New Build: Windows Sequence vs Brickwork


Recommended Posts

I've a mix of brick and block (with render) in my build. We're measuring the windows off the actual timber frame when its erected. During the 8-10 weeks they'll take to arrive I wanted to get the outer block/brick leaf built and render the blockwork, do soffits, fascia, gutters etc. 

Met the brickie today and he prefers the windows to be installed so they can cosy up the brickwork. That would mean 8-10 weeks of no work though and scaffolding I'll be paying for. I could take it down but is there a middle ground that let's me get the brickwork done in advance before the windows arrive? 

Thanks!

Link to comment
Share on other sites

I did it differently, being OCD I wanted only whole and half bricks around openings and bespoke windows, the brickie was told the approx size and place of the windows and ordered the windows afterwards fitted to check reveals (Windows mounted on the inside of the outer brick skin in the insulation zone.)

  • Like 1
Link to comment
Share on other sites

Make up some formers with 4 x 2 timber cut accurately to your required structural openings on a chopsaw and screwed together.  Square them up and screw a piece of ply over the top corners.  Get you bricklayer to build up to these.

  • Like 2
Link to comment
Share on other sites

Make sure you get absolutely spot on  dimensions from the window company. Not done a TF myself for years but we used to have to leave a gap top & bottom around the frames to allow for differential settlement between the TF & masonry-worth checking what’s required now as the bricklayer will need that info too. 

  • Like 2
Link to comment
Share on other sites

Create an account or sign in to comment

You need to be a member in order to leave a comment

Create an account

Sign up for a new account in our community. It's easy!

Register a new account

Sign in

Already have an account? Sign in here.

Sign In Now
×
×
  • Create New...