Water Posted August 18, 2020 Posted August 18, 2020 Hi all We are using a main contractor for our build, we are proposing a 5% retention which the contractor has accepted and they want this paid on completion. Is this normal? I thought there might be a longer retention period although I accept 5% is a lot to hold on to. Cheers
nod Posted August 18, 2020 Posted August 18, 2020 28 minutes ago, Water said: Hi all We are using a main contractor for our build, we are proposing a 5% retention which the contractor has accepted and they want this paid on completion. Is this normal? I thought there might be a longer retention period although I accept 5% is a lot to hold on to. Cheers No Im a contractor and leave between 3 and 5 % Payable three months after completion 1 1
the_r_sole Posted August 19, 2020 Posted August 19, 2020 3% and six months is usually my preference, it's tough to negotiate 5% and anything more than 3 ime
Ralph Posted August 19, 2020 Posted August 19, 2020 Mine is 5% retention throughout the project dropping to 2.5% for 1 year for defects.
Conor Posted August 19, 2020 Posted August 19, 2020 (edited) We're doing 5% of total contract value. 2.5% will be paid upon handover of documents, certificates etc and when architect signs it off. Remaining 2.5% will be paid after a three month defects period. We're not doing anymore than that as it's just a contract for a watertight shell. Edited August 19, 2020 by Conor
Recommended Posts
Create an account or sign in to comment
You need to be a member in order to leave a comment
Create an account
Sign up for a new account in our community. It's easy!
Register a new accountSign in
Already have an account? Sign in here.
Sign In Now