Electric meter install


Recommended Posts

New build in progress. DNO installed their 3 phase cutouts in our external kiosk, but for various reasons postponed connecting the electric supply. They will shortly provide 3 phase supply.

 

After the DNO connects electricity, BG electricity will install a smart electricity meter.

 

Not familiar with any of this.

Is there anything we need to be doing before the electricity meter is installed in our kiosk? BG have not mentioned anything. Will they simply turn up and do their thing?

Link to comment
Share on other sites

 it maybe worth getting yourself 3x 100A main breaker and have BG them install them after the meter. Then your electrician can hook the breakers into the CU.  This makes life a bit easier if/when any changes are needed to the CU, no need to open the meter to disconnect it.

 

- Some meters have a main shut off built in, but not sure any 3ph smart meters do

- Some suppliers will automatically provision breakers after the meter, but not all will

 

  • Like 1
Link to comment
Share on other sites

Create an account or sign in to comment

You need to be a member in order to leave a comment

Create an account

Sign up for a new account in our community. It's easy!

Register a new account

Sign in

Already have an account? Sign in here.

Sign In Now
×
×
  • Create New...