How long after gaining planning permission does the CIL exemption get granted? 

 

We recently gained PP but have not heard anything from CIL dept.  Do they tend to contact us or should we contact them?  When compiling the form i recall we shouldn't start work until we have exemption granted...

Posted
36 minutes ago, Digger1 said:

How long after gaining planning permission does the CIL exemption get granted? 

 

We recently gained PP but have not heard anything from CIL dept.  Do they tend to contact us or should we contact them?  When compiling the form i recall we shouldn't start work until we have exemption granted...

 

Did you send in the CIL exemption claim form at same time as the PP application?  

 

If so I suspect they couldn't process it until PP was granted and not sure anyone will have told them.

 

 

 

 

 

Posted

They normally get in contact very soon after approval. But like with all things, they may be dealing with a current backlog. Maybe give it a couple of weeks and if you still haven’t heard, get in contact with them. 

Posted

Does the CIL dept take your word for the m2 of the new building or do they check themselves? 

 

We had to make some tweaks to our drawings after submitting the planning, therefore the CIL form i initially sent in is not accurate.  At £175pm2 i am keen for the calculation to be spot on!

Posted

It would depend how much it’s out. If it’s minor, i.e. a few square metres then I wouldn’t worry about it. If the increase (or decrease) is noticeable, then look to submit revised figures.

Create an account or sign in to comment

You need to be a member in order to leave a comment

Create an account

Sign up for a new account in our community. It's easy!

Register a new account

Sign in

Already have an account? Sign in here.

Sign In Now
×
×
  • Create New...