ADringer Posted September 1, 2022 Share Posted September 1, 2022 Hi all, Question about edge insulation - do you fit it on all edges or just external walls? And if it's external, does that include party walls? Thanks Alex Link to comment Share on other sites More sharing options...
Bonner Posted September 1, 2022 Share Posted September 1, 2022 All edges, reduces cold bridging and allows the screed to expand. Link to comment Share on other sites More sharing options...
ADringer Posted September 1, 2022 Author Share Posted September 1, 2022 16 minutes ago, Bonner said: All edges, reduces cold bridging and allows the screed to expand. That's what I thought, it's just our building regs drawing says for external walls. Link to comment Share on other sites More sharing options...
ETC Posted September 1, 2022 Share Posted September 1, 2022 External walls only but would do the party wall too. Not needed between heated spaces. Link to comment Share on other sites More sharing options...
ADringer Posted September 1, 2022 Author Share Posted September 1, 2022 5 minutes ago, ETC said: External walls only but would do the party wall too. Not needed between heated spaces. We've joined up the garage to our house now into a single heated space, so although they were external walls, they're not anymore. Does this count as internal now? Wasn't sure if it made any difference as some of the wall is only internal to single storey. Link to comment Share on other sites More sharing options...
ETC Posted September 1, 2022 Share Posted September 1, 2022 The garage will unheated so the wall between the garage and the dwelling needs perimeter insulation on the dwelling side. Link to comment Share on other sites More sharing options...
Shoestring Posted September 8, 2022 Share Posted September 8, 2022 Hi, we have just done this job on our house. The screed man & underfloor heating company specified we needed the blue foam (comes on a roll) for the internal walls and 25mm PIR for the external walls, the blue foam helps provide an expansion gap for the screed and the PIR is to stop thermal bridging. We cut our 25mm PIR to 100mm "skirting boards" on the external walls (for our 65mm of screed) and then cut them down to size after the screed was down and hard enough. Hopefully that makes sense and is of help to you! 1 Link to comment Share on other sites More sharing options...
JohnMo Posted September 8, 2022 Share Posted September 8, 2022 I just used 70mm PIR upstands on all external walls. Link to comment Share on other sites More sharing options...
Recommended Posts
Create an account or sign in to comment
You need to be a member in order to leave a comment
Create an account
Sign up for a new account in our community. It's easy!
Register a new accountSign in
Already have an account? Sign in here.
Sign In Now