Jump to content

BotusBuild

Members
  • Posts

    1258
  • Joined

  • Last visited

  • Days Won

    10

Blog Entries posted by BotusBuild

  1. BotusBuild
    Don't Panic - we're not selling what we've been building.
     
    Back at the end of April (I thought it was longer ago than that - time either slowed down or we sped up, not sure which) SWMBO had just had a toe joint fused together to try to resolve a long period of pain following the critical infection she got over 3 years ago. We're pleased to say that it seems to have done the trick, and she has now rejoined me in getting the house ready for habitation.
     
    I left you all with another list to contemplate. So here it is with some brief updates:
     
    Hassle the SH1T out of the window installation company to investigate and fix the leaks (three fixed windows and a sliding door) that came to light after we did the first lot of plastering - it worked, and the window no longer leaks - yeehah!! the rest of the plastering - was all completed the rest of the mist coating and painting - one bedroom and an ensuite left more stone work - still on the list moving as much stuff into what we now call the attic (a very large room downstairs as we don't have a real attic) in order to clear all the other rooms - done Install the UFH upstairs with plywood cover - done, and manifold connected up and filled fit the bathroom - done fit the kitchen - done fit the utility and cloakroom, utility done electric 2nd fix - done and signed off rainwater soakaways - still on the list rainwater collection system - still on the list backfilling - partly done, still on the list concrete lego brick retaining wall - delivered, to be fitted Flooring - in progress Wood cladding - still on the list Air tightness test (as I write this, I think "oh, sh1t, I must get that booked in") - done and certificate issued Fit internal doors - still on the list Fit en suite - still on the list Build MY garage - still on the list A green roof system, because its on the planning application, and may be required for certificate of completion (unless someone can enlighten me as to how to avoid this, and be able to delay the installation) - still on the list  
    So, that big window, the one in the middle bottom below. First chap who came to inspect and report back left the company without doing anything, so two chaps came out (I think mainly as protection for each other from my wrath). Suffice to say they inspected thoroughly having listened to the fact that we had investigated excessively to find the point of ingress of the water. The ensuing repair entailed the whole window (glazing, individual door frames, and the outer rail frame) being removed from the hole (thank goodness for the steel beams above), a manufacturing fault being rectified, and the multiple installation faults also be repaired and then finally reinstalled correctly. A few days later to allow the massive amounts of sealant that were applied to cure, we sprayed a large amount of water at the window and gladly it seems to be OK. We now await a traditional SW'ley storm this coming winter.

     
    All the remaining plastering was completed, and not only did the mighty SWMBO mist coat all but one bedroom, she also painted all the walls bar the bedroom and the en-suite. I'm not sure she wanted to see a paint roller for a few weeks after doing that lot.
     
    As you can see in the picture above, on the right hand side, we started laying the UFH insulation and pipes and overlaying that with 6 or 9mm ply, depending on what the final floor finishing was going to be (we planned ahead 🙂 )
     
    In May, we were joined by our son who had stated clearly that he wanted to help us with fitting the kitchen. This was very welcome as there were a few heavy units to move into place, and it was fantastic to have a pair of stronger arms (than mine) around. And so with his help we managed to get to this point (left photo). Since then I've been doing all the finishing off (doors, plinths, hidden handles etc..) But the "pièce de résistance" was having the breakfast bar made from planks of the trunk of a walnut tree that we had to remove to build the house. Here it is in the right hand photo
         
     
    Having done the kitchen, focus turned to the bathroom. Here's the result

     
    We started putting down final flooring. In the breakfast bar picture above you'll see the stick down LVT that we had fitters into do, and we've done LVT click flooring in the bathroom, a bedroom, the utility and cloakroom, and one other room.
       
     
    We also had some of the backfilling done, meaning we could do away with the temporary steps upto the front door and the areas around it.
       
     
    So, still a lot to complete. This last week has seen the temporary utility removed and the permanent one installed, and a bed has arrived into the one floored bedroom.
     
     
    Selling up:
    We've sold our "holiday home", and our primary residence is on the market (anyone want a four bed detached with double garage in the Reading area?).
     
    Next week we begin the process of moving into a building site, albeit one with a few luxuries (like the ability to cook a full roast dinner without the electricity tripping, and have the option for a bath!)
     
    No new list this time around 🙂 
  2. BotusBuild

    We moved in, the left
    The end of our last blog entry ended thus:
    Dare I add a what's next list 🙂 ?
     
    Well, here goes ....
    Plastering finished in the open plan area this coming week (by others) Remainder of stone cladding arrives and work begins to get the most inaccessible (high) parts put up before the scaffold gets taken away - this means cladding two 7m x 2m wide walls Plumbing pipework ready for ASHP installation Gabion basket and pad for ASHP to be installed on Mist coat and first coat on plaster (SWMBO is at the ready) Begin fitting upstairs UFH Front door being fitted (January) by others Take 3-4 days off for Xmas ASHP installation (January) by others, that will allow for hot water and the downstairs UFH to be available ... Fit a temporary bathroom ... Fit out utility room as temp kitchen ... ... and this is why - Move out of static van for the month of February (rules is rules!) and decamp to the house  
    The title of the blog may be a little misleading - let me assure you that living in the house for a short while was great. We liked it so much we stayed for 5 weeks instead of the 4 that we had to, as it was warmer than the static van we would be going back to. If you recall the beginning of March was a little frigid, even down here in the South West (the van sits in a valley that collects the cool air very well and so is often 3 to 4 degrees (K and C) cooler than the surrounding area.
     
    We can recommend such a short stay in the house before getting stuck into the final push on the interior. It has definitely helped in providing an order of works for us in the coming months before we finally move in properly by highlighting things that may have been overlooked or forgotten in the general melee of all the other things that have been taking place over the previous 6 months.
     
    So, back to that list:
    I've commented on this in a post somewhere else, but in coloured text this is what happened
    Plastering finished in the open plan area this coming week (by others) This did happen in October Remainder of stone cladding arrives and work begins to get the most inaccessible (high) parts put up before the scaffold gets taken away - this means cladding two 7m x 2m wide walls      This also got done before the scaffold was removed in early January - thankfully the temperatures and the rain played ball Plumbing pipework ready for ASHP installation    Sorted Gabion basket and pad for ASHP to be installed on    Filled and Pad poured Mist coat and first coat on plaster (SWMBO is at the ready)    What a job - so much brighter Begin fitting upstairs UFH    No, no, no, what were you thinking (but more to come on this below) Front door being fitted (January) by others      All done and glad I did not have to lift it up the stairs Take 3-4 days off for Xmas    OH, YES and very much enjoyed ASHP installation (January) by others, that will allow for hot water and the downstairs UFH to be available ...  All done and worked very well, hence the extra weeks stay Fit a temporary bathroom ...  The temporary shower was so good we were going to keep it but then changed design of the bathroom - one of the things from living in the house Fit out utility room as temp kitchen ...  This is still in place and being used as part of our welfare unit on site  
    Here are some pictures of the above work

     
     
    And so, we moved in just at the end of January and lived in the house for 5 weeks. During this time we experienced what the house was going to offer us, and, apart from the dust, we were only too happy to be able to stay an extra week when the cold snap came along at the beginning of March and we could delay our return to the static van (AKA tin box). This in spite of a temporary bathroom, kitchen and bedroom facilities. The cat, however, thought differently about the dust, but seemed generally happy with the quality of work
     

     
    While we were in the house during March work carried on with fitting the remaining plasterboard ready for the plasterers to come along in March. This was pretty much all we did - and we're very glad to only have a few more sheets plus some waterproof backerboard to fit. No pictures of this as it is really not that inspiring 🙂 
     
    Going into March we created YAL (Yet Another List) 🙂 We've all been there - the ever changing & expanding, rarely static or reducing list. Anyone got onto the LOL yet (the List Of Lists)?
     
    This included, in no particular order (that came later),
    Hassle the SH1T out of the window installation company to investigate and fix the leaks (three fixed windows and a sliding door) that came to light after we did the first lot of plastering the rest of the plastering, the rest of the mist coating and painting, more stone work, moving as much stuff into what we now call the attic (a very large room downstairs as we don't have a real attic) in order to clear all the other rooms, Install the UFH upstairs with plywood cover fit the bathroom, fit the kitchen, fit the utility and cloakroom, electric 2nd fix rainwater soakaways rainwater collection system backfilling concrete lego brick retaining wall Flooring Wood cladding Air tightness test (as I write this, I think "oh, sh1t, I must get that booked in") Fit internal doors Fit en suite Build MY garage A green roof system, because its on the planning application, and may be required for certificate of completion (unless someone can enlighten me as to how to avoid this, and be able to delay the installation)  
    We are focusing on the internal works in order that we can move in, although not necessarily completed on the outside, sometime in the summer months.
     
    The first 3 or 4 items have progressed well:
        <----- This is the "attic" with a garage floor paint that remains a little tacky even 3 weeks later, but it'll eventually get covered with a "proper" floor at some point in the future
     
    Despite the window leaks not being fixed yet, we have ploughed on and had all the other plastering done. The window installation company knows the situation and is fully aware that we expect them to repair any further damage caused by the water ingress. (I'll not respond to any comments on this point for my own sanity 🙂 )
     
    Flooring has been ordered, and 2nd fix electrics loosely scheduled in, as well as some of the backfilling, and prepping for the garage foundation.
     
    The UFH has started where the floor is available, and in order to be able to install the kitchen (the picture below is not where the kitchen will be - I don't appear to have photoed that - strange.

     
    Those who have been reading my blogs will recall from an earlier entry the terrible story of SWMBO's foot. Well today (Apr29) as I write this on a hotel terrace in Oxford she is recovering from her sixth operation, this time a toe fusion, that will take her out of the game for at least 6 weeks, 2 of which she has to spend with the offending appendage raised above her heart for 23 out of 24 hours every day. She won't even be able to climb the walls with frustration. So yours truly will likely be happy to be dispatched to the house each day to GO AND DO SOME WORK!! 🤣
     
    Until next time, which I hope will be the "We've moved in" entry.
     

  3. BotusBuild

    Progress speeds up
    So a quick recap - back in December 2023, what may be my last ever employer decided to ask me to leave. I had mixed feelings about this. I took several weeks to think about next steps and actually get around to writing a father of the bride speech which I'd been putting off. After the wedding in March (a great day and a great speech!) I started to look more seriously for a new job, but being the wrong side of 60 now, the IT industry is not a good place to be looking especially when so many other people have been let go as well.
     
    Coming up to the end of May, we sat down and took some tough decisions; we bought a static van on a site about 3 miles from the plot, I stopped looking for a new job, SWMBO did an internal job transfer, we rented out our current house (instead of our original plan to sell up) to three newly qualified doctors (our niece and two others on their first F1 rotations in our local hospital so that worked out well), and we spent 6 weeks decluttering, and moved down SE Cornwall (Kernow) at the end of July.
     
    In the last blog entry I ended with a list:
     
    Finish ventilation system
    Finish insulating the GWW
    Finish backfilling
    Electrics
    Floors
    Walls
    ASHP and HWC
    Kitchen
    Bathrooms
    The remaining plumbing
    Outer wall coverings
     
    This is how it looks today
     
    Finish ventilation system
    Finish insulating the GWW (Great West Wall)
    Finish backfilling (on the back burner)
    Electrics (first fix)
    Floors (now on the back burner)
    Walls (En suite partition walls to be done)
    ASHP and HWC (being done in January)
    Kitchen (planned for January or February)
    Bathrooms (temporary loo and basin installed, cold water only, temp bathroom planned for January)
    The remaining plumbing
    Outer wall coverings (rendering done, stone cladding starting next week)
     
    What I missed off the list, and has taken most of our time:
    Sound insulation (R35 rockwool and resilient bars) Plasterboarding  
    So a few photos are required I think:
    MVHR unit in place (since removed as plant room walls have been put in and waiting to be plastered inside)

    Ventilation distribution boxes and pipes fitted:

    Plaster board arrived (in May):

    My cold water manifold has pipes attached for the first time (one now being used for the temporary toilet and basin), no picture of it but just to the right is the hot water equivalent:

    We powered up the sewage treatment plant for the first time (nearly 4 years after it was first installed!):

    We started plasterboarding, first a large room into which we moved all our stuff that was in storage so saving a hefty wedge per month on storage fees, and then the much larger and more complex open living area:

    We took some time off in early October and went sailing for a week, and when we got back some kind fellows had installed some scaffold (first time on this build), and in the following few weeks we had the renderers in thanks to the Kernow weather gods:

    Meanwhile back inside, we finished plasterboarding the large living area, and during this last week the plastering started (kitchen area first!). We set off a couple of insect smoke bombs as we had a cluster fly infestation and wanted rid before plastering started 🙂 :

     
    Dare I add a what's next list 🙂 ?
     
    Well, here goes ....
    Plastering finished in the open plan area this coming week (by others) Remainder of stone cladding arrives and work begins to get the most inaccessible (high) parts put up before the scaffold gets taken away - this means cladding two 7m x 2m wide walls Plumbing pipework ready for ASHP installation Gabion basket and pad for ASHP to be installed on Mist coat and first coat on plaster (SWMBO is at the ready) Begin fitting upstairs UFH Front door being fitted (January) by others Take 3-4 days off for Xmas ASHP installation (January) by others, that will allow for hot water and the downstairs UFH to be available ... Fit a temporary bathroom ... Fit out utility room as temp kitchen ... ... and this is why - Move out of static van for the month of February (rules is rules!) and decamp to the house  
    Well, I'll let you know how it all goes 🙂
  4. BotusBuild

    Return of SWMBO
    Apart from the “picture from the mound” timelapse blog entry, there’s not been much of an update since mid September 2022. So, get your preferred hot drink (maybe a SteamyTea), and settle back for the next instalment.
     
    Where were we? SWMBO was still in recovery from her foot infection - you remember? The one that might have killed her? The second floor ICF had been installed, and the concrete poured. I’m still going to spare you any pictures of the foot, but here is a concrete pump truck instead.
                          
     
    So, next on the list - a roof please. But before that, the final steel beams had to be installed [FX - thumbs twiddling in the foreground and whistling can be heard as we wait for the steelworker once again], but it wasn’t too long a wait, and by mid October 2022 we had the beams installed.
                                 
     
    In late October and early November I set to work with the ground worker to do some backfilling, and of course on the days I chose to have the digger onsite, Cornwall delivered some of its traditional autumnal weather so any attempt to properly compact anything was nigh on futile.
                                       
     
    In the meantime, more joists, endless sheets of T&G OSB, vapour barrier, 160mm deep sheets of PIR insulation, and some of the biggest screws are readied for ordering. The joists arrived in and in early December I had my supervisor and client (SWMBO) back on site 🙂, and she has graduated to being a mountain goat.
    She now refers to the site as her "happy place", even though we have a strong suspicion that the infection was started by a visit to a local beach.
               
     
    By mid April, with help from some now local family members, we’d installed the roof joists, and in mid May we were ready to start boardin’, vapour barrierin’, and insulatin’. The GRP was installed in mid July 2022 (by others).
          
     
    I’d also been readying the Great West Wall (GWW) to have the triple glazed sliding doors and windows installed (by others), and this took place in mid August, just in time for my significant birthday. There were some fitting errors, but I have to take my hat off to the installation company, they have been back to rectify their work, and have supported me with making the suppliers change some of the sliding door fittings as they were just not correct despite their protestations.

     
    In October, we had the mains electric and meter moved from their temporary location to inside the house. Over the ensuing autumn and winter months, we’ve been installing some of the final internal partition walls, running water pipes, installing more insulation around the GWW windows, and recently started on the ventilation ducting following some core drilling being undertaken (Tip: always ask for a hole to be drilled that is about 10mm bigger than you need - expanding foam is your friend. I donate my scar tissue to you all 😂)
     
          
     
    In December, I got made redundant. No worries, this may actually be a blessing in disguise.
     
    Next up on the list:
    Finish ventilation system
    Finish insulating the GWW
    Finish backfilling
    Electrics
    Floors
    Walls
    ASHP and HWC
    Kitchen
    Bathrooms
    The remaining plumbing
    Outer wall coverings
     
    But, in the meantime, we have the small matter of our daughter’s wedding. DOES SHE NOT KNOW WE’RE TRYING TO BUILD A HOUSE!?
     
    (Time to end: 2 years 🙂 )
  5. BotusBuild

    Picture from the mound
    Since starting this build we've had a handy mound of "spoil" from which I have been taking regular photos from the same(ish) spot to remind me of progress during the "down" days which we self builders all suffer from time to time. I thought I'd share this with you. It starts in May 2021, when the major groundworks had been underway for a few weeks and goes up until April this year - about 2 years.
     
    First a picture of the mound of spoil for reference:

     
    and now the "timelapse":





     
    Since that last picture we've been putting on the warm roof structure, so any further photos from this vantage point don't show much sign of progress. so until something significant happens in August this view won't change much
  6. BotusBuild
    We left you with a poured slab and we were chomping at the bit to get the ground floor Nudura walls up before the end of the year. Well, I am glad to report we got there - almost ? 
     
    After getting the slab done, I figured I'd get ahead a bit and it would be a good idea to talk to someone about the waterproofing we would have to put on the outside the walls before we started backfilling. To cut a long story short
    using waterproof concrete in walls such as these is a complete non-starter, so Type-B waterproofing cannot be used. Visqueen's R400 Radon barrier is not an effective waterproofing method and so we now face having to use a Type A and a Type C waterproofing method - basically this will mean for us a waterproof screed being added to the floor with channel ducting where the walls meet the floor and the "egg-crate" plastic material across the screed and up the inside of the walls. That should eat into our contingency ? ? ?
     
      But also it meant a dash to get some waterproof slurry to paint round where the Nudura blocks would be laid the following morning and mixing and painting it on under floodlights (it's the dark grey stuff in the picture to the right). Oh what fun!!
     
     
    But, the following day we were up early to welcome out walls, the bracing and two fine chaps (Louie and Harry) from The Fell Partnership who would be helping us Day 1 to get the first row in place. We then scurried around unloading things off trailers and flat beds, and installing the waterbar between those pieces of upright rebar. By 10am we were ready to go.
     
    By about 2pm we had most of the first row in and part of the second row (see below). If it hadn't been for some non-standard corners in the design, we would probably have been at Row 3, but that's what you get for following a design religiously ✝️
     
          
     
    (FYI - the T-corner is all to do with the design - don't ask yet)
     
    On the second day we were left to our own devices, I had to make a dash to collect some extra Nudura parts and some waterproofing equipment (due to the direction our waterproofing system now had to take) so we made a later start but still we were very pleased to get up to 4 rows installed.
    Day 3 we were ready to begin installing all the bracing system, and after hitting her head SWMBO was made to wear the Christmas present from her children.
     
       
     
    and on Day 4 it inevitably rained in Cornwall ? , but before our help arrived again we had managed to just squeeze a block on to Row 6 (the final row before the first pour of concrete)
     
    After the help on Day 4, we continued to finish things off on Day 5 by constructing part of an internal load bearing wall, and a wall with the only window opening at this level which will be for the family bathroom. FYI - the rest of that side of the house will consist mainly of windows into bedrooms plus some extra small sections of walling (to be determined)
     

     
     Where we were not able to complete things before the pour happened (time didn't allow) was where the internal wall meets the external wall and there are two doorways to construct (this is why I said we almost made it). I will have to do these in the New Year, mixing and pouring the concrete by hand (just under 1 cubic m) so that'll burn off the Christmas pudding ?
     
    A week later (during which we had some more high winds) I came back down to finalise a few bits (like lack of scaffold planks and bracing in some places) to be greeted by a snaky ?  wall.
     
     
     
     
     
    so that was all straightened up, the rest of the bracing fitted, and the Nudura joist hangers inserted. 
     
    (Between straightening and the pour we had Storm Barra, but my remedial work held up nicely)
     
     
     
     
     
     
     
     
     
     
     
     
     
    I won't bore you with pictures of hunky men doing manly stuff with concrete pumps etc. but suffice to say it all went very well, with no leaks or blow outs so "he who shall not be named from Channel 4" would have been very disappointed if he was allowed onsite.
     
    And so, last weekend (after a midweek pour in the remnants of Storm Barra) I was able to deconstruct the bracing and we are now the proud owners of some freestanding, high-wind-proof walls.
     

     
     
     
     
     
     
     
     
     
     
     
     
     
     
     
     
     
     
     
     
    Really happy at the attention to detail that Louie and Harry paid to ensuring the walls were straight and true before the pour began - right up my street.
     
    So now we have a tidyish site again (for a short while) ready for steels installation in the New Year. We have to finish off the internal wall, then waterproof and backfill outside, and install joists and flooring before we can continue with building the upper floor walls. We're hoping that by middle of next year we can start on those upper floor walls.
     
    So until 2022, and the inevitable next lockdown, I wish you all a very Merry Christmas ? and a Happy New Year ?
  7. BotusBuild

    Blog - Upper Floor Wall
    I’ve been meaning to  provide an update on the progress of this build for a while, and I find myself with a spare couple of work hours 🙂
     
    At the end of December 2021, we left you with 95% of the lower floor walls complete, and looking forward to getting the first set of steels installed. Of course, last winter’s weather, including some furious storms, had a thing or two to say about that, which included me going down at short notice and staying in the local Travelodge (other chains are available) ready for the inevitable turmoil that would greet me after the 90mph storm. It turned out not to be too bad, with only limited damage to the caravan awning, and some items moved around the plot.
     
    In early March we decided to make our first visit since that storm, and were greeted by a lovely surprise - the first set of steels were in place. I am still amazed at the lack of communication from some building industry people, but as I am told by the locals “its Cornwall”.

     
    It was time to order the next set of materials to get to the upper floor stage, which we wanted to get done by the end  of June/mid July  (it’s always good to have a target even though you won’t meet it 🙂 ). This included joists, flooring, the next set of Nudura and wood to create partition walls.
     
    In the meantime, we got started with applying the over-specced, and over-engineeed waterproofing scheme that our “professional” had stated we needed after deciding that their first spec was not up to the mustard. 
      
     
    Can I just say at this point - there is an awful lot of discrepancy with what we self-builders are being told is required, and even after asking a lot of dumb questions, it’s almost impossible to get a straight and consistent answer, even from the same person sometimes. This is where having some common sense mixed with an engineering/technical background does come in extremely handy. Suffice it to say, that I have ditched some of the “uprated” waterproofing spec on the basis that logically it was overkill for the build type and soil conditions. Some will question “what about building warranty/guarantee” which is fair, but on the basis that we are not intending to sell and to live there for many decades to come, we are prepared to take what is a very small risk on this.
     
    Come early May, and with careful planning and scheduling I had 3 major deliveries lined up for the same day. The careful scheduling went South of course, and everything turned up within an hour of each other. 3.5 non-stop hours of handballing Nudura ICF, webjoists and floorboards, a 150kg, 6m long glulam beam (more of which later) and enough wood to build an ark (at least that what is seemed like at the time), I was a gibbering wreck, only fit to nurse a mug of tea and a heavily bruised thigh (did I mention a glulam beam?).

     
    For 5 weeks between the end of May and the beginning of July, supporting partition walls were created and installed, joists hangers and joists put up and some flooring. This work also included the installation of that 6m glulam beam which was a one day job on its own. 
                
     
    So finally, at the beginning of July we were ready to miss our end of June/mid July target date but roped in some family members to help get us cracking on doing the second floor Nudura walling (the pic of the family is from July 10).
       . 
     
    We were still on for an end of July concrete pour, until …… I would insert some pictures, but cannot take responsibility for any impact they have on the squeamish and faint of heart.
     
    Neither we, or any of the medical staff who have been involved with the treatment, can put our finger on where the infection came from but shortly after that July 10th picture of the family, the wife was struck down with Cellulitis that turned into necrotising fasciitis, which could have led to sepsis. If you read the link, you will realise that building a house suddenly becomes the least important thing on your mind. However, I am happy to report that the first operation saved her foot, and quite possibly her life, and the subsequent 3 operations to clean and repair the foot have been traumatic and very worrying. She is now on the mend but ….. I AM DOWN A LABOURER.
     
    Thanks to the NHS, however, and the enforced hospitalisations, and visiting being taken care of by other family and friends, the wife was able to send me to Cornwall (rather than Coventry) and I managed to get the walls finished and the concrete pour took place on September 9th.
     
     
    Now to wait for the second set of steels to go in, and I can order the roof joists. We might be semi weathertight for the winger 🙂

  8. BotusBuild
    ... and so, in mid July, we had just a few things to do before we could pour concrete. <CUT, CUT, CUT> That's wrong again, you forgot the three spur walls and you've order some wrong parts. Go again, from the top
     
    ... and so, in mid July, we had an unknown quantity of things to do before we could pour concrete ? 
     
    But before all of that happened, as a family we were all brought together for one of the inevitable things about life - every one must some day some to an end, this time it was my Mother-in-Law, a real matriarch, in the best way. After having gone through several operations and rounds of chemotherapy, her cancer got to the brain, and all other plans went on hold. We were able to get back to site shortly after she passed away in late August to continue. She did get to visit the site, and was so pleased with where we going to be living.
     
    So, first on the list was the starter bars for the retaining walls with this amazing double row being installed by my erstwhile wife
      
     
    and with all those complete, it was onto the underfloor heating loops
     

     
    and then the bolts that will locate a couple of steel columns
     

     
    Now, the eagle eyed amongst you will recognise those as M16 bolts (well done to all the bolt nerds), and when a steel fabricator came along, having seen the plans, he fortunately pointed out that they should be M20 bolts. So, if anyone is in need of some 300mm M16 bolts and fittings, tap me up for a deal ?
     
    And, so we thought we were ready for a bunch of concrete, until we visited our friendly ICF supplier to talk about the walls and realised I had omitted the shoring for three extra pieces of wall that needed to be tied to the main slab. So after a stupidly self-imposed extra delay, we managed to get everything in place to have some jolly super chaps (Tom, Phil and Ross) to bring along a concrete pump and other wonderful paraphernalia to pour, tamp and float our insulated slab foundation.
     
        . 
     
    We can almost smell the completion of the house ?  ?   ?   ?
  9. BotusBuild
    As I wrote the last blog entry, Scotland ???????  were beating England ???????  in the Calcutta Cup and we were all wondering when Lockdown 3.0 would end - we're nearly there apparently. We were also
    sorting out re-mortgaging to a lower fixed interest rate, - DONE, and we are paying about £200 a month less than before!! choosing insulated raft supplier - DONE, we went with Jackodur Atlas system determining steel re-inforcement requirements for the foundations - DONE and for the most part installed ?  
    So, after more enforced delays, it was back onsite in May with the groundworker to get the stone and blinding sand in place ready for the insulated foundation system to be installed.
     
     
    This involved about 80 tonnes of stone and 15 tonnes of sand being delivered - we have about 5 tonnes of each left over, fo which I have no doubt we'll find a use ?
    (and before anyone asks, yes, it was rolled with an appropriately large machine at the appropriate time).
     
    This all added to a sense of well being - we were in the fresh air, doing something beneficial (for us at least) and we were finally coming UP, out of the ground! Break out the party poppers ?
     
    Ahhhhh - the insulated raft choice - it started out so simply having read the various comments in the forum, and Kore Systems it was going to be. I did then visit the Swindon self build centre and saw Jackon's stand and what seemed like a good system. Our SE had specified a 250mm thick slab throughout - no thin bits and thick bits - the Jackon Jackodur Atlas system seemed to fit the bill - a few calls, swap some drawings, commitment to delivery timescales, but with the flexibility I needed, a person onsite on day 1 to help. Quite straightforward. I won't go into detail, but let's just says Kore Systems approach was "our way or no way".
     
    With a delivery to a local yard by articulated lorry and then our groundworker getting it on his trailer to go the last mile or so, we then proceeded to handball it all off the trailer. From delivery to the yard at 8:30am onto the ground by 1:30pm. The handballing was done by Mrs BB and I in about 4 hours.
     

     
    The insulation comes with a nice waterproof holder for the instructions and the plan to follow - think "a jigsaw puzzle with the special parts all numbered and shown on a drawing". All the other parts are standard, but if you work from pallet 1 through pallet 2 to pallet N, you can't go far wrong. The very nice man from Jackon arrived just after we had stopped for lunch and we began with laying the first two sides and three corners, and then Mrs BB and I carried on the following few days to lay the rest. We did come across one part while the man was onsite which had not been cut properly in the German factory - you should have seen the delight on his face when he realised he was going to be able to send a snottogram ?.   It was easily sorted, but if he had not been onsite I can see that it could have caused a big time day - even with being onsite it took about 45 minutes for him to work out what had gone wrong.
     
    Day 1:                  Day 2:    
     
    Day 3:          Day 4.   :
     
    Next in was the combined Radon barrier/DPM, the first layer of reinforcing mesh, including a double-layer strip (see left hand photo below) around the 3 sides that will be retaining walls. During the laying of the re-inforcing mesh we suffered our first big accident when one of them caught Mrs BB on the shin and we ended up at the local A&E for her to have a few stitches applied - she is still talking to me ? 
    Over the last few weeks we have managed to get the time to put in the second layer of mesh, with the help of a good friend and one of our neighbours-to-be.
     
                           
     
    We're pretty close to pouring concrete, but just have the starter bars for the external walls and one internal wall to put in place, and two sets of bolts that will eventually have two steel columns attached to them.
     
    Oh, and well done Italy ??.  (he said grudgingly)
     
  10. BotusBuild
    I left the site in November 2019 with the two trees felled, and we had decided that the design and approved planning application were not quote to our liking, so we took the decision to put in a variation of condition which went in for consideration in December 2019?. 
    Little did we know what this would mean to progress; as we are building very much at the DIY end of the self build spectrum, and not living close to site, by the time we had the go-ahead we were in Lockdown 1.0 and unable to get to site until July 2020.
    But before that, I'd already started the applications to install water and electricity, so in the first few months of 2020, I had lined up the water installation and had most of the things in place for the electricity connection. The water was due to go in at the end of March, and as you can expect, this was postponed. However, by keeping in touch with my local ground worker, the two neighbours and hte water and electricity folks, we were able to get things lined up to get both connected in the same week in July. Also, our local ground worker convinced us to push an access straight from the lane down to where we were building - I recommend listening to the experienced ?

     
    As well as getting things in place for our return to site, we took the opportunity to source a caravan that we could put onsite in order to make it easier to be able to travel straight to site and not have to rely on being able to use the local TravelLodge - little did we know how useful that was going to be.
     

     
    So, in June and early July a couple of short preparatory trips
    moving the caravan to site and setting up, connecting the water standing pipe, installing meter boxes, then in July - October, we made several trips to
    clear and burn vegetation, feed and water the water and electricity teams, have meals with our "to be" neighbours, take delivery of a septic tank dig a lot of holes lay drainage pipes fit a septic tank fill holes with stone fill holes with spoil and finally start digging a very large foundation hole for the insulated raft foundation
     


    20201012_094541.mp4  
    And then we hit Lockdown 2.0 - another month of enforced "stay away from site", then in early December, I returned for two short visits to finish off concreting in the drainage pipes that will end up feeding through the insulated raft.
     

     
    And so we find ourselves in Lockdown 3.0 during which
    we are sorting out re-mortgaging to a lower fixed interest rate, which we always knew we would do, but we had hoped to be a lot further along ?  choosing insulated raft supplier determining steel re-inforcement requirements and, due to delays, considering moving slightly along the self build spectrum towards more use of subcontractors ?  
    And so as I write this with the Calcutta Cup on in the background wondering how long it will be before the travel restrictions are lifted, but planning for a late March trip West.
     
     
     
  11. BotusBuild
    Having eventually found our plot in episode one, and worked out where the plans had the house to be built we found that a walnut tree had to make way. A second tree, a horse chestnut was also badly diseases with a split trunk and as we didn't want that falling on the newly built house in the Autumn of 2019 (or Fall for our American cousins as I am writing this on Thanksgiving Day 2020) I headed off with equipment in hand to so some tree felling.
    First some photos of entrance to site (now wider!)

     
    and then some of the felling

     
    and of course the obligatory fire, and a beautiful sunset as my reward at the end of the first day




  12. BotusBuild
    So, I have told this story to quite a few family members, friends and colleagues over the last few years, and thought I will record it here so that other new members might learn about the patience and surprises that can occur in this phase of the self build adventure ⛺ 
     
    It all started when I was 14. I blame my stepfather. He made me dig ♠️  foundations by hand ?️   OK, it was only for an extension, but they didn't tell me about the concrete encased foul and storm water drains  we would find. Digging to depths of 10ft by hand should have left severe scars  to put me off this self build lark for life. But, hey, I got a new stereo ? for all of my hard graft [For you youngsters, a stereo was the way we played music ?  back in the day].
     
    Anyway, many years later, the wife and I are in the Lake District and see a barn ripe for conversion, and the timing must have been right - you know, the stars in alignment ⭐  ⭐, and the phase of the moon?  augered well, or some other psychological/astronomical claptrap - and we both said "time to get out of the South East". Well, that was about 5 years ago, and we are still in the South East. Lesson 1 for all new south builders - Tip 1: patience my friends!!
     
    Tip 2 - unless you are lucky enough to have been handed a plot of land on which to build, start searching where the wife would like to start, followed closely by Tip 3: using subtle hints and prods in order to expand or direct the search appropriately, always with the mantra (Tip 4) "we need some money left over to build the damn thing!" (Note: some forum members may say that doing that doesn't make for enough of an adventure ? ), we started in the North Devon area, a place where my wife had spent time holidaying as a child with her family, which is as good a reason as any to choose a starting point. We (I) trawled the usual sites for plots (estate agents, land agents, auction sites etc.), we trawled the lanes and byways of North Devon on a number of visits, propping up the local hospitality businesses along the way, I got so bored at one point I went trawling (OK, sea fishing from a trawler ?️  but go with it, for the sake of the story!).
    Having searched for about 18 months and found nothing, I expanded the search outside N Devon and we started seeing results in East Devon and on the outskirts of Exmoor and Dartmoor. 6 months later and we were looking at plots in the South Hams (S Devon).
    We saw scrub covered plots, plots with dense woodland ?  ? , people looking for a swift profit by selling their back gardens (soon avoided forever after seeing two such postage stamps ? ), old industrial sites, then we went to see two modern(ish) barn conversions and decided to make an offer (below asking price ? of course!). Herein lies a conundrum I have never quite got my head around - asking price £200,000, Offer £165,000, offer refused. OK Offer £175,000. Offer refused. I'll leave the offer there if you change you mind. 2 months later same property on the market for £170,000!!! Offer £150,000, then £160,000, both refused. 2 months later same property on market for £150,000 and marked as SOLD!! The only reason I can fathom is that they wanted someone particular to buy it.
    After I had calmed down, 6 months later (yes I had been really annoyed) we renewed our search and found an abandoned ex-SW Water above ground reservoir with FPP and amazing views. Problem, it was above our plot buying budget (refer to Tip 4) and the seller refused to move an inch on the price.
    So, the searches started again. This time, the wife was now quite pliable about the distance from where we currently live and the areas we should look. This is were I have to admit that I had seen a plot with FPP and plans I liked the look of probably about 9 months before the fluidly priced barn fiasco. And, the distance was about 1 mile less than to the old reservoir. So, off I trotted ?‍♂️ one day.....to CORNWALL.
    Another visit with the wife, a coffee ☕  with the sellers (neighbours to be) to discuss the plans that had been approved and a re-mortgage later, and we became the proud owners of about 1/2 acre of Cornwall just on the edge of an AONB.
    Just a word of warning - this "plot" did not have its own title deed, and it has taken nearly 18 months for the Land Registry to finalise the new title for us. This in itself has probably given me more grey hair so far than any other aspect of the build so far.
×
×
  • Create New...