June 23, 20233 yr I’m going to try and get the UFH and screed in over the next couple of weeks (168m2) We called in to a kitchen showroom where a friend of ours works to get a kitchen design done So I can set the pipe work out accurately We will self fit a German kitchen again Last time Nolte This time Hacker Previously 5 years ago the lead times where 8-12 week The lead time is down to 4-6 Not just the UK slowing down
June 23, 20233 yr Interesting times ahead. Last year the lead time for floor screed for my build was just over 12 weeks. (Outlying location contributes much to this)
June 23, 20233 yr Author I’m still very busy with my site work But it’s a false busy Work that was scheduled and re scheduled I think a truer picture will be after Christmas Whilst I’ll do the screeding myself over two separate days I’ve had two different screed companies offer to quote and I’ve lost count of the window company reps calling on 12 months ago when we first started There was a six week wait for a quote for block and beam Supply only What a difference a year makes
June 24, 20233 yr I signed off the plans for beam and block last Monday and it was delivered Friday morning. It took longer to get a dolly to put them in.
June 24, 20233 yr 6 hours ago, Canski said: I signed off the plans for beam and block last Monday and it was delivered Friday morning. It took longer to get a dolly to put them in. because recession is here.
June 24, 20233 yr 56 minutes ago, Dave Jones said: because recession is here. No it’s not Not (but Germany is!).