Quick Progress Update
A quick photo update, I will do proper blog posts over the next few days......
The ground works were started back in August, however there was a long delay with the timber frame being manufactured (partly due the the first floor layout changes), which meant that the TF kit wasn't delivered until November the 18th.
Last week the house was made wind and watertight.
This week the ground floor UFH was laid and the screed poured.
We are hoping that the steel for the cantilevered stair will be fabricated and installed over the next 2 weeks.