dogman Posted December 21, 2016 Author Share Posted December 21, 2016 I planned mine better than you. Had my major accidents before we demolished. thought it best i got them over with 1 Link to comment Share on other sites More sharing options...
Gone West Posted December 21, 2016 Share Posted December 21, 2016 (edited) 6 hours ago, dogman said: It was the red rhino 5000. Took all day and coped with most of the materials. Thanks, that's the one I've been looking at. Do you mind me asking what you paid for a days hire? Would it cope with 4" thick concrete. Edited December 21, 2016 by PeterStarck Link to comment Share on other sites More sharing options...
joe90 Posted December 21, 2016 Share Posted December 21, 2016 Does that fall within the remit of project manager?. Link to comment Share on other sites More sharing options...
dogman Posted December 21, 2016 Author Share Posted December 21, 2016 Peter we had the crusher digger and operator for just over 600. The machine copes with most things as long as it is clean( no mud or metal) 200mm is about the biggest. We had some extremely hard concrete that was hard tto break with a breaker and although it was slow it managed it. It does actually crush it there are two large metal plates arranged in a V that move together, it was surprisingly quiet Link to comment Share on other sites More sharing options...
dogman Posted March 8, 2017 Author Share Posted March 8, 2017 At long last we have got going again. Due to some delays with slab design we lost our ground work team. However as is the case in building industry(apparently) i was passed from one contractor to another until one wanted the work. They turned up this morning with a five tonne machine so a bit smaller than expected but the operator is really good and has made good progress pulling out the old footings and levelling the base. Only slight issue is that the expected chalk across the site as found when we dug trial pits has become subsoil in the middle of the dig ( the dark brown stuff at the edge of the chalk) It is still very firm but Building Control have asked us to refer it back the the S.E The hole is currently 1m deep at the end nearest the camera but that will be lowered by 500mm when we finish Link to comment Share on other sites More sharing options...
Recommended Posts
Create an account or sign in to comment
You need to be a member in order to leave a comment
Create an account
Sign up for a new account in our community. It's easy!
Register a new accountSign in
Already have an account? Sign in here.
Sign In Now