Water Posted August 18, 2020 Share Posted August 18, 2020 Hi all We are using a main contractor for our build, we are proposing a 5% retention which the contractor has accepted and they want this paid on completion. Is this normal? I thought there might be a longer retention period although I accept 5% is a lot to hold on to. Cheers Link to comment Share on other sites More sharing options...
nod Posted August 18, 2020 Share Posted August 18, 2020 28 minutes ago, Water said: Hi all We are using a main contractor for our build, we are proposing a 5% retention which the contractor has accepted and they want this paid on completion. Is this normal? I thought there might be a longer retention period although I accept 5% is a lot to hold on to. Cheers No Im a contractor and leave between 3 and 5 % Payable three months after completion 1 1 Link to comment Share on other sites More sharing options...
the_r_sole Posted August 19, 2020 Share Posted August 19, 2020 3% and six months is usually my preference, it's tough to negotiate 5% and anything more than 3 ime Link to comment Share on other sites More sharing options...
Ralph Posted August 19, 2020 Share Posted August 19, 2020 Mine is 5% retention throughout the project dropping to 2.5% for 1 year for defects. Link to comment Share on other sites More sharing options...
Conor Posted August 19, 2020 Share Posted August 19, 2020 (edited) We're doing 5% of total contract value. 2.5% will be paid upon handover of documents, certificates etc and when architect signs it off. Remaining 2.5% will be paid after a three month defects period. We're not doing anymore than that as it's just a contract for a watertight shell. Edited August 19, 2020 by Conor Link to comment Share on other sites More sharing options...
Recommended Posts
Create an account or sign in to comment
You need to be a member in order to leave a comment
Create an account
Sign up for a new account in our community. It's easy!
Register a new accountSign in
Already have an account? Sign in here.
Sign In Now