC to plate as 20 days labour and with a labour cost of 20k. Given brickies are ~£300 an a labourer £200?, This is still seems high and considering I just received a labour only quote of 30k. I am thinking that either estimators is wrong, or the brickie who has quoted is expensive.
July 20, 20251 yr On 20/07/2025 at 17:05, flanagaj said: Estimators online are stating that below DPC, internal sleep walls and then DPC to plate as 20 days labour and with a labour cost of 20k. Just out of interest how deep are your foundations and how many linear metres is that?
July 21, 20251 yr Author 12 hours ago, G and J said: Just out of interest how deep ate your foundations and how many linear metres is that? I hit chalk within a metre, so planning on using strip foundations. Estimators have gone with trench fill and they have listed the following m2 figures. Block solid concrete 7.3Kn 100mm, cavity walls. M2 62.983 Block solid concrete 7.3Kn 100mm, internal walls. M2 20.583
July 21, 20251 yr I lost my Brickies for the foundations on the first day It only took my wife and myself five days Pay them £18 meter
July 26, 20251 yr Author On 21/07/2025 at 10:32, nod said: I lost my Brickies for the foundations on the first day It on took my wife and myself five days Pay them £18 meter @nod Apologies, but can you clarify what you mean, as I didn't understand a word of it. I am also very interested in the approach taken with the construction method. So I see you have got a solid 100mm + 225mm + 100mm wall? I have not seen this before and always assumed that you just laid the blocks as standard and then filled the cavity with concrete. Is this an alternative option to that approach?
July 26, 20251 yr I used the 100 mil solids to add extra width on the foundations As i had a plinth wall running around the front and and side and six inch solids at the rear elevation due to an architect's cock up Due to Covid there was a 9 week delay on the correct width foundation block This was part of why the Brickies walked off My wife has just prompted me and said you You did call them wining little Bitc##s and tell them if you don’t like it F##k off Start as you mean to go on Don’t let anyone hold you to ransom
July 26, 20251 yr 2 hours ago, nod said: Bitc##s Only a bit of a (expletive deleted), not the full marsey.
August 21, 20251 yr As a bricklayer of 22 years. Let me tell you now that day rate for a bricklayer is about £230 and £160 for a labourer. For £300 day rate, I’d want a 10hr shift done. £675 a thousand on standard stretcher bond and bucket handle pointing. £17m2 on 4inch concrete or thermalite.
August 22, 20251 yr Author 19 hours ago, DannyT said: As a bricklayer of 22 years. Let me tell you now that day rate for a bricklayer is about £230 and £160 for a labourer. For £300 day rate, I’d want a 10hr shift done. £675 a thousand on standard stretcher bond and bucket handle pointing. £17m2 on 4inch concrete or thermalite. So my most recent quote of 60k for below DPC and then up to plate is a bit steep 😂
August 22, 20251 yr Lincolnshire. Day rate - labour only. From found to wall plate inc two external gables and one internal. 101m2 external 150mm cavity wall. Brick/block with English garden wall bond externally. 45m2 internal block some 140mm and some 100mm. All “technicians” work I.e tray, taped insulation, stays etc. insulated block and beam with reinforced slab atop. couple of days left but currently sitting at 13k and forecasting to finish under 18k
Create an account or sign in to comment