CIL complication


Recommended Posts

Posted (edited)

Our self build is on part of a development currently awaiting planning permission (hopefully with a decision this coming week). We have understood what paperwork we need to do, when and in what order. Our complication is that, not only do we have to wait 2-3 years for them to build down to our plot so that we can start but, the developers of the site have tacked our self build onto their planning application. Having just re read the CIL requirements again I see there is a Form 1 which is submitted with planning. Because we are included in their planning application do we also need to submit Form 1 ourselves?

TIA

Edited by Selfbuildsarah
Typo
Link to comment
Share on other sites

You need to get it removed and put on a separate application We have two plots and whilst we realized we could only qualify for one Cil Our cil application was refused as we had included the other plot on our ap Even though we only intended putting the foundations in for the second 

The chap at the Cil office was really good and explained By putting in for two houses I’d become a developer 

I changed the application and they quickly sent out anther email exempting us from the 65 k That would have been due three weeks from breaking ground

 

Link to comment
Share on other sites

Why have they added your self-build to their application. That doesn’t seem good for you or them? And how have you ended up in a position where you are reliant upon them building down to you before you can start? 

Link to comment
Share on other sites

Kelvin, they were trying to be helpful and save us time, hassle and money. We always knew we were going to have to wait until they were well into the build as our plot is adjoining a piece of land not included in the sale at the bottom of the development.

Link to comment
Share on other sites

Posted (edited)

Fair enough but personally I’d want everything to be separate and as straightforward as possible. What happens if they run into trouble part way through their development and have to stop for some reason so it takes much longer than 2 or 3 years or go bust? Where would it leave you? These things happen. Not pouring cold water on your plans. It’s exciting building a house. But it’s also risky and stressful. And things go wrong. 

Edited by Kelvin
  • Like 1
Link to comment
Share on other sites

6 hours ago, nod said:

Then you have no problem 

They can only go off the planning application Remove yours Job done 

Link to comment
Share on other sites

Posted (edited)

The planning application is for 120 houses plus one self build. What I’m asking is, do we have to submit a Form 1 prior to submitting a Form 7 because it’s not our application, it’s the developers?

Edited by Selfbuildsarah
omission
Link to comment
Share on other sites

If anything, including your property within the original application has not made the situation very easy… not just in terms of CIL but also any other Planning obligations and conditions.

Link to comment
Share on other sites

  • 2 weeks later...

Sorted!
Planners require Form 2 Assumption of Liability form from the developer covering their units and also one from us covering our self build.
Form 7 Self Build Exemption Part 1 from us going in at the same time.

Link to comment
Share on other sites

  • 2 weeks later...

Hi Alan, they have just revised this as the developers have said they are now phasing the build. In what way this affects things I’m not sure but CIL officer has said we also need to do a Form 6 now. We are away on hols at the moment. Will update when we get home. Like you, will send one anyway. Can’t be too careful.

Link to comment
Share on other sites

Create an account or sign in to comment

You need to be a member in order to leave a comment

Create an account

Sign up for a new account in our community. It's easy!

Register a new account

Sign in

Already have an account? Sign in here.

Sign In Now
×
×
  • Create New...